RESOLVED - (1) That, f ollowing the successful completion of RIBA stage 2 for Sale Leisure Centre, and an independent review of the income and expenditure, approval be given to the continuation with the proposed capital investment into the design of the refurbishment up to the end of RIBA Stage 3 at a cost of up to £300k. (2) That it be noted that the outcomes of the RIBA Stage 3 report for Altrincham Leisure Centre will be presented to the Executive in July 2022. (3) That it be n oted that, in parallel a full business case review will be undertaken for Stretford Leisure Centre and will be presented to the July 2022 Executive for approval to proceed to RIBA Stage 3.
Word for word from the decision Trafford published for this meeting.Source: democratic.trafford.gov.uk
The report provides an update on the leisure investment strategy and associated refurbishment options for Altrincham, Sale and Stretford Leisure Centres
The report seeks approval to proceed to the next stage in the refurbishment process, RIBA stage 3 for Sale Leisure Centre. This will provide a greater level of cost confidence before seeking Executive approval to progress to planning for Sale Leisure Centre.
Recommendations
That the Executive.
1) Following the successful completion of RIBA stage 2 for Sale Leisure Centre, and an independent review of the income and expenditure, approves the continuation with the proposed capital investment into the design of the refurbishment up to the end of RIBA Stage 3 at a cost of up to £300k
2) Notes that the outcomes of the RIBA Stage 3 report for Altrincham Leisure Centre will be presented to the Executive in July 2022.
3) Notes that, in parallel a full business case review will be undertaken for Stretford Leisure Centre and will be presented to the July 2022 Executive for approval to proceed to RIBA Stage 3.
1 Contact person for access to background papers and further information:
Relationship to Policy Contributes to and supports the revised (2021) Framework/Corporate Priorities Corporate Priorities: Reducing Health Inequalities and Addressing our Climate Crisis. It will also support the Active Travel Strategy. Relationship to GM Policy or The decision relates to the GM Moving strategy in Strategy Framework terms of the aim to increase physical activity levels and GM Gear Change in relation to Active Travel. Financial In February 2022 Executive approved £52.1m into the capital programme to cover the costs of the proposed refurbishment of Altrincham, Sale and Stretford Leisure Centres. The recommendation in this report is to spend c£300k of the approved capital budget to progress the refurbishment proposal to the end of RIBA stage 3 for Sale Leisure Centre. This will provide greater cost and risk certainty and inform the business case to confirm the amount and affordability of the approved capital expenditure.
The spend relating to RIBA stage 3 will be at risk and will be a revenue budget pressure should no refurbishment programme be undertaken.
The revenue budget and reserves approved by Council in February 2022 included support for a full range of leisure provision for 2022/23 and over the medium term. Operating losses in the region of £1.5m in 2021/22 are currently being supported from Council reserves and one-off external funding. The identification and funding of revenue costs to support business disruption during the refurbishment programme will also need to be assessed and considered as part of the ongoing budget setting process. Legal Implications: There are no legal implications in this report Equality/Diversity Implications An Equality Impact Assessment is to be completed with each refurbishment design at RIBA Stage 3. Sustainability Implications The redevelopment designs include the replacement of the fossil fuel (gas) heating system with Air Sourced Heat Pumps and Solar Panels
2 which are both significantly more sustainable options than those within the existing facilities.
The refurbishment option will reduce the carbon omissions compared to a new build development Carbon Reduction The redevelopment designs include the replacement of the fossil fuel (gas) heating system with Air Sourced Heat Pumps and Solar Panels which are both significantly more sustainable options than those within the existing facilities.
The refurbishment option will reduce the carbon omissions compared to a new build development.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.