Resolved

The Pre-Decision Scrutiny Questions and officer responses were noted. DECISION 1. To authorise the procurement of an architect and multi-disciplinary design team to take the design and construction through to completion and the inclusion of this contract on the Contracts Forward Plan. 2. To authorise the procurement of an Employer’s Agent to take the construction through to completion. 3. To authorise the procurement of a construction contractor to undertake the construction work. 4. To note the budget approval of £51.400m for the development of George Green School and the funding sources identified and allocated for this purpose. 5. To authorise the Corporate Director place to award the contracts referred to above in consultation with the Corporate Director of Resources, subject to approval through the capital governance process and tenders being within the approved capital estimate. 6. To authorise the Corporate Director Place to enter into any agreements relating to and facilitating the above arrangements such as collateral warranties, novation agreements in order to protect the Council’s interests. 7. To note the Equalities Impact Assessment as set out in Paragraph 4.1 of the report. Action by: CORPORATE DIRECTOR PLACE (A. SUTCLIFFE) (Head of Capital Delivery (J. Abraham) Reasons for Decision The council’s Financial Regulations and Procurement Rules require Cabinet approval for the appointment of services over £0.250m and works over £5.000m. The appointment of the architect and multi-disciplinary design team to develop the design to planning submission stage is expected to cost in excess of £0.250m and the works contract will significantly exceed £5.000m. Alternative Options The Q4 Contracts Forward Plan is due to be presented to Cabinet early next year. Without an earlier approval, the procurement of a design team to submit a planning application by April 2022 will be delayed and it will not be possible to deliver a replacement scheme by the target date of September 2024.
Word for word from the decision Tower Hamlets published for this meeting. Source: democracy.towerhamlets.gov.uk

Follow this further

Built from Tower Hamlets's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
George Green School: Procurement of works and servicesReport 249 KB Copy on its way

At this meeting

Whole meeting

On this subject at Tower Hamlets

Search all
  1. George Green School: Procurement of works and servicesThis decision
  2. George Green Change of Designation from Complex Needs to Autistic Spectrum Condition - Formal Decision following statutory notice.Approved
  3. Report on outcome of the stage one consultation on the proposal to change the designation of George Green School Specialist Provision and increase Pupil NumbersNoted
  4. George Green’s Almshouses - Transfer of RTB grant to new Charitable Incorporated OrganisationApproved
  5. Affordable Housing Grant Programme - George Green's AlmshousesAgreed
  6. TH Affordable Housing Grant - continuous market engagement (George Green Almshouses)Agreed

More from Tower Hamlets Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 6th Floor of Town Hall LettingDECISION: 1. Grant permission for a 15 years lease to London Air Ambulance 2. To delegate authority to the Corporate ... Agreed Open
23 Sep 2026 Cressy PlaceDECISION: 1. Delegate authority to the Corporate Director of Housing & Regeneration in conjunction with the mayor to ... Agreed Open
23 Sep 2026 Caxton GroveDECISION: 1. Delegate authority to the Corporate Director of Housing & Regeneration in conjunction with the mayor to ... Agreed Open
23 Sep 2026 Brunton Wharf housing schemeDECISION: 1. Delegate authority to the Corporate Director of Housing & Regeneration in consultation with the Mayor to... Agreed Open
23 Sep 2026 Copenhagen Place SchemeDECISION: 1. Delegate authority to the Corporate Director of Housing & Regeneration in consultation with the Mayor to... Agreed Open