That the content of the summary report be noted. 2. That the changes to the 2015/18 Programme be approved. 3. That approval be given to the additional expenditure, listed in Appendix B to the report, in accordance with Financial Procedure Rule No. 4. 4. That the outturn of the prudential indicators for 2014/15 as set out in paragraph 14 and Appendix C to the report be noted.
Word for word from the decision Trafford published for this meeting.Source: democratic.trafford.gov.uk
The report summarises the outturn position for 2014/15 and the consequential impact on the Medium Term Financial Plan 2015/18.
Capital expenditure for 2014/15 amounted to £26.5m, equivalent to 62% of revised budget of £42.9m. The forecast outturn for 2014/15 had been £35.8m and the variance of £9.3m can be explained by a number of factors that are detailed in the report
Net re-profiling of £16.9m will increase the Capital Investment Programme in 2015/16 and later years.
Recommendation(s)
The Executive is requested to
Note this summary report Approve the changes to the 2015/18 Programme Approve the additional expenditure, listed in Appendix B, in accordance with Financial Procedure Rule No. 4 Note the outturn of the prudential indicators for 2014/15 as set out in paragraph 14 and Appendix C.
Contact person for access to background papers and further information: Name: Mark Hughes Extension: 2072
Background Papers - None
1 Capital Expenditure 2014/15
1. The original budget for 2014/15 was approved at £40.9m in February 2014. The Executive approved a revised budget of £42.9m as at Quarter 3 which reflected new schemes supported by capital grants and contributions.
2. Final capital expenditure of £26.5m has been incurred in 2014/15 and some of the main highlights include: School Improvements - £13.2m:- Broadheath Road Primary School refurbishment- £1.4m Bowdon CoE Primary School - £2.6m Springfield Primary School refurbishment - £1.5m Expansion & Basic Need Works - £4.1m Improvements via Devolved Formula Capital - £0.6m Capital Maintenance works - £2.0m Universal Infant Free school Meals works - £0.6m Adult Social Services - £3.0m:- Disabled Facilities Grants - £1.5m Telecare System - £0.4m Extra Care Housing - £0.7m Liquid Logic – ICT Social Care System - £0.4m Major building works on Public & Operational Buildings - £0.5m Regeneration Projects - £1.5m Highway Related Improvements - £6.6m:- Integrated Transport Improvements - £2.5m Highway Structural Maintenance - £3.5m Bridges and Street Lighting Improvements - £0.6m Sport, Recreation & Culture - £0.9m ICT Investment £ 0.7m
3. The level of capital expenditure equates to 62% of the approved budget and a summary of the major variances is shown below. Appendix A provides an analysis of variance at a service level whilst Appendix B details variances at an individual scheme level.
Actual Capital Expenditure compared to £m Revised Budget 2014/15 Revised 2014/15 Budget 42.9 Actual 26.5 Variance (16.4) Explained By:- Re-profiling to future years (Appendix B, pages 11-14) (18.3) Acceleration (Appendix B, page 14) 1.4 Additional Expenditure (Appendix B, page 14-15) 0.8 Savings (Appendix B, page 15) (0.3) Total (16.4)
2 4. Outturn was projected at Quarter 3 to be £35.8m and the level of expenditure incurred has fallen to the final figure of £26.5m. This reflects changes to a number of schemes requiring further re-profiling to 2015/16 and later years. The main areas of change are :- Schools related works - £2.6m Services for Adults - £1.0m Corporate Landlord related scheme s - £1.2m Highways structural maintenance & improvements - £1.4m Information Technology schemes - £2.0m. Other services - £1.1m Specific explanations are provided in the service analyses included in Paragraphs 11 – 13
5. Included in the figures above are a number of schemes where the Council has limited control over the phasing of expenditure. Schools Devolved Formula capital, land assembly schemes and third party grants are outside our control and after adjusting for these outturn performance increases to 66%.
Financing of Capital Expenditure
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.