Cabinet, Wednesday 26 June 2019

Urgent Structural Works-Brewster House and Malting House

Agreed Executive 5 papers

Cabinet agreed this item on Wednesday 26 June 2019. Below is the council's own wording, with the papers it was decided on.

Item6.2

Resolved

The Recommendations were amended and agreed. DECISION 1. To note that officers will explore the voluntary buy-back of leasehold properties in the two blocks, under the existing budgeted borough-wide buy-back programme, with potential costs estimated at c .£ 9.6m. 2. To agree to the introduction of two additional borough-wide leasehold service charge payment options as set out in sections 9.5 - 9.7 of the report. 3. To defer agreement of the following three recommendations subject to further discussion – with final decisions to be taken by Individual Mayoral Decision if required: a. To agree that capital resources of £8,083,081 are made available within the five year HRA Capital Programme to fund the works (Option 1) and the services associated with delivering the works, and agree to adjust the five year programme accordingly. b. Agree to the award of the works contract to Wates in the sum of £6,276,605.50. Wates has been procured via the Council’s Better Neighbourhoods Works Framework. c. Agree to formally consult leaseholders and to recharge them for their portion of the cost of the works. Action by: CORPORATE DIRECTOR, PLACE (A. SUTCLIFFE) (Interim Divisional Director, Housing and Regeneration (M. Baigent)
Word for word from the decision Tower Hamlets published for this meeting. Source: democracy.towerhamlets.gov.uk

Follow this further

Built from Tower Hamlets's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Wilde Carter Clack Barley Mow Final ReportAppendix 1 918 KB Copy on its way
PDF
CURTINS RISK ASSESSMENT May 19Appendix 2 958 KB Copy on its way
PDF
Third Party R and R 1 May 2019Appendix 4 233 KB Copy on its way
PDF
Brewster and Malting programmeAppendix 5 212 KB Copy on its way
PDF
Urgent Structural Works-Brewster House and Malting HouseReport 424 KB Copy on its way

At this meeting

Whole meeting

More from Tower Hamlets Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 6th Floor of Town Hall LettingDECISION: 1. Grant permission for a 15 years lease to London Air Ambulance 2. To delegate authority to the Corporate ... Agreed Open
23 Sep 2026 Cressy PlaceDECISION: 1. Delegate authority to the Corporate Director of Housing & Regeneration in conjunction with the mayor to ... Agreed Open
23 Sep 2026 Caxton GroveDECISION: 1. Delegate authority to the Corporate Director of Housing & Regeneration in conjunction with the mayor to ... Agreed Open
23 Sep 2026 Brunton Wharf housing schemeDECISION: 1. Delegate authority to the Corporate Director of Housing & Regeneration in consultation with the Mayor to... Agreed Open
23 Sep 2026 Copenhagen Place SchemeDECISION: 1. Delegate authority to the Corporate Director of Housing & Regeneration in consultation with the Mayor to... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies