Cabinet, Wednesday 23 September 2026

Arnold Road Development (3-5 Arnold Road) – rationale and delivery

Noted Executive 2 papers

AI summaryTower Hamlets Cabinet approves a Pre-Construction Services Agreement with Lovell Partnerships to complete the 62-home Arnold Road affordable housing scheme after the insolvency of Jerram Falkus Construction Ltd.

AI summaryIn plain English

Written from the decision wording; the report is not read yetPDF Pro
OutcomeNotedSubject to public sector framework, with delegated authority
MoneyBudget in Exempt Appendix 2Specific figures not provided in supplied papers
What happens nextRun PCSA then decide main worksReview cost, programme, risk, contract form before award
Who it affects62 affordable homes plus commercial spaceCouncil-led scheme at 3-5 Arnold Road

What was decided

Cabinet approved a Pre-Construction Services Agreement with Lovell Partnerships Ltd through a compliant public sector framework, and approved the budget allocation and uplift set out in Exempt Appendix 2 to fund the PCSA and the later completion of the development.

Cabinet noted that Lovell's preferred delivery approach is Management Contracting rather than a traditional Design and Build contract, and that the PCSA will assess the cost, programme, risk and value-for-money implications before any main works award.

Cabinet delegated authority to the Corporate Director of Housing and Regeneration, in consultation with the Mayor and the Director of Legal Services, to enter into the PCSA and later the main works contract.

Why

Arnold Road is a strategically important Council-led affordable housing development delivering 62 affordable homes and commercial space, now partially completed following the insolvency of Jerram Falkus Construction Ltd.

Specialist investigations are required before the Council can fix the final scope, programme and cost of completion, and to secure regulatory approvals and a robust completion strategy.

Appointing Lovell under a PCSA is intended to protect the Council's investment, limit further deterioration of the asset, and support the earliest possible delivery of affordable homes.

What happens next

Lovell will undertake surveys, investigations, consultant reviews, statutory approvals and other activities during the PCSA, producing a validated cost-to-complete, a recommended delivery model, a detailed construction programme and the proposed form of construction contract.

After the PCSA report is reviewed, the Council can choose to appoint Lovell for the main works under a management contracting approach or seek an alternative main works contractor.

The main works contract award is subject to confirmation through the PCSA process and approval under the delegated authority set out in the decision.

The money

  • Budget allocation and uplift as set out in Exempt Appendix 2 (figures not provided in supplied papers) Funding for the PCSA and for completing the Arnold Road development

Options considered

  • Chosen: Award a Pre-Construction Services Agreement to Lovell Partnerships Ltd via a compliant public sector framework (chosen). Enables due diligence, validation of construction risks, regulatory approvals and a completion strategy for the partially built affordable housing scheme
  • Chosen: Management Contracting as the preferred main works delivery model (subject to PCSA assessment). Lovell's current preferred approach; cost, programme, risk and value-for-money implications to be assessed during the PCSA before award
  • Rejected: Design and Build as the main works contract form. Lovell's preferred approach is Management Contracting; the PCSA will test the implications of each before a decision on the main works contract
  • Rejected: Seek an alternative main works contractor after the PCSA. Remains available as a fallback once the PCSA report is reviewed, but is not the preferred route
  • : Alternative option 1 referenced in the decision paper (text truncated in supplied papers)

Implications

  • Financial: Approval of a budget allocation and uplift in Exempt Appendix 2; the main works contract award is subject to confirmation of the validated cost-to-complete and any implications for the approved main works budget.
  • Risk: The insolvency of Jerram Falkus Construction Ltd has left the development partially completed and created significant technical, regulatory and commercial uncertainty; the PCSA is intended to validate construction risks.
  • Legal: Authority to enter into the PCSA and the main works contract is delegated to the Corporate Director of Housing and Regeneration in consultation with the Mayor and the Director of Legal Services.
  • Other: Switching from the original contractor to a new procurement route via a public sector framework is required to keep the scheme moving.
  • Other: Choice of Management Contracting over Design and Build changes how trades and risk are allocated for the completion works, to be tested during the PCSA.

Who and where

  • Future residents of the 62 affordable homes at 3-5 Arnold Road
  • London Borough of Tower Hamlets as the developer and asset owner
  • Prospective users of the commercial space included in the development
  • Subcontractors and supply chain affected by the insolvency of Jerram Falkus Construction Ltd and the change of contractor

Timeline

  • Cabinet decision dated 2026-09-23: Approval of PCSA award, associated budget, and delegations of authority
  • Following the decision: PCSA period covering surveys, investigations, consultant reviews, statutory approvals and other activities to support a completion strategy
  • At the end of the PCSA period: Review of validated cost-to-complete, recommended delivery model, detailed construction programme, budget implications and proposed form of construction contract, leading to a decision on the main works contract

Plain English for the jargon

  • PCSA (Pre-Construction Services Agreement): A contract under which a contractor carries out surveys, investigations, design development and pricing work before the main construction contract is awarded.
  • Management Contracting: A delivery model where the management contractor manages the works and lets individual trade packages, rather than carrying out the design and build itself.
  • Design and Build: A single contractor takes responsibility for both the design and construction of the works.
  • Cost-to-complete: The validated estimate of the remaining expenditure needed to finish a partially completed project.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6.6

Resolved

DECISION: 1. Note the current status of the Arnold Road development and the impact arising from the insolvency of Jerram Falkus Construction Ltd. 2. Approve the award of a Pre-Construction Services Agreement (PCSA) to Lovell Partnerships Ltd through a compliant public sector framework. 3. Approve the budget allocation set out in Exempt Appendix 2 to undertake the PCSA, including surveys, investigations, consultant reviews, statutory approvals and other activities required to support the completion strategy. 4. Approve the budget uplift set out in Exempt Appendix 2 to facilitate completion of the development following the PCSA period, subject to confirmation through the PCSA process and approval of the main works contract in accordance with the delegated authority set out below. Please refer to exempt appendix 2 for the details. 5. Delegate authority to the Corporate Director of Housing and Regeneration, in consultation with the Mayor and the Director of Legal Services, to enter into the PCSA and associated contractual documentation. 6. Note Lovell's current preferred approach for delivery of the completion works is through a Management Contracting contract rather than a traditional Design and Build contract, and that the PCSA will provide a detailed assessment of the cost, programme, risk and value-for-money implications of this approach prior to any award of the main works contract. 7. Delegate authority to the Corporate Director of Housing and Regeneration, in consultation with the Mayor and the Director of Legal Services, to enter into the main works contract and associated contractual documentation following the successful conclusion of the PCSA. REASONS FOR DECISION: 1. Arnold Road is a strategically important Council-led affordable housing development delivering 62 affordable homes and commercial space. 2. The insolvency of Jerram Falkus Construction Ltd has left the development partially completed and created significant technical, regulatory and commercial uncertainty. 3. Further specialist investigations are required before the Council can determine the final scope, programme and cost of the completion works. 4. Appointment of Lovell Partnerships Ltd under a Pre-Construction Services Agreement will enable the Council to undertake the necessary due diligence, validate construction risks, secure regulatory approvals and establish a robust completion strategy. 5. Approval of the PCSA and associated budget will protect the Council's investment, limit further deterioration of the asset and support the earliest possible delivery of affordable homes to residents. 6. Once the PCSA is completed it allows the Council the opportunity to appoint Lovell for the main works under a management contracting approach. Further details on this will be provided to the Council as part of the decision-making process at the end of the PCSA period. This will set out: • the validated cost-to-complete position; • the recommended delivery model; • the detailed construction programme; • any implications for the approved main works budget; and the proposed form of construction contract 7. Once the PCSA report is reviewed the Council will have the opportunity to either proceed with Lovell Partnerships and enter a main works contract or seek an alternative main works contractor. ALTERNATIVE OPTIONS: 1. Option 1 – Compliant call off award from ...
Word for word from the decision Tower Hamlets published for this meeting. Source: democracy.towerhamlets.gov.uk

Follow this further

Built from Tower Hamlets's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Arnold Road Development (3-5 Arnold Road): rationale and deliveryReport 215 KB Copy on its way
PDF
Arnold Road Development (3-5 Arnold Road): rationale and deliveryReport 215 KB Copy on its way

At this meeting

Whole meeting

More from Tower Hamlets Cabinet

All decisions
MeetingDecisionOutcome
23 Sep 2026 6th Floor of Town Hall LettingDECISION: 1. Grant permission for a 15 years lease to London Air Ambulance 2. To delegate authority to the Corporate ... Agreed Open
23 Sep 2026 Cressy PlaceDECISION: 1. Delegate authority to the Corporate Director of Housing & Regeneration in conjunction with the mayor to ... Agreed Open
23 Sep 2026 Caxton GroveDECISION: 1. Delegate authority to the Corporate Director of Housing & Regeneration in conjunction with the mayor to ... Agreed Open
23 Sep 2026 Brunton Wharf housing schemeDECISION: 1. Delegate authority to the Corporate Director of Housing & Regeneration in consultation with the Mayor to... Agreed Open
23 Sep 2026 Copenhagen Place SchemeDECISION: 1. Delegate authority to the Corporate Director of Housing & Regeneration in consultation with the Mayor to... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies