STAR Joint Committee approved this item on Wednesday 20 July 2016. Below is the council's own wording, with the papers it was decided on.

Item11

Resolved

That the revised Contract Procedure Rules be endorsed by the Joint Committee and referred to each Council for their approval and incorporation into their respective Constitutions.
Word for word from the decision Trafford published for this meeting. Source: democratic.trafford.gov.uk

Follow this further

Built from Trafford's papers

What the report saysPro

Report to STAR Joint Committee

Summary

The purpose of this report is to set out proposed amendments to the harmonised CPRs currently adopted into each Council Constitution and the request agreement to these revisions

Recommendations

The recommendation of this report is that the Joint Committee approves the revised CPRs provided at Appendix 2 and recommends that the revised CPRs are incorporated into the relevant Constitution of each Council

Contact person for access to background papers and further information:

Name: Sharon Robson Phone: [phone removed]

STAR Procurement is the shared procurement service for Stockport, Trafford and Rochdale Councils Page 2 of 48

Background

Financial Impact: None Legal Impact: Amendments to the Contract Procedure Rules will need to be formally adopted by each Council in accordance with its procedures for amendment of its Constitution Human Resources Impact: None Asset Management Impact: None E-Government Impact: None Risk Management Impact: None Health and Safety Impact: None

Consultation

No public consultation required

Reasons for Recommendation(s)

1.1The harmonised CPRs were adopted into the Constitution of each Council in 2015 and the Joint Committee requested a review of the CPRs in 2016. The project to adopt harmonised rules was a substantial and significant piece of work completed by the CPR working group which consisted of Legal and Finance Offices from each of the three Councils. .

1.2Response to the CPRs as adopted in 2015 has been overwhelmingly positive and reflects the rigour with which the initial review was undertaken. It was always planned to have an overview after the initial year of operation. STAR Procurement has canvassed opinion from key users and has collated feedback from customer surveys to inform the proposed revisions.

1.3STAR Legal, in conjunction with STAR Procurement, has reviewed all suggested amendments and condensed these into a series of proposals that are provided in Appendix 1 and has then made the required amendment to the text of the CPRS and this amended text with tracked changes is provided in Appendix 2

1.4In some instances we have proposed that the CPRs are amended, in others and in order to ensure that the CPRs are “future proof” we propose to add

STAR Procurement is the shared procurement service for Stockport, Trafford and Rochdale Councils Page 3 of 48

further guidance to the Procurement Handbook. We have also amended the Procurement Policy referenced in the original document to the Procurement Handbook where all supporting information is contained for users.

1.5The Joint Committee is empowered to consider the CPRs under which the participating Councils will operate. Subject to agreement by the Joint Committee, each Council will separately consider the proposed amendments and decide whether to alter its Constitution to incorporate the revised Rules. Until each Council has adopted the revised Rules, STAR will operate on the existing harmonised rules (Appendix 1 lists the proposed changes via tracked changes).

2. Key Proposed CPR Amendments

2.1Authority to procure. This amendment will reinforce the requirement for officers to ensure that they have the authority to procure from the outset, as the procurement process commences with submission of a Procurement Initiation Document (PID) and STAR Procurement acts on this PID

2.2Framework Agreements. The CPRs are unclear as to whether an exemption report is required when calling off goods services or works from a framework contract. The original intention was that call off from a properly procured framework would fall within the Rules and therefore not require the completion of an exemption form. The proposed amendment removes the ambiguity.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Contract Procedure RulesReport 420 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

3 of 3 attended
AB
Councillor Allen BrettChair, present
PM
Councillor Patrick MyersCommittee Member, present
DS
Councillor David SedgwickVice-Chair, present

On this subject at Trafford

Search all
  1. Contract Procedure RulesThis decision
  2. Contract procedure rules update - procurement legislationNoted
  3. Contract Procedure rulesApproved
  4. Contract Procedure RulesApproved
  5. Contract procedure rules (cprs)Noted
  6. Contract procedure rulesNoted

More from Trafford STAR Joint Committee

All decisions
MeetingDecisionOutcome
21 Mar 2025 Q3 performance and 2025/26 performance measures1) That the Committee agrees the STAR Key Performance Measures and Targets for 2025/26. 2) That the report be noted. Agreed Open
21 Mar 2025 Procurement act 2023 implementation update1) That the report be noted. Noted Open
21 Mar 2025 Q3 budget position - 3 year budget forecast and 2025/26 budget settingRESOLVED – That the Committee agrees the recommendations set out in the report. Agreed Open
15 Jun 2022 Membership of the committee 2022/23 including chairman and vice-chairmanThat at the start of the new Municipal Year the new chair nominated the vice chair and new membership be noted. Noted Open
15 Jun 2022 Quarter 4 5-star performance 2021/22(1) That the content of the report and performance to the end of Quarter 4 be noted. (2) That the Joint Committee con... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies