That the progress to date in developing proposals for an extra care scheme and associated development in Old Trafford be noted. 2. That approval be given to the Council’s contribution of land to support the development which will be conditional on reaching agreement on the overall financing for the construction and running costs of the new facility. 3. That authority be delegated to the Corporate Director for Economic Growth and Prosperity, in consultation with the Director of Finance and Director of Legal to approve final terms for: a. The disposal of the land; b. The lease and costs for the library and Sure Start Centre; and c. The provision of a community centre.
Word for word from the decision Trafford published for this meeting.Source: democratic.trafford.gov.uk
The report provides an update on progress of the development of an integrated extra care scheme, health facility and community hub (including library) on Shrewsbury Street, Old Trafford.
Recommendation(s)
The Executive are recommended to:
1) Note the progress to date in developing proposals for an extra care scheme and associated development in Old Trafford; 2) Approve the Council’s contribution of land to support the development which will be conditional on reaching agreement on the overall financing for the construction and running costs of the new facility; 3) Delegate the Corporate Director for Economic Growth and Prosperity, in consultation with the Director of Finance and Director of Legal to approve final terms for: a. The disposal of the land; b. The lease and costs for the library and Sure Start Centre; and c. The provision of a community centre.
Contact person for access to background papers and further information:
Name: Linda Harper; Richard Roe Extension: 1890; 4265
Background Papers: None.
1 Implications:
Relationship to Policy This report relates to the corporate priorities Framework/Corporate Priorities economic growth and development and services focused on the most vulnerable people.
The proposed scheme will support the successful implementation of the Old Trafford Masterplan and support the delivery of the adopted Trafford Local Plan: Core Strategy which identifies Old Trafford as a Priority Regeneration Area. Financial Addition to the Capital Investment Programme to be financed from the capital receipt from the disposal of the site to Trafford Housing Trust. The fit out costs of £58,100 will be a charge to the Capital Investment Programme Scheme Ref 2582.
The premise costs of the current site for the Library, Sure Start and Community Centre is £126,000. The proposal is to transfer the Community Centre asset to Trafford Housing Trust (THT) and replace Library and Sure Start facilities. Indicative costs for the Library/Sure Start facility given by THT are:
£ Lease per annum 48,000 Service charge 25,785 Total per annum 73,785 Plus utility bills, NNDR, third party support, proportion of “back office space” and cost of transitional arrangements
These are draft costs and are subject to further review and acceptance by the Council and acceptance of the final business case..
The provision of an 80 bed extra care facility may potentially delay or divert individuals from entering local authority funded residential care. Average gross costs of residential care are in the range of £22,000 to £26,000 per annum.
The new units of accommodation will generate additional New Homes Bonus. Legal Implications: The disposal of the Council’s land to Trafford Housing Trust will require the Department of Community and Local Government’s consent under section 123 of the Local Government Act 1972.
There are not thought to be any European Union
2 procurement implications to the proposed scheme.
There are not thought to be any State Aid implications to the proposed scheme.
Equality/Diversity Implications The latest reliable statistics with regard to BME population at small geographic areas (2001 census) indicated that for the four wards that comprise the North of the Borough, the proportion of non-white ethnicity was 23%, with one ward recording 54%. Developing an Extra Care facility in this area offers an opportunity to tailor services to the specific needs of this large population, particularly important given the lack of alternative provision within the area. Sustainability Implications The proposed development will provide modern, fit for purpose facilities to meet the current and future needs of older people and the wider community.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.