CORNBROOK HUB COMPULSORY PURCHASE ORDER

Approved Executive 3 papers

Executive approved this item on Monday 27 July 2015. Below is the council's own wording, with the papers it was decided on.

Item24

Resolved

That the approach to the delivery of the Cornbrook Hub Site as set out in the report be endorsed. 2. That in principle approval be provided to the use of compulsory purchase powers to deliver the regeneration of the Cornbrook Hub Site. 3. That it be requested that, in the event of compulsory acquisition becoming expedient for the regeneration of the area, officers shall bring a further report to the Executive. 4. That a uthorisation be given to the service of Requisition for Information upon all owners, occupiers and those with any other interests in the Cornbrook Hub site pursuant to Section 16 of the Local Government (Miscellaneous Provisions) Act 1976. 5. That the Corporate Director for Economic Growth, Environment and Infrastructure and Director of Legal and Democratic Services be authorised to negotiate and complete an appropriate CPO Indemnity Agreement with Manchester Ship Canal Developments Limited to secure all the costs associated with the making of the Order (if required) and the acquisition of all remaining third party interests in the Cornbrook Hub Site including compensation costs as set out in section 5 of the report. 6. That, in the event that such an Indemnity Agreement is concluded, the Corporate Director for Economic Growth, Environment and Infrastructure be authorised to negotiate the acquisition of all interests in the site, in advance of confirmation of a CPO, as if such CPO had been confirmed.
Word for word from the decision Trafford published for this meeting. Source: democratic.trafford.gov.uk

Follow this further

Built from Trafford's papers

What the report saysPro

Report to Executive

Summary

The report requests in principle approval to the use of compulsory purchase powers to deliver the regeneration of the Cornbrook Hub Site

Recommendation(s)

The Executive is recommended to: 1. Endorse the approach to the delivery of the Cornbrook Hub Site as set out in this Report; 2. Provide in principle approval to the use of compulsory purchase powers to deliver the regeneration of the Cornbrook Hub Site; 3. Request that, in the event of compulsory acquisition becoming expedient for the regeneration of the area, officers shall bring a further report to the Executive.

4 Authorise the service of Requisition for Information upon all owners, occupiers and those with any other interests in the Cornbrook Hub site pursuant to Section 16 of the Local Government (Miscellaneous Provisions) Act 1976; and 5 Authorise the Corporate Director for Economic Growth, Environment and Infrastructure and Director of Legal and Democratic Services to negotiate and complete an appropriate CPO Indemnity Agreement with Manchester Ship Canal Developments Limited to secure all the costs associated with the making of the Order (if required) and the acquisition of all remaining third party interests in the Cornbrook Hub Site including compensation costs as set out in section 5 of the report. 6 In the event that such an Indemnity Agreement is concluded, authorise the Corporate Director for Economic Growth, Environment and Infrastructure to negotiate the acquisition of all interests in the site, in advance of confirmation of a CPO, as if such CPO had been confirmed.

Contact person for access to background papers and further information:

Name: Richard Roe 1 Extension: 4265

Background Papers: None Implications:

Relationship to Policy This report relates to the corporate priority for Framework/Corporate Priorities economic growth and development and will support the delivery of a strategic regeneration site. Financial Any costs associated with the CPO process will be underwritten in full by the developer.

Legal Implications All owners, occupiers and those with any other interests in the Cornbrook Hub site will be served with a Requisition for Information pursuant to Section 16 of the Local Government (Miscellaneous Provisions) Act 1976. This is to ensure that all parties affected by the proposed CPO are correctly identified before the CPO is made.

A CPO Indemnity Agreement will be entered into with Manchester Ship Canal Developments Limited to secure the funding needed (including all costs incurred by the Council which also includes officer time) to acquire all remaining third party interests in the Cornbrook Hub Site.

Equality/Diversity Implications No direct implications Resource Implications e.g. Staffing No direct implications / ICT / Assets Risk Management Implications No direct implications Health & Wellbeing Implications Not applicable. Health and Safety Implications Not applicable.

Background

1.1The Cornbrook Site is situated on the fringe of Manchester city centre close to the Bridgewater Canal and railway lines that link the city centre with other parts of the regional centre within Salford and Trafford. Whilst the area has many attributes, including the presence of a metrolink station and has benefitted from some development, principally residential-led, it is unlikely that significant and comprehensive change can or will take place here in the absence of a co-ordinated approach to its regeneration.

1.2The Cornbrook Hub regeneration site falls within the boundaries of both Trafford and Manchester. Manchester Ship Canal Developments (MSCD) which is owned by Peel has a significant landholding in the Cornbrook area and they propose to develop large scale residential schemes around the Pomona area in Trafford.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CORNBROOK HUB COMPULSORY PURCHASE ORDERReport 141 KB DownloadRead as text
PDF
Cornbrook Appendix 1 Masterpln Cornbrook Hub ProposalsAppendix 707 KB Download
PDF
Cornbrook Appendix 2 Pomona Island Draft Phasing PlanAppendix 4.2 MB Download

At this meeting

Whole meeting

Who was there

22 of 23 attended
SA
Councillor Sean AnsteeChair, present
ML
Councillor Mrs. Laura EvansCommittee Member, present
MH
Councillor Michael Hyman J.P.Committee Member, present
JL
Councillor John LambCommittee Member, apologies
PM
Councillor Patrick MyersCommittee Member, present
JR
Councillor John ReillyCommittee Member, present
AW
Councillor Alex WilliamsCommittee Member, present
MY
Councillor Michael YoungVice-Chair, present
SA
Councillor Stephen AdsheadGuest, present
RB
Councillor Raymond Bowker MBEGuest, present
MC
Councillor Mike CordingleyGuest, present
MC
Councillor Michael CornesGuest, present

All 23 on the meeting page

On this subject at Trafford

Search all
  1. CORNBROOK HUB COMPULSORY PURCHASE ORDERThis decision
  2. Proposed cornbrook hub compulsory purchase orderApproved
  3. Cornbrook hub strategic regeneration frameworkApproved
  4. Cornbrook hub strategic regeneration frameworkDecided

More from Trafford Executive

All decisions
MeetingDecisionOutcome
21 Sep 2026 Greater Manchester End to End Fostering Recruitment Hub1) That the national and Greater Manchester context supporting the developments of the Greater Manchester End-to-End ... Approved Open
21 Sep 2026 Sale Waterside Private Finance Initiative Exit1) That the hand back of the Sale Waterside PFI assets to Council ownership on expiry of the PFI contract on 28 th Oc... Approved Open
20 Jul 2026 Wharfside Strategic MasterplanThat the Executive: (i) Approves the draft Trafford for consultation. (ii) (ii) Delegates authority to the Corporate ... Approved Open
20 Jul 2026 Local Plan Regulation 19 Consultation ApprovalThat the Executive: (i) Approves the Trafford Local Plan (Publication Version) 2026, including allocations, designati... Approved Open
15 Jun 2026 Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2... Noted Open