Resolved
That the proposals to relocate Brentwood school to a new purpose built school based at Cherry Manor be approved.
Executive approved this item on Monday 16 March 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
That the proposals to relocate Brentwood school to a new purpose built school based at Cherry Manor be approved.
The Council has a statutory duty to provide sufficient school places in its area. This includes provision for special school places. To support the achievement of this duty, and to meet any risks in relation to school conditions and access, we have received allocated capital funding of £18.85 million for the two years up to 2015.
The SEN Review March 2013 highlighted the growth in overall school place demand for learners with SEN as well as the increasing need for special school places. The number of statements for Trafford children has increased by 30% in the period since 2010. Brentwood School has a site capacity for 88 pupils and currently has 108 pupils on roll. This is projected to grow to 120 by 2018. The review recommended an expansion of Brentwood on a new site at Cherry Manor.
In March 2014 an update report concerning the recommendation went to Trafford Executive Committee who accepted the recommendation for a complete new build on the Cherry Manor site to accommodate Brentwood School.
Following the decision of the Executive Committee (13.03.14) all the required consultation processes for the expansion of the School have now been completed.
Recommendation(s)
That the proposals to relocate Brentwood school to a new purpose built school based at Cherry Manor be approved. Schedule 3 of The School Organisation (Prescribed Alterations to Maintained Schools) (England) Regulations 2013, requires that any determination must be made within the period of two months of the end of the representation period. The grant of planning permission under Part 3 of the Town and Country Planning Act 1990(1) is prescribed in the Regulations as a specified event which (if the approval is expressed to take effect only if they occur) must occur by a date specified in the approval.
Contact person for access to background papers and further information:
Name: Marilyn Golding Extension: 912 1853
Background Papers: None
1 Implications:
Relationship to Policy Framework/Corporate Priorities Preserving and improving education excellence
Financial Total budget for the Brentwood School Capital project is £10.5 million. This includes a significant contribution of £1.6 million from the school (£700K towards the new build and £900K towards the Hydrotherapy pool). There is also a 214k contribution from the EFA. Total commitment from Trafford School Capital fund is £8.7m
In March 2014 Trafford’s Executive committee agreed funding from the schools capital basic need combined with some prudential borrowing to fund the proposal.
Legal Implications: The expansion and relocation of special schools is subject to statutory processes, which will need to be adhered to as appropriate for the scheme. In addition, the LA has statutory duties in relation to the provision of school places, including using its planning powers to secure provision. Equality/Diversity Implications Schools are subject to current legislation about equality and diversity. These have been considered as part of this process. Sustainability Implications School buildings are procured requiring successful contractors to meet required sustainability criteria. Staffing/E-Government/Asset The new school building (in particular new Management Implications hydrotherapy provision) and its increased capacity will require additional staff, facilities and ICT provision. These will be a matter for the School’s Governing Body. Risk Management Implications Failure to provide sufficient school places will find the Council in breach of its statutory duty.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
RELOCATION AND EXPANSION OF BRENTWOOD COMMUNITY SPECIAL SCHOOL: FINAL APPROVALReport | 152 KB | DownloadRead as text |
Follow Executive at Trafford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Sep 2026 | Greater Manchester End to End Fostering Recruitment Hub1) That the national and Greater Manchester context supporting the developments of the Greater Manchester End-to-End ... | Approved | Open |
| 21 Sep 2026 | Sale Waterside Private Finance Initiative Exit1) That the hand back of the Sale Waterside PFI assets to Council ownership on expiry of the PFI contract on 28 th Oc... | Approved | Open |
| 20 Jul 2026 | Wharfside Strategic MasterplanThat the Executive: (i) Approves the draft Trafford for consultation. (ii) (ii) Delegates authority to the Corporate ... | Approved | Open |
| 20 Jul 2026 | Local Plan Regulation 19 Consultation ApprovalThat the Executive: (i) Approves the Trafford Local Plan (Publication Version) 2026, including allocations, designati... | Approved | Open |
| 15 Jun 2026 | Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.