Resolved
That the report be noted and approved.
Accounts and Audit Committee noted this item on Tuesday 24 March 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted and approved.
The purpose of the report is to provide, at a high level, the proposed Internal Audit Operational Plan for 2015/16.
The Accounts and Audit Committee is asked to approve the 2015/16 Internal Audit Plan.
Contact person for access to background papers and further information:
Name: Mark Foster – Audit and Assurance Manager Extension: 1323
Background Papers: None Internal Audit Operational Plan 2015/16 – Audit and Assurance Service 1. Introduction
1.1The 2015/16 Internal Audit Operational Plan identifies the work to be undertaken by the Audit and Assurance Service during the year. This report describes its method of compilation and presents, at a high level, the 2015/16 Plan for approval.
2.1Each year the Audit and Assurance Service produces a report setting out its annual plan for approval by CMT and the Accounts and Audit Committee. Subsequent updates are then provided to CMT and the Accounts and Audit Committee through the year highlighting work undertaken and progress against key areas of the Plan.
2.2In accordance with the Accounts and Audit (England) Regulations 2011, it is a requirement that the Council “must undertake an adequate and effective internal audit of its accounting records and its system of internal control in accordance with the proper practices in relation to internal control.” (Note: Accounts and Audit Regulations 2015 to come into effect from April 2015). In order to support this, the Audit and Assurance Service must undertake its work in accordance with the Public Sector Internal Audit Standards which have been in place since April 2013.
2.3The Service’s approach to undertaking internal audit work is set out in the Internal Audit Charter and Strategy documents which were approved by CMT and the Accounts and Audit Committee in March 2014.
3. Compilation of the Plan
3.1The Operational Plan is produced to take into account coverage of risks and associated controls in place. An important consideration is that the Operational Plan should include good coverage across Council services and systems. The ongoing financial challenges facing the Council highlight the need to ensure there are effective governance and internal control arrangements in place to ensure risks are managed and value for money is achieved.
3.2A number of factors are taken into account in compiling the Operational Plan based on both statutory obligations, the objectives of the Council and an assessment of risks. Factors such as materiality, business risks, inherent risks and time since the area was last reviewed are taken into account.
3.3New developments such as changes in legislation and council responsibilities are considered in planning work. Current developments
Internal Audit Plan 2015/16 2 across the Council are taken into account in planning and scheduling work. In 2015/16 for instance, time is set aside for the audit of new systems within Adult Social Care. Time is also allocated in relation to the proposed Joint Venture.
3.4Corporate Directorates provide input to the plan through liaison with the Audit and Assurance Service throughout the year and through information provided such as through risk registers, action plans, self assessments and control / governance issues raised.
3.5The Service has a number of obligations to take into account in producing the Plan. This includes the need to set aside time to meet the requirements of the Accounts and Audit Regulations by facilitating the production of the Authority’s Annual Governance Statement. The Service also co-ordinates the update of the Council’s strategic risk register.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
INTERNAL AUDIT PLAN 2015/16Report | 138 KB | DownloadRead as text |
Follow Accounts and Audit Committee at Trafford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Mar 2022 | MINUTESRESOLVED – That the Minutes of the Meeting held on 2 nd February 2022 be approved as a correct record and signed by t... | Approved | Open |
| 22 Mar 2022 | 2021/22 annual governance statement - approach / timetableRESOLVED - (1) That the timetable / action plan be noted. (2) That it be noted that the Committee would have input in... | Noted | Open |
| 22 Mar 2022 | Audit progress reportRESOLVED – That the content of the report be noted. | Noted | Open |
| 22 Mar 2022 | Budget monitoring report 2021/22 - period 10 (april 2021 - january 2022RESOLVED – That the updated positions on the revenue budget, collection fund and capital programme, and the observati... | Noted | Open |
| 22 Mar 2022 | Accounting concepts and policiesRESOLVED - (1) That the accounting concepts and policies that will be used in completing the 2021/22 annual accounts ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.