London Borough of Tower Hamlets
Cabinet, Friday 27 March 2026

Governance decision to support the completion of the Maltings and Brewster building safety project

Approved Executive 1 paper

AI summaryCabinet approved direct award to Wates of £11.3m to finish building safety work at Maltings and Brewster, taking total project spend to £22,772,931 with completion by Autumn 2027.

AI summaryIn plain English

Written from the decision wording; the report is not read yetPDF Pro
OutcomeApprovedTo complete remaining structural and cladding works at Maltings and Brewster
Money£11.3m further awardTotal project value £22,772,931
What happens nextWates completes remaining works70 week programme, site exit by Autumn 2027
Who it affectsHigh rise residents and leaseholdersAt Brewster and Malting House in the borough

What was decided

Cabinet approved continued use of Wates to deliver the remaining works via a direct award, as an amendment to the current structural work contract.

Cabinet noted the value of this further award is £11.3m, making a total project value of £22,772,931.

Cabinet noted that, once approved, the governance process will progress to ensure all payments and financial requirements are met.

Why

After the Grenfell fire, flammable External Wall Insulation at Brewster and Malting House was judged a significant risk to life in a fire.

A structural review also found the Large Panel System blocks could suffer progressive collapse in an explosion, so cladding works were paused in December 2018.

Using the same contractor avoids litigation risk from two contractors on the same site and saves up to 40 weeks of inconvenience for residents.

What happens next

Wates will install the remaining External Wall Insulation on the four end elevations that have been exposed since 2018.

The 70 week programme runs from commencement, with Wates expected to leave site by Autumn 2027.

Governance and payment processes will be progressed to meet financial requirements.

The money

  • £11.3m Value of the further award to Wates
  • £22,772,931 Total project value
  • £1,398,804.50 Original EWI 1 contract awarded to Wates, started February 2018
  • £9,209,014.63 Structural works contract, commenced January 2023
  • £4,270,588 Supplementary funding application dated 21/03/25, fully signed 30/04/25
  • £5,252,319.03 Value of this order (final EWI phase)

Options considered

  • Chosen: Directly award the remaining EWI works to Wates as an amendment to the current contract. Wates already on site, ensures continuity, avoids litigation risk and saves up to 40 weeks for residents
  • Rejected: Appoint a different construction contractor for the remaining EWI works. Impractical given Wates were already on site delivering the paused works

Implications

  • Financial: Adds £11.3m of council spend, bringing total project cost to £22,772,931 across multiple contracts and a supplementary funding application.
  • Legal: Direct award to the existing contractor avoids litigation risk that could arise from two different contractors working on the same site and same works.
  • Risk: Decision addresses life safety risks from flammable EWI cladding and structural risk of progressive collapse in Large Panel System blocks.
  • Other: Using the same contractor is expected to save up to 40 weeks of disruption for residents compared with switching contractors.

Who and where

  • Residents and leaseholders of Brewster House and Malting House
  • London Borough of Tower Hamlets as building owner and duty holder

Timeline

  • February 2018: Wates started EWI 1 cladding works under the Better Neighbourhoods Framework
  • December 2018: Cladding works paused after structural engineer identified progressive collapse risk, leaving four end elevations exposed
  • January 2023: Structural works directly awarded to Wates and commenced, around four years after cladding was paused
  • 21/03/25: Supplementary funding application dated
  • 30/04/25: Supplementary funding application fully signed
  • 2026-03-27: Cabinet decision to approve continued use of Wates and the further award
  • Autumn 2027: Anticipated that Wates will leave site after the 70 week final phase

Plain English for the jargon

  • EWI: External Wall Insulation, the cladding system on the outside of a building
  • Large Panel System: A type of high rise construction identified for structural review after Grenfell
  • Progressive collapse: A structural failure where damage in one area spreads and causes wider building collapse
  • Better Neighbourhoods Framework: The procurement framework under which the original Wates contracts were awarded
  • Wilde Carter Clack: The council's appointed structural engineer for the project
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5.4

Resolved

DECISION 1. Approve the continued use of Wates to deliver the remaining works to complete the structural strengthening and EWI2 works via a direct award as an amendment to the current structural work contract. 2. To note that the value of this further award is £11.3m making a total project value of £22,772,931. 3. To note that once approved the governance process will progress to ensure all payments and financial requirements are met. Reasons for the decision Background Following the Grenfell tragedy and a review of all high-rise buildings in the Borough, it was identified that both Brewster and Malting House had a potentially flammable External Wall Insulation (EWI) material that posed a significant risk of life in the event of a fire. As a result, Wates Living Space (Wates) were awarded a contract (EWI 1) under the Better Neighbourhoods Framework and started works in February 2018 to remove this cladding and replace it with a fire-resistant material at a value of £1,398,804.50. During this period the Ministry of Housing and Local Government asked all Councils to review buildings constructed with ‘Large Panel Systems’ (such as Brewster and Maltings), to ensure that they were safe. Our appointed Structural Engineer (Wilde Carter Clack) identified serious structural issues with both blocks that meant that in the event of an explosion, the building(s) could suffer from progressive collapse. As a result, the cladding works were paused in December 2018, leaving the four end elevations exposed without any cladding. Following extensive investigations and design work by our structural engineer a solution was found to address the structural issues. Given that Wates were already on site and it would be impractical to appoint a different construction contractor, the Council directly awarded to Wates the structural works in accordance with the terms of the procured Better Neighbourhoods Framework contract. This commenced in January 2023, circa 4 years after the cladding works were paused. The value of the second contract, issued under the Better Neighbourhoods Framework, was £9,209,014.63. A supplementary funding application, as per Appendix 1, was dated 21/03/25 and fully signed by 30/04/25 for £4,270,588. The installation of the internal steel columns and beams have been completed to both blocks and the drilling, anchor and steel frame installation to the external end (flank) walls are 90% complete. The work to install the remaining EWI on the end elevations is proposed to be awarded to Wates as part of the current contract so they can complete the works they had to pause in December 2018. The appointment of Wates will ensure continuity and avoid litigation risks relating to two different contractors working on the same site and the same works. Also by using the same contractor could save up to 40 weeks inconvenience to residents. This final phase is programmed to take 70 weeks from commencement, and it is anticipated the remaining EWI can be complete, with Wates leaving site, by Autumn 2027. The value of this order is £5,252,319.03. The final account for the original EWI ...
Word for word from the decision Tower Hamlets published for this meeting. Source: democracy.towerhamlets.gov.uk

Follow this further

Built from Tower Hamlets's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Governance decision to support the completion of the Maltings and Brewster building safety projectDecisions 145 KB Copy on its way

At this meeting

Whole meeting

More from Tower Hamlets Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 6th Floor of Town Hall LettingDECISION: 1. Grant permission for a 15 years lease to London Air Ambulance 2. To delegate authority to the Corporate ... Agreed Open
23 Sep 2026 Cressy PlaceDECISION: 1. Delegate authority to the Corporate Director of Housing & Regeneration in conjunction with the mayor to ... Agreed Open
23 Sep 2026 Caxton GroveDECISION: 1. Delegate authority to the Corporate Director of Housing & Regeneration in conjunction with the mayor to ... Agreed Open
23 Sep 2026 Brunton Wharf housing schemeDECISION: 1. Delegate authority to the Corporate Director of Housing & Regeneration in consultation with the Mayor to... Agreed Open
23 Sep 2026 Copenhagen Place SchemeDECISION: 1. Delegate authority to the Corporate Director of Housing & Regeneration in consultation with the Mayor to... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies