RESOLVED – (1) That the forecast revenue budget underspend of £326k be noted. (2) That the additional £600k investment in the highways which has been made possible by the overachievement of income on garden waste collection, as detailed in table 2 to the report, be noted. (3) That the changes to the Capital Programme, as detailed in paragraph 17 of the report, be noted.
Word for word from the decision Trafford published for this meeting.Source: democratic.trafford.gov.uk
The purpose of this report is to inform Members of the current 2017/18 forecast outturn figures relating to both Revenue and Capital budgets. It also summarises the latest forecast position for Council Tax and Business Rates within the Collection Fund.
Recommendation(s)
It is recommended that: a) the Executive note the forecast revenue budget underspend of £326k b) the Executive note the additional £600k investment in the highways which has been made possible by the overachievement of income on garden waste collection as detailed in table 2. c) The executive note the changes to the Capital Programme as detailed in paragraph 17.
Contact person for access to background papers and further information:
David Muggeridge, Finance Manager, Financial Accounting Extension: 4534
Background Papers: None
Relationship to Policy Value for Money Framework/Corporate Priorities
Financial Revenue and Capital expenditure to be contained within available resources in 2017/18. Legal Implications: None arising out of this report Equality/Diversity Implications None arising out of this report Sustainability Implications None arising out of this report Resource Implications e.g. Staffing Not applicable / ICT / Assets Risk Management Implications Not applicable
1 Health & Wellbeing Implications Not applicable
Health and Safety Implications Not applicable
Other Options
Not Applicable
Consultation
Not Applicable
Reasons for recommendation
Not Applicable
Finance Officer Clearance …GB…………… Legal Officer Clearance DA
CORPORATE DIRECTOR’S SIGNATURE …… ……
2 REVENUE BUDGET
Budget Monitoring - Financial Results
1. The approved budget agreed at the 22 February 2017 Council meeting is £160.83m. In determining the budget an overall gap of £25.37m was addressed by a combination of additional resources of £9.80m, including projected growth in business rates, council tax and use of general reserve and £15.57m of service savings and additional income. 2. Based on the budget monitoring for the first 4 months the year end forecast outturn is an underspend of £326k, an adverse movement of £548k since Period 2. This overall position reflects the active process of prudent budget management as managers are acutely aware of the overall budget position of the Council. This position also takes into account planned additional investment in the Council’s highways of £600k due to the positive position of the EGEI budget (See Table 2). At this stage caution should be exercised as the projections are based on a number of assumptions including delivery of the significant savings programme in year (see para 8), the ongoing risk to business rate income (see para 15) and the stability of demographic pressures in social care. 3. Detailed below in Table 1 is a summary breakdown of the service and funding variances against budget, with Table 2 providing an explanation of the variances:
Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.