That the outcome of stage 1 and stage 2 of the Strategic Outcomes Planning Model (SOPM) be noted and the undertaking of stages 3 and 4 approved. 2. That a proposed revised leisure strategy be noted in line with a refurbishment programme for the three leisure centres of Altrincham, Sale and Stretford, subject to completion of the SOPM stages 3 and 4 which will be submitted to the Executive in 2021. 3. That it be noted that Trafford is developing an Active Travel Plan for 2021 that will include integrated walking and cycling strategy and connectivity to the leisure estate. 4. That it be noted that as part of the formulation of the capital programme for 2021/24 this will include for the development and delivery of the business case for three Leisure Centre refurbishments, along with essential maintenance works across the leisure estate. 5. That it be approved that Trafford Leisure CIC continue the role of managing Council owned leisure facilities within new Governance arrangements based on a new contract and operating agreement. 6. That authority be delegated to the Corporate Director of Place in consultation with the Corporate Director for Governance and Community Strategy to negotiate and agree the terms of new agreements and leases with Trafford Leisure CIC Limited in relation to the use and operation of the facilities. 7. That authority be delegated to the Corporate Director for Governance and Community Strategy to enter into and sign and/or seal the said agreements and leases on behalf of the Council.
Word for word from the decision Trafford published for this meeting.Source: democratic.trafford.gov.uk
The report sets out a new Strategic Outcomes Planning Model (SOPM), aligning the leisure strategy with the Council’s corporate plan to inform decisions on leisure facilities and services. The report revises the leisure investment strategy to take account of current financial challenges faced by the Council and Trafford Leisure and confirms the preferred management option for its delivery.
Due to significant budget pressures the investment strategy has been reviewed to provide an affordable option that would improve the leisure centre facilities and continue to meet the objective improving health and wellbeing outcomes for a greater number of Trafford residents through increasing levels of physical activity.
Recommendations
That the Executive;
1) Notes the outcome of stage 1 and stage 2 of the SOPM and approves the undertaking of stages 3 and 4.
2) Notes a proposed revised leisure strategy in line with a refurbishment programme for the three leisure centres of Altrincham, Sale and Stretford, subject to completion of the SOPM stages 3 and 4 which will be submitted to the Executive in 2021.
3) Notes that Trafford is developing an Active Travel Plan for 2021 that will include integrated walking and cycling strategy and connectivity to the leisure estate.
4) Note that as part of the formulation of the capital programme for 2021/24 this will include for the development and delivery of the business case for three Leisure Centre refurbishments, along with essential maintenance works across the leisure estate.
1 5) Approve that Trafford Leisure CIC continue the role of managing Council owned leisure facilities within new Governance arrangements based on a new contract and operating agreement.
6) Delegate authority to the Corporate Director of Place in consultation with the Corporate Director for Governance and Community Strategy to negotiate and agree the terms of new agreements and leases with Trafford Leisure CIC Limited in relation to the use and operation of the facilities.
7) Delegate authority to the Corporate Director for Governance and Community Strategy to enter into and sign and/or seal the said agreements and leases on behalf of the Council.
Contact person for access to background papers and further information:
Name: Chris Jennings – Senior Business Change Manager
Contact: [phone removed]
Background Papers: None
Implications
Relationship to Policy Contributes to the Corporate Priorities: Health and Framework/Corporate Priorities Wellbeing, Successful & Thriving Places, Children & Young People and Green & Connected.
Relationship to GM Policy or The decision relates to the GM Moving strategy in Strategy Framework terms of the aim to increase physical activity levels. Financial As part of the formulation of the capital programme for 2021/24 this will include for the development and delivery of the business case for three Leisure Centre refurbishments (the full programme will be approved by Executive in February 2021) as well as essential maintenance works across the leisure estate. It is proposed to start advanced design work on the refurbishment option during this financial year and this will be funded from within the existing approved capital programme for 2020/21. Legal Implications: Early steps will be required in relation to the approval of these recommendations in terms of negotiation and finalisation of a new operating agreement and contract to be entered into between the Council and Trafford Leisure CIC. Equality/Diversity Implications The redevelopments will be DDA compliant and accessible. A revised Equality Impact Assessment to be submitted with each refurbishment design at RIBA Stage 3.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.