Cabinet, Wednesday 23 September 2026

Brunton Wharf housing scheme

Agreed Executive 4 papers

AI summaryTower Hamlets Cabinet delegates authority to override rights of light and settle related claims so the 9-storey Brunton Wharf housing block with 32 affordable homes can proceed.

AI summaryIn plain English

Written from the decision wording; the report is not read yetPDF Pro
OutcomeAgreedTo appropriate land and override rights of light
MoneySettlement figures in exempt appendix
What happens nextNot stated
Who it affects2 buildings, 1 school, 4 street or road propertiesIdentified as affected by rights of light analysis

What was decided

Authority delegated to the Corporate Director of Housing and Regeneration, in consultation with the Mayor, to appropriate the Land for planning purposes under section 122 of the Local Government Act 1972 and to use powers under sections 203 and 206 of the Housing and Planning Act 2016 to override rights of light of neighbouring properties infringed by the redevelopment.

Authority delegated to the Corporate Director of Housing and Regeneration, in consultation with the Mayor, to agree the settlement of rights of light claims with any affected party, together with any associated fees.

Cabinet noted that the cost of the proposed settlement payments and associated fees will be met from the capital budget for the Brunton Wharf site development.

Why

The decisions are sought to enable construction on the Land of a new 9-storey residential housing block, which will deliver 32 new affordable homes.

A Rights of Light Consultant identified that 2 buildings, 1 school and 4 street or road properties may suffer an adverse impact to light, with dwellings affected to varying degrees, and provided a potential settlement budget for releasing those rights.

Because of a high risk of an injunction to prevent the scheme being delivered and the associated settlement costs, the Council needs to use its powers to mitigate these risks.

What happens next

The Corporate Director of Housing and Regeneration will progress the appropriation of the Land, the rights of light settlements and any related property documentation, supported by the Director of Governance and Legal Services.

Options considered

  • Rejected: Do nothing: do not appropriate the Land and do not use statutory powers to override rights of light. Affected private property owners could seek an injunction that stops or significantly delays the project and the 32 new affordable homes

Implications

  • Legal: The Council will exercise its power under section 122 of the Local Government Act 1972 to appropriate the Land for planning purposes, and sections 203 and 206 of the Housing and Planning Act 2016 to override neighbouring rights of light.
  • Financial: Rights of light compensation payments and associated fees will be funded from the existing capital budget for the Brunton Wharf site development; full settlement budgets are in the exempt appendix.
  • Risk: Failure to use the override powers is identified as carrying a high risk of injunction proceedings that could halt or significantly delay delivery of the scheme.

Who and where

  • Owners and occupiers of 2 surrounding buildings identified as potentially affected by loss of light
  • 1 school identified as potentially affected by loss of light
  • 4 street or road properties identified as potentially affected by loss of light
  • Future residents of the 32 new affordable homes to be delivered at Brunton Wharf

Plain English for the jargon

  • Appropriation for planning purposes: Changing the use of council-owned land to a planning purpose under section 122 of the Local Government Act 1972.
  • Rights of light: A property owner's right to receive a reasonable amount of natural light through a defined aperture, which can be infringed by nearby building works.
  • Sections 203 and 206, Housing and Planning Act 2016: Statutory powers that allow a council, in defined circumstances, to override private rights such as rights of light to enable housing development.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6.4

Resolved

DECISION: 1. Delegate authority to the Corporate Director of Housing & Regeneration in consultation with the Mayor to appropriate the Land for planning purposes in accordance with section 122 Local Government Act 1972 and subsequent use of the Council’s powers under s203 s206 of the Housing & Planning Act 2016 to override rights to light of neighbouring properties that would be infringed by the redevelopment the Land. 2. Delegate authority to the Corporate Director of Housing & Regeneration in consultation with the Mayor to agree the settlement of rights of light claims with an affected party, together with any associated fees. 3. Delegate authority to the Director of Governance and Legal Services in consultation with the Mayor to agree the terms of and enter into any documentation required to deal with any property matters necessary to progress the development of the Land. 4. Note that the cost of the proposed settlement of rights of light compensation payments and associated fees will be met from the capital budget for the Brunton Wharf site development. REASON FOR DECISION: 1. The decisions sought in this report are to enable the construction on the Land of the new building, a 9-storey residential housing block. 2. The Council has instructed Rights of Light Consultant to carry out an analysis to identify surrounding properties which may suffer an adverse impact to the level of light currently maintained. They reported that there are potentially 2 buildings, 1 school and 4 further Street \ Road properties that may be affected by the development with the individual dwellings therein being affected to varying degrees as detailed in the right to light report. 3. Rights of Light Consultant have also assessed the level of light infringement to each individual property that is affected and provided details of the potential settlement budget for the release of these rights. Full details of the affected parties, settlement budgets as well as negotiations are set in the exempt appendix. Due to the high risk of an injunction to prevent the scheme being delivered and the associated settlement costs, the Council needs to consider appropriate use of its powers to mitigate these risks. ALTERNATIVE OPTIONS: Do nothing option: if the Council decides not to appropriate the Land, then there is the potential that affected private property owners could bring injunction proceedings which could stop the construction of the project or significantly delay its delivery and the 32 new affordable homes. Action by: Corporate Director of Housing and Regeneration
Word for word from the decision Tower Hamlets published for this meeting. Source: democracy.towerhamlets.gov.uk

Follow this further

Built from Tower Hamlets's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix. 1 for Brunton Wharf housing schemeAppendix 259 KB Copy on its way
PDF
Appendix. 1 for Brunton Wharf housing schemeAppendix 259 KB Copy on its way
PDF
Brunton Wharf housing schemeReport 196 KB Copy on its way
PDF
Brunton Wharf housing schemeReport 196 KB Copy on its way

At this meeting

Whole meeting

On this subject at Tower Hamlets

Search all
  1. Brunton Wharf housing schemeThis decision
  2. Seeking approval to progress the procurement and delivery of new build housing projects: Albert Jacob House, Brunton Wharf, Caxton Grove, Copenhagen Place and Rushmead.Approved

More from Tower Hamlets Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 6th Floor of Town Hall LettingDECISION: 1. Grant permission for a 15 years lease to London Air Ambulance 2. To delegate authority to the Corporate ... Agreed Open
23 Sep 2026 Cressy PlaceDECISION: 1. Delegate authority to the Corporate Director of Housing & Regeneration in conjunction with the mayor to ... Agreed Open
23 Sep 2026 Caxton GroveDECISION: 1. Delegate authority to the Corporate Director of Housing & Regeneration in conjunction with the mayor to ... Agreed Open
23 Sep 2026 Copenhagen Place SchemeDECISION: 1. Delegate authority to the Corporate Director of Housing & Regeneration in consultation with the Mayor to... Agreed Open
23 Sep 2026 Arnold Road Development (3-5 Arnold Road) – rationale and deliveryDECISION: 1. Note the current status of the Arnold Road development and the impact arising from the insolvency of Jer... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies