That the content of the report be noted. 2. That a pproval be given to the Council’s proposed participation within the GM Local Full Fibre Network Programme as detailed in the report. 3. That the Council’s proposed £705,090 capital contribution as detailed within the report be approved. 4. That authority be d elegated to the Corporate Director for Finance and Systems, in consultation with the Corporate Director for Governance and Community Strategy, to agree the terms and conditions of, and enter into all legal documentation associated with, the GM Programme including, but not limited to: a) the Inter Authority Agreement b) the Framework Agreement c) the Delivery Agreement 5. That authority be delegated to the Corporate Director for Place, in consultation with the Corporate Director for Finance and Systems, to add or remove Council buildings from the programme.
Word for word from the decision Trafford published for this meeting.Source: democratic.trafford.gov.uk
Following the successful bid to Government’s Department for Digital Culture Media and Sport (DCMS) for £23.8m Local Full Fibre Networks funding (LFFN) in March 2018 a considerable amount of work has been undertaken to finalise this large complex project. Tameside Council has entered into separate arrangements with DCMS for £2.5M of the GM LFFN funding which builds on an earlier phase of the LFFN Programme for its full fibre programme. The total LFFN programme funding for rest of GM is therefore £21.3M.
The Programme is being overseen by the Full Fibre Programme Board, chaired by the GM Digital Lead Chief Executive, Tony Oakman and overseen by Andrew Western, Digital Portfolio Lead. The timetable for the delivery of this programme is extremely tight. It has to be procured by spring 2019 to ensure that this new full fibre network connecting public sector sites (over 450km) can be constructed within the project timeline. All Government funding has to be expended before the end of March 2021.
The programme requires participating LAs and GMCA (Fire & Rescue Service, TfGM assets) to re- channel existing and future revenue spend on broadband connectivity into upfront capital to fix the costs of access to full fibre for the next 20 years and to confirm respective capital commitments.
The GMCA at its meeting on 27th July 2018 noted the indicative capital funding requirements required to secure DCMS LFFN funding. GMCA also noted the requirement to secure local funding budget approvals. It also recognised the direct funding requirements from GMCA to fund Programme Management and related costs.
An Inter Authority Agreement is proposed to formalise partner participation and secure government grant funding.
The approach to the procurement of the Programme has been optimised to ensure that partners are able to capitalise funding and deliver the best possible value for money.
Recommendations
It is recommended that: Investment of £1.46M capital from GMCA (Fire & Rescue Service) and £3.384M capital from GMCA (TfGM Urban Traffic Management Control) is agreed based on projected revenue costs for connectivity over 20 years as upfront capital.
1 The £21.3m grant DCMS LFFN is allocated between the Districts and the GMCA to maximise full fibre site coverage across each district noting that CA agreement will be sought to the final grant splits following the market response to the procurement. Participating district partners are requested to secure their individual financial investment commitment before the end of March 2019 (set out in Appendix A). The proposed approach to procurement and contract management is agreed. Participating Local Authorities are requested to agree the Inter Authority Agreement to formalise their participation in the GM Full Fibre Programme and secure Government (DCMS) LFFN grant funding. The GM Prospectus is put in place by July 2019 to minimise barriers to investment and reduce roll out costs of utilities works across GM. Local authorities are requested to provide dedicated local management support for the programme
CONTACT OFFICERS: PHIL SWAN, GMCA; JOHN STEWARD, GMCA; RICHARD PAVER GMCA
Background
1.1In March 2018, GM secured 25% of the UK LFFN funding pot to connect over 1300 public sector sites across GM. This will include over 1300 public sector assets. This is expected to encourage further private sector investment of up to £250M and could be worth over £2.1BN1 to the GM economy over the next fifteen years. The LFFN Programme would have a transformational impact on digital infrastructure in GM - leading to an increase of full fibre coverage from 2% now to around 25% within three years. Greater Manchester would then have the best high-speed digital infrastructure coverage of any city-region in the UK.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.