That the outcome of the Examiner’s report be considered and noted. 2. That Council be recommended formally to adopt the Trafford Community Infrastructure Levy Charging Schedule (as detailed in Appendix A to the report, which includes the modifications proposed by the Examiner as summarised at paragraph 2.1), the supporting Regulation 123 List (as set out in Appendix B) and the Instalments Policy (as set out in Appendix C) for implementation on Monday 07 July 2014. 3. That the Revised SPD1: Planning Obligations 2014 be adopted for implementation on Monday 07 July 2014 (as set out in Appendix D). 4. That authority be delegated to the Corporate Director of Economic Growth and Prosperity for approving the CIL Exceptional Circumstances Policy, Infrastructure Payments Policy and any minor amendments to the wording of all documentation , prior to its implementation.
Word for word from the decision Trafford published for this meeting.Source: democratic.trafford.gov.uk
This report seeks Executive and then Council approval of the Trafford Community Infrastructure Levy (CIL) Charging Schedule (CS). It also seeks Executive approval for the Revised SPD1: Planning Obligations 2014 for adoption together with supporting documentation for the implementation of the levy on all planning applications determined from Monday 07 July 2014.
Recommendation(s)
That Executive: 1. Consider the outcome of the Examiner’s report. 2. Recommend to Council that it formally adopts the Trafford Community Infrastructure Levy Charging Schedule (as detailed in Appendix A, which includes the modifications proposed by the Examiner as summarised at paragraph 2.1), the supporting Regulation 123 List (as set out in Appendix B) and the Instalments Policy (as set out in Appendix C) for implementation on Monday 07 July 2014. 3. Adopt the Revised SPD1: Planning Obligations 2014 for implementation on Monday 07 July 2014 (as set out in Appendix D). 4. Delegate responsibility for approving the CIL Exceptional Circumstances Policy, Infrastructure Payments Policy and any minor amendments to the wording of all documentation to the Corporate Director of Economic Growth and Prosperity, prior to its implementation.
That Council: 1. Adopts the Trafford Community Infrastructure Levy Charging Schedule (as detailed in Appendix A, which includes the modifications proposed by the Examiner as summarised at paragraph 2.1), the supporting regulation 123 list (as set out in Appendix B) and the Instalments Policy (as set out in Appendix C), for implementation on Monday 07 July 2014.
1 Contact person for access to background papers and further information:
Name: Rob Haslam (Head of Planning Services) Extension: 4788
Background Papers: None.
2 Implications: Relationship to Policy The CIL Charging Schedule has been developed Framework/Corporate Priorities to support growth planned in the Trafford Local Plan: Core Strategy. Financial CIL provides the mechanism for the Council to secure funding towards the required essential infrastructure in the borough. Upon implementation of CIL, a management fee of up to 5% will be collected from CIL to support the management and delivery of CIL in Trafford. Legal Implications: The CIL Charging Schedule is being developed in line with the requirements of the Planning Act 2008, CIL Regulations 2010 as amended. Upon adoption it will replace in part the current planning obligations regime set out in Policy L8 of the Core Strategy and the current Planning Obligations Supplementary Planning Document with a revised version. Equality/Diversity Implications The draft CIL Charging Schedule was subject to an EIA assessment in September 2013 to ensure that equality issues have been considered as part of the preparation. Sustainability Implications The CIL Charging Schedule has been subject to an independent viability appraisal. Most of the evidence supporting it will have been subject to independent sustainability appraisal as part of the preparation of the Core Strategy. Staffing/E-Government/Asset Consultees have been able to make electronic Management Implications submissions to the CIL Charging Schedule consultations online and all the documentation is available to access through the Strategic Planning web pages. Risk Management Implications A timetable for clearance of outstanding S106 agreements has been set up to ensure a smooth transition to the CIL system. Public Health Implications None. Health and Safety Implications None.
1.0Background 1.1 The Community Infrastructure Levy (CIL) was created under the terms of the Planning Act 2008, and establishes a new system for collecting developer contributions towards essential infrastructure.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.