Resolved
That the amendments to the 2015/16 Capital Investment Programme be approved. 2. That the monitoring report be noted.
Executive approved this item on Monday 16 November 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
That the amendments to the 2015/16 Capital Investment Programme be approved. 2. That the monitoring report be noted.
This report summarises the budget position for the period to 30 September 2015. The salient features are: The updated 2015/16 budget approved in July 2015 was £44.3m. Taking into account minor amendments in the second quarter the programme remains at £44.3m. Capital expenditure to date is £13.5m, being 31% of the budget with an outturn projection for 2015/16 of £40.6m. (see Appendix 2 for detail by service area).
Recommendation(s)
1. That the amendments to the 2015/16 Capital Investment Programme be approved.
2. That the monitoring report be noted.
Contact person for access to background papers and further information: Name: Mark Hughes Extension: 2072 Implications: Relationship to Policy Value for Money Framework/Corporate Priorities Capital expenditure to be been contained within Financial available resources in 2015/16. Legal Implications: None arising out of this report Equality/Diversity Implications None arising out of this report Sustainability Implications None arising out of this report Staffing/E-Government/Asset A number of improvement schemes are being Management Implications undertaken in 2015/16. Risk Management Implications Not Applicable A number of schemes are being undertaken in Health and Safety Implications 2015/16 on the grounds of health and safety.
1. Capital Investment Programme Update
1.1This report summarises the current position and progress of the 2015/16 Capital Investment Programme and its’ financing as at 30 September 2015. It takes into account both financial and scheme progress monitoring undertaken with service area project officers.
1.2Capital expenditure in 2015/16 is currently estimated at £44.3m which is the same as the budget estimate agreed in the Q1 Monitor Report in July 2015.
1.3The TfGM funded City Cycle Ambition initiative is now close to completion and the final costs are lower than originally budgeted. As a result of this reduced requirement the level grant support has been reduced by £149k.
1.4In partnership with the Trafford Clinical Commissioning Group (CCG) the Council has agreed to develop Davyhulme Library into a Doctor’s Surgery, which the CCG will then lease. The CCG has agreed to fund the refurbishment, which is estimated to cost £300k. To date £70k of this funding has been confirmed. A budget to this value has been added to the Capital Programme and will be increased, up to £300k, as the CCG confirms the funding.
1.5Two grant awards have been received to support additional investment in Sustainability and Greenspace projects: Longford Park, Stretford - £10k: A grant from Trafford Housing Trust to support the continued development of the park. Countryside Infrastructure - £20k: A Land Fill Tax grant has been awarded to support improvements to the Trans Pennine Trail at the Lesley Road area of Stretford.
2 Resourcing
2.1The chart below shows the types and levels of resource available to finance the Capital Investment Programme. Internal funding of £11.2m equates to 25% of the total funding requirement, whilst external funding makes up the balance of £33.1m with 80% of this being government grants (£26.6m). 2.2 The current estimate of capital receipts has been updated to reflect the latest information from the Land Sales Programme (LSP). The table below shows the current value of estimated capital receipts available to support the capital budget has increased by £0.2m compared to the position reported in the Q1 Monitor Report as a result of a new site being added to the programme. Therefore the overall position remains the same as a surplus of £2.8m.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CAPITAL INVESTMENT PROGRAMME MONITORING 2015/16 2ND QUARTER (APRIL: SEPTEMBER)Report | 193 KB | DownloadRead as text |
Follow Executive at Trafford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Sep 2026 | Greater Manchester End to End Fostering Recruitment Hub1) That the national and Greater Manchester context supporting the developments of the Greater Manchester End-to-End ... | Approved | Open |
| 21 Sep 2026 | Sale Waterside Private Finance Initiative Exit1) That the hand back of the Sale Waterside PFI assets to Council ownership on expiry of the PFI contract on 28 th Oc... | Approved | Open |
| 20 Jul 2026 | Wharfside Strategic MasterplanThat the Executive: (i) Approves the draft Trafford for consultation. (ii) (ii) Delegates authority to the Corporate ... | Approved | Open |
| 20 Jul 2026 | Local Plan Regulation 19 Consultation ApprovalThat the Executive: (i) Approves the Trafford Local Plan (Publication Version) 2026, including allocations, designati... | Approved | Open |
| 15 Jun 2026 | Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.