Resolved

That agreement be given to progress the proposed option for Urmston Leisure Centre for refurbishment & extension at a cost of up to £6.4m financed as set out in paragraph 3 of the report. 2. That agreement be given that the additional borrowing of £1.15m to fund the scheme be included as part of the 18/19 budget proposals. 3. That it be noted that that steps are being taken to explore further options and opportunities in relation to Sale Leisure Centre, to be brought back to a future meeting of the Executive.
Word for word from the decision Trafford published for this meeting. Source: democratic.trafford.gov.uk

Follow this further

Built from Trafford's papers

What the report saysPro

Report to Executive

Summary

Following the decision of the Executive in November 2016 to invest £24.39m in improving a number of Leisure Centres this report sets out the detail for the proposed refurbishment of Urmston Leisure Centre and an update on proposals in relation to Sale Leisure Centre.

Recommendation(s):

That the Executive;

1) Agrees to progress the proposed option for Urmston Leisure Centre for refurbishment & extension at a cost of up to £6.4m financed as set out in paragraph 3 of the report.

2) Agrees that the additional borrowing of £1.15m to fund the scheme, be included as part of the 18/19 budget proposals.

3) Notes that steps are being taken to explore further options and opportunities in relation to Sale Leisure Centre, to be brought back to a future meeting of the Executive.

Financial Impact: Estimated capital investment in the Council’s leisure centres to be financed from a combination of capital receipts, and borrowing. It is intended that any associated financing costs will be recovered from Trafford Leisure CC Ltd and 1 where appropriate also provide an additional income stream to support the future revenue budget.

Legal Impact The immediate steps which will be required to be taken as a consequence of the approval of these recommendations are those related to the negotiation and finalisation of a new operating agreement to be entered into between the Council and Trafford Leisure CIC to cover the income stream to be received by Trafford Council from Trafford Leisure CIC.

Human Resources Impact: With investment and growth in leisure centre usage, there is potential to create a greater number of local jobs and apprenticeships.

Asset Management Impact: See report

E-Government Impact: None

Risk Management Impact: See report

Health and Safety Impact: See report

Contact person for access to background papers and further information:

Name: Joanne Hyde Extension: 0161 912 4009

Background papers

Executive reports and papers from the Executive Decision November 2016

2 1 Background

1.1At a meeting of the Executive in November 2016 a decision was made to approve a capital investment of £24.39m to improve Sale, Urmston, Stretford and Altrincham Leisure Centres. It was also agreed that further reports should be brought back to the Executive to seek approval for any investment, provided that such proposals demonstrated sufficient income growth to fund the capital costs.

1.2Further work has been undertaken in order to present schemes in relation to Urmston and Sale Leisure Centres. Gardiner & Theobald project management consultants (G&T) were procured under the terms of the Executive approval to provide project management support to these projects.

1.3In addition G&T appointed a design team and specialist surveyors to work alongside them supporting this work. Trafford Leisure CIC (“Trafford Leisure”) has been involved as part of the project team to ensure the development of appropriate revenue opportunities were considered to compliment the designs and increase future income profiles.

2 Urmston Leisure Centre

2.1In November 2016, following the development of a commercial prospectus that reviewed the business of Trafford Leisure and the leisure assets currently owned by the Council, a proposal was brought forward to invest £2.1m in the development and improvement of Urmston Leisure Centre which included a number of condition works.

2.2The detail of the proposals contained in that scheme included:

 £767k of condition works;

 A modern fitness suite, updated pool viewing area, new multi-use studio carved out from the sports hall, new dance studio, new toning room along with flexible wellness room;

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
LEISURE CENTRE REDEVELOPMENTSReport 448 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

21 of 25 attended
SA
Councillor Sean AnsteeChair, apologies
AW
Councillor Alex WilliamsVice-Chair, present
SA
Councillor Stephen AnsteeCommittee Member, present
ML
Councillor Mrs. Laura EvansCommittee Member, apologies
DH
Councillor David HoppsCommittee Member, present
JL
Councillor John LambCommittee Member, present
PM
Councillor Patrick MyersCommittee Member, present
JR
Councillor John ReillyCommittee Member, apologies
MW
Councillor Michael WhettonCommittee Member, present
SA
Councillor Stephen AdsheadGuest, present
ML
Councillor Miss Linda BlackburnGuest, present
DB
Councillor Dylan ButtGuest, present

All 25 on the meeting page

On this subject at Trafford

Search all
  1. LEISURE CENTRE REDEVELOPMENTSThis decision
  2. Approval to complete a community asset transfer (cat) for george h carnall leisure centre (ghc) with effect 4th january 2021Approved
  3. Re-designation of the Leisure Centre Refurbishment Earmarked ReserveApproved
  4. Proposed community asset transfer for george h. carnall leisure centreApproved
  5. Application for planning permission 95501/ful/18 - urmston leisure centre, bowfell road, urmstonDecided
  6. Application for planning permission 95501/ful/18 - urmston leisure centre, bowfell road, urmstonDeferred

More from Trafford Executive

All decisions
MeetingDecisionOutcome
21 Sep 2026 Greater Manchester End to End Fostering Recruitment Hub1) That the national and Greater Manchester context supporting the developments of the Greater Manchester End-to-End ... Approved Open
21 Sep 2026 Sale Waterside Private Finance Initiative Exit1) That the hand back of the Sale Waterside PFI assets to Council ownership on expiry of the PFI contract on 28 th Oc... Approved Open
20 Jul 2026 Wharfside Strategic MasterplanThat the Executive: (i) Approves the draft Trafford for consultation. (ii) (ii) Delegates authority to the Corporate ... Approved Open
20 Jul 2026 Local Plan Regulation 19 Consultation ApprovalThat the Executive: (i) Approves the Trafford Local Plan (Publication Version) 2026, including allocations, designati... Approved Open
15 Jun 2026 Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2... Noted Open