Resolved
That the report be noted.
Accounts and Audit Committee noted this item on Tuesday 24 March 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted.
The Audit Plan for Trafford Council
Year ended 31 March 2015 24 March 2015
Mike Thomas Director / Engagement Lead T 0161 214 6368 E [email removed]
Helen Stevenson Manager T 0161 234 6354 E [email removed]
Andrew McNeil Executive T 0161 912 4560 E [email removed]
© 2015 Grant Thornton UK LLP | Audit Plan 2014-15 – Trafford Council Contents Section
1. Understanding your business 2. Developments relevant to your business and the audit 3. Our audit approach 4. Significant risks identified 5. Other risks 6. Value for Money 7. Results of interim work 8. Key dates 9. Fees and independence 10. Communication of audit matters with those charged with governance
The contents of this report relate only to the matters which have come to our attention, which we believe need to be reported to you as part of our audit process. It is not a comprehensive record of all the relevant matters, which may be subject to change, and in particular we cannot be held responsible to you for reporting all of the risks which may affect the Council or any weaknesses in your internal controls. This report has been prepared solely for your benefit and should not be quoted in whole or in part without our prior written consent. We do not accept any responsibility for any loss occasioned to any third party acting, or refraining from acting on the basis of the content of this report, as this report was not prepared for, nor intended for, any other purpose.
© 2015 Grant Thornton UK LLP | Audit Plan 2014-15 – Trafford Council Understanding your business In planning our audit we need to understand the challenges and opportunities the Council is facing. We set out a summary of our understanding below.
Challenges/opportunities
1. Alternative Delivery Models 2. Procurement and 3. Public Sector Reform and 4. LG Finance Settlement 5. Collaborative working with Commissioning Devolution • The local government the NHS Partnership working with other bodies and the • Delivering efficiency Regional devolution plans spending settlement showed • Development of new voluntary sector. savings through improved Combined authorities local authorities are facing a working arrangements to procurement cash reduction in their deliver the Better Care Confederations spending power of 6% in Fund • Moving from the provision to 2015-16. • NHS emergency care the commissioning of services • At the same time local overload and the re- authorities are facing emergence of bed-blocking increasing demands for linked to adult social care school places and adult capacity. social care services.
Our response
We will assess progress in We will review the progress • We will discuss your We will examine your 2015- We will discuss your plans in developing alternative you have made in delivering progress towards the 16 budget and medium term these areas through our delivery models and your efficiency savings in this implementation of the outlook as part of our work regular meetings with senior collaborative arrangements area as part of our work on Greater Manchester on assessing your management and report to as part of your Reshaping your arrangements for Devolution Plan arrangements for financial those charged with Trafford Council Programme financial resilience. resilience governance, where appropriate. Your Reshaping Trafford Council Programme sets out to deliver £21.5 million savings and additional income for 2015/16
© 2015 Grant Thornton UK LLP | Audit Plan 2014-15 – Trafford Council Developments relevant to your business and the audit In planning our audit we also consider the impact of key developments in the sector and take account of national audit requirements as set out in the Code of Audit Practice ('the code') and associated guidance.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
TRAFFORD AUDIT PLANReport | 207 KB | DownloadRead as text |
Follow Accounts and Audit Committee at Trafford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Mar 2022 | MINUTESRESOLVED – That the Minutes of the Meeting held on 2 nd February 2022 be approved as a correct record and signed by t... | Approved | Open |
| 22 Mar 2022 | 2021/22 annual governance statement - approach / timetableRESOLVED - (1) That the timetable / action plan be noted. (2) That it be noted that the Committee would have input in... | Noted | Open |
| 22 Mar 2022 | Audit progress reportRESOLVED – That the content of the report be noted. | Noted | Open |
| 22 Mar 2022 | Budget monitoring report 2021/22 - period 10 (april 2021 - january 2022RESOLVED – That the updated positions on the revenue budget, collection fund and capital programme, and the observati... | Noted | Open |
| 22 Mar 2022 | Accounting concepts and policiesRESOLVED - (1) That the accounting concepts and policies that will be used in completing the 2021/22 annual accounts ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.