The report seeks final approval for the expansion of Oldfield Brow Primary School.
The Council has a statutory duty to provide sufficient school places in its area. To support the achievement of this duty and to meet any risks in relation to school conditions and access, the Council have received allocated capital funding of £18.85 million for the two years up to 2015. The expansion of Oldfield Brow primary school is required in order to address some of the capacity demands. Following the decision of the Executive Committee (E/24.06.13/19), taken on 24th June 2013 and the decision of the Executive Member for Education (M/09.07.14/CS) taken on 9th July 2014 all the required consultation processes for the expansion of the School have now been completed.
Recommendation(s)
That the proposals to expand Oldfield Brow Primary School are approved.
Contact person for access to background papers and further information:
Name: Marilyn Golding Extension: 912 1853
Background Papers: None
Implications:
Relationship to Policy Framework/Corporate Priorities Preserving and improving education excellence
Financial In June 2013 Trafford’s Executive Committee agreed £1,500,000 basic need funding to take Oldfield Brow from 1FE to 1.5FE.
In July 2014 The Executive Member for Education approved a further £2,800,000 to increase the intake from 1FE to 2FE.
Legal Implications: The expansion of schools is subject to statutory processes, which will need to be adhered to as 1 appropriate for the scheme. In addition, the LA has statutory duties in relation to the provision of school places, including using its planning powers to secure provision. Equality/Diversity Implications Schools are subject to current legislation about equality and diversity. The equality and diversity implications have been considered as part of the overall process.
Sustainability Implications School buildings are procured requiring successful contractors to meet required sustainability criteria. Staffing/E-Government/Asset Expanding schools requires additional staff and ICT Management Implications provision, which is a matter for the School’s Governing Body. Risk Management Implications Failure to provide sufficient school places will find the Council in breach of its statutory duty.
Health & Wellbeing Implications Providing suitable school places within a reasonable distance from home for children resident in the Altrincham area. Health and Safety Implications All school building work is subject to appropriate current Health and Safety/CDM regulations.
Appendix A of the Education and Early Years Capital Programme, approved by the Executive Committee on 2nd June 2014, provided statistical details of pupil place predictions and capacity. The data indicated that the demand for places in Trafford schools would continue to increase through to 2016 and beyond. Altrincham was identified as one of the areas where demand will exceed current capacity through to 2016. Oldfield Brow showed a particular shortfall in places and therefore, the Report recommended the expansion of Oldfield Brow Primary School subject to the completion of statutory processes.
1.1Need or demand for additional places
There are several factors contributing to the growth in demand for primary school places in the Altrincham area and in Trafford as a whole;
i) Birth Rate
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
EXPANSION OF OLDFIELD BROW PRIMARY SCHOOL: FINAL APPROVALReport | 200 KB | DownloadRead as text |
Follow Executive at Trafford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Sep 2026 | Greater Manchester End to End Fostering Recruitment Hub1) That the national and Greater Manchester context supporting the developments of the Greater Manchester End-to-End ... | Approved | Open |
| 21 Sep 2026 | Sale Waterside Private Finance Initiative Exit1) That the hand back of the Sale Waterside PFI assets to Council ownership on expiry of the PFI contract on 28 th Oc... | Approved | Open |
| 20 Jul 2026 | Wharfside Strategic MasterplanThat the Executive: (i) Approves the draft Trafford for consultation. (ii) (ii) Delegates authority to the Corporate ... | Approved | Open |
| 20 Jul 2026 | Local Plan Regulation 19 Consultation ApprovalThat the Executive: (i) Approves the Trafford Local Plan (Publication Version) 2026, including allocations, designati... | Approved | Open |
| 15 Jun 2026 | Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.