Resolved
1) That the report be noted. 2) That the changes to the Risk Register, as recommended in the report, be agreed.
STAR Joint Committee noted this item on Monday 21 August 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
1) That the report be noted. 2) That the changes to the Risk Register, as recommended in the report, be agreed.
Joint Committee notes the content of the Risk Register provided and approves the changes highlighted in this report
Contact person for access to background papers and further information:
Name: Mark Pearson Phone: [phone removed]
Financial Impact: None Legal Impact: None Human Resources Impact: None Asset Management Impact: None E-Government Impact: None Risk Management Impact: Subject matter of the report comprises the current risk management status for STAR Procurement Health and Safety Impact: None
STAR Procurement is the shared procurement service for Stockport, Trafford and Rochdale Councils Consultation
No public consultation required
Reasons for Recommendation(s)
The risk register is issued for information and the Joint Committee is asked to approve proposed changes. The Joint Committee will be able to query any aspect of the risk register during the course of the Joint Committee Meeting
1.1In the period, one risk has been downgraded. Mitigation comments have been reviewed and amended where appropriate
2. Changes to the Risk Register Entries
2.1P007 – Income generation opportunities impacting on service delivery Risk downgrade; this risk is now addressed in the 2017-20 Business Plan and STAR ensures that additional resources are made available to address income-generation workload to ensure that service delivery is not affected. The recommendation is for this risk to be downgraded
3.1It is recommended that the STAR Joint Committee notes the content of the risk register and approves the changes highlighted in this report
Appendix 1
STAR Procurement Risk Register v13 dated 9 August 2017
STAR Procurement is the shared procurement service for Stockport, Trafford and Rochdale Councils Appendix 1: STAR Risk Register
Risk Register Version: 13 Issue Date: 21 August 2017 Document Owner: Mark Pearson, Business Improvement Manager
Summary Risk Description & Impact Preventative Actions Date Prob Impact Score Risk ID Status Type Description of risk / impact Mitigating actions / Countermeasures Raised (1-3) (1-3) (P x I) Owner
F005 17 Sep 14 On going Finance Not able to balance cost savings against "local 2 2 4 This risk is addressed in the STAR Business Plan2017-20. Local spend will be delivered through each Board / agenda" aspirations of the Five Cs of this Plan and is specifically referenced in Communities. By way of example, a pilot DoP / project in Rochdale - 'Buy Local' will be delivered in 2017-18 before being rolled out across Stockport HoSPs / CMs and Trafford P003 17 Sep 14 On going Process & STAR Procurement Contract Register does not 2 2 4 STAR Procurement has obtained influenceable spend date from each Council and has identified on- HoSPs / Resources include all contracting activity and off-contract spend with the top 300 suppliers for each Council. Combined with budget CMs holder/stakeholder identification, STAR category managers are now better positioned to identify contracts missing from the STAR Contracts Register and their new Category Plan implementation will improve contract knowledge and data capture
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
STAR Risk RegisterReport | 261 KB | DownloadRead as text |
Follow STAR Joint Committee at Trafford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Mar 2025 | Q3 performance and 2025/26 performance measures1) That the Committee agrees the STAR Key Performance Measures and Targets for 2025/26. 2) That the report be noted. | Agreed | Open |
| 21 Mar 2025 | Procurement act 2023 implementation update1) That the report be noted. | Noted | Open |
| 21 Mar 2025 | Q3 budget position - 3 year budget forecast and 2025/26 budget settingRESOLVED – That the Committee agrees the recommendations set out in the report. | Agreed | Open |
| 15 Jun 2022 | Membership of the committee 2022/23 including chairman and vice-chairmanThat at the start of the new Municipal Year the new chair nominated the vice chair and new membership be noted. | Noted | Open |
| 15 Jun 2022 | Quarter 4 5-star performance 2021/22(1) That the content of the report and performance to the end of Quarter 4 be noted. (2) That the Joint Committee con... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.