That approval be given to the inclusion of the following Trafford HIF schemes and their funding allocations onto the Council’s Capital Programme in terms of: o Junction improvement works on Trafford Way and Redclyffe Road at the Trafford Waters site. o The Carrington Relief Road, including site rationalisation works at the Future Carrington site and note the funding allocated via Growth Deal 3. 2. That authority be delegated to the Corporate Director of Place to agree terms with Homes England and the relevant developers for the draw down of HIF funding to support housing delivery at the Trafford Waters and Future Carrington sites. 3. That authority be delegated to the Corporate Director for Governance and Community Strategy to enter into legal agreements as required in order to implement the above recommendations
Word for word from the decision Trafford published for this meeting.Source: democratic.trafford.gov.uk
The Council has received conditional approval for funding via the Housing Infrastructure Fund (HIF) at the Trafford Waters and Future Carrington sites. This report seeks approval for the inclusion of the Trafford HIF schemes in the Council’s Capital Programme.
Recommendation(s)
It is recommended that the Executive:
(i) Approves the inclusion of the following Trafford HIF schemes and their funding allocations onto the Council’s Capital Programme in terms of: o Junction improvement works on Trafford Way and Redclyffe Road at the Trafford Waters site.
o The Carrington Relief Road, including site rationalisation works at the Future Carrington site and note the funding allocated via Growth Deal 3. (ii) Delegates authority to the Corporate Director of Place agree terms with Homes England and the relevant developers for the draw down of HIF funding to support housing delivery at the Trafford Waters and Future Carrington sites.
(iii) Delegates authority to the Corporate Director for Governance and Community Strategy to enter into legal agreements as required in order to implement the above recommendations.
Contact person for access to background papers and further information:
Name: Mike Reed, Strategic Growth Manager Extension: x 4924
Background Papers: None
1 Implications:
Relationship to Policy Delivery of the Trafford Housing Infrastructure Framework/Corporate Priorities schemes at Trafford Waters and Carrington will support the delivery of the Council’s Corporate Plan (2019), including the priorities Building Quality, Affordable and Social Housing, Health and Wellbeing, Green and Connected, and Successful and Thriving Places. Relationship to GM Policy or Delivery of the schemes will support the growth Strategy Framework ambitions articulated within the emerging Greater Manchester Spatial Framework and the GM Strategy. The schemes will be delivered in the context of the GM 2040 Transport Strategy, GM Congestion Plan, and Made to Move walking and cycling plan to identify improvements tackling traffic congestion, promote sustainable modes of travel and better integrate transport and new developments. Financial The estimated capital cost of the infrastructure proposals is £6.45m for Trafford Waters and £32.8m for Future Carrington to be financed by a range of capital grants and external contributions as detailed in the report.
Until formal grant approval is obtained from HE in respect of HIF and TfGM in respect of Growth Deal 3 an element of cost is deemed to be at risk but arrangements for this to be fully underwritten by the developers of the respective sites will be formalised before further work on scheme development is undertaken and costs incurred. Legal Implications: As set out in the report. Equality/Diversity Implications None as a consequence of this report. Sustainability Implications The delivery of the schemes will be required to meet current policy in relation to sustainability. Resource Implications e.g. Staffing Existing resources have been identified to support / ICT / Assets the delivery of the schemes and related activity across all the partners. Risk Management Implications The delivery of the schemes will be supported by a risk plan setting out the key risks to delivery and proposed mitigation measures. Health & Wellbeing Implications None as a consequence of this report. Health and Safety Implications None as a consequence of this report.
2 1.0 Background
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.