1. Full Year Position
1.1Position The final full year position on the Balanced Scorecard for 15/16 is very positive, STAR have met either the targets set in April 15 by the Board and Joint Committee or the October 15 revised targets.
1.2Revised Targets o C3 (planned exemptions) is a target increased from 50% to 60% in October 15, the final position for STAR is 71.6%
o C4 (filed contractual documents) is a target that was reduced in October 15 from 100% to 80%, the final position for STAR is 88.4%
o F2 (PIDS representing Savings) is a target that was increased in October 15 from 90 % to 100%, the final position for STAR is 100%
o S1 (social value (SV)) is a target that was reduced in October 15 from 50% to 40%, the final position for STAR is 58.2%
STAR Procurement is the shared procurement service for Stockport, Trafford and Rochdale Councils o S4 (Spend with SME’s) is a target that was reduced in October 15 from 10% to 9%, the final position for STAR is 34% o S5 (tender exercises with measureable SV outcomes) is a target that was reduced in October 15 from 40% to 30%, the final position for STAR is 32%
o P1 (Customer Satisfaction) is a target that was increased in October 15 from 50% to 85% , the final position for STAR is 85%
1.3Original Targets All targets that were not revised in October 15 have been met or exceeded, highlights for STAR are: o C5 (planned procurements) the target set in April 15 was 65%, the final position for STAR is 88.2%
o S3 (local spend) the target set in April 15 was 30%, the final position for STAR is 34.3%
1.4The DOP (Director of Procurement) and SMT (Senior Management Team) are very proud of the performance for 15/16 in particular the improvements made in the final quarter of the year.
1.5The new balanced scorecard for financial year 16/17 is now established the new metric and measuring systems are being utilised. The revised metrics being measured are:
Finance 40% Compliance 30% Social Value 20% Performance/Customer service 10%
2.1The final position reflects the progress made by STAR on delivering the objectives of the Joint Committee and the STAR Board. All targets have been met or exceeded.
2.2STAR have taken some learning from the 15/16 scorecard and enhanced the reporting going into 16/17 in terms of Social Value and how the report is presented.
STAR Procurement is the shared procurement service for Stockport, Trafford and Rochdale Councils Appendix 1: April 16 Balanced Scorecard
Compliance (Weighting 30%) STAR
Measure ment Revised Forecast Ref Metric Target Weighting Achieved Score Period October 2015
Number of contracts in the work plan C1 awarded without a successful legal Annually 100% 100% 5% 100.0% 5.00 challenge against the total number of % of ‘live’ / compliant contracts in the C2 Contracts Register against the total number Annually 90% 90% 10% 92.9% 10.00 of contracts in the Contracts Register % of planned exemptions to the Contract C3 Procedure Rules against the total number of Annually 50% 60% 5% 71.6% 5.00 exemptions % of signed contractual documents filed on C4 The Chest within 12 weeks form Contract Annually 100% 80% 5% 88.4% 5.00 Award % of planned procurement activities in the C5 work plan against the total number of work Annually 65% 65% 5% 88.2% 5.00 plan activities. Compliance Score > 30/30
Finance (Weighting 40%)
F1 % of achieved savings against target Annually 90% 100% 35% 100.0% 35.00
% of PIDs with Savings represented F2 Annually 90% 100% 5% 100.0% 5.00 against all signed PIDs Finance Score > 40/40
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2015/16 Balanced Scorecard Final PositionReport | 137 KB | DownloadRead as text |
Follow STAR Joint Committee at Trafford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Mar 2025 | Q3 performance and 2025/26 performance measures1) That the Committee agrees the STAR Key Performance Measures and Targets for 2025/26. 2) That the report be noted. | Agreed | Open |
| 21 Mar 2025 | Procurement act 2023 implementation update1) That the report be noted. | Noted | Open |
| 21 Mar 2025 | Q3 budget position - 3 year budget forecast and 2025/26 budget settingRESOLVED – That the Committee agrees the recommendations set out in the report. | Agreed | Open |
| 15 Jun 2022 | Membership of the committee 2022/23 including chairman and vice-chairmanThat at the start of the new Municipal Year the new chair nominated the vice chair and new membership be noted. | Noted | Open |
| 15 Jun 2022 | Quarter 4 5-star performance 2021/22(1) That the content of the report and performance to the end of Quarter 4 be noted. (2) That the Joint Committee con... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.