Resolved
RESOLVED – That the content of the report be noted.
Accounts and Audit Committee noted this item on Thursday 22 July 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the content of the report be noted.
The Accounts and Audit Committee is asked to consider this report which provides an update on the strategic risk environment, setting out developments relating to the management of each of the Council’s strategic risks.
The Accounts and Audit Committee notes the report.
Contact person for access to background papers and further information:
Mark Foster – Audit & Assurance Manager. Email: [email protected] Peter Morris – Senior Audit & Assurance Officer. Email: [email protected]
Background Papers: None
Strategic Risk Register Report – July 2021 Page 1 1. INTRODUCTION
1.1The Council’s Strategic Risk Register (SRR) contains the strategic risks the Council is likely to face in achieving its high level corporate objectives.
1.2In accordance with the Council’s Risk Management Policy, the Corporate Leadership Team (CLT) provides regular periodic updates on the strategic risk environment and in particular performance in managing the specific risks incorporated within the SRR.
1.3This report is based on information provided by risk owners in June/July 2021 for each risk unless otherwise stated.
2. THE STRATEGIC RISK ENVIRONMENT – RISK EXPOSURE AND PERFORMANCE MANAGEMENT
2.1The Audit & Assurance Service liaised with CLT and senior managers to agree the risks to be included in the strategic risk register and provide updates on risks under their remit, including progress in managing these risks. Section 3 of this report contains an update on the strategic risks previously reported in March 2021. Where applicable, risks have been updated in light of developments in respect of the COVID-19 pandemic.
2.2The risk chart below shows an analysis of the current strategic risks. The chart analyses the levels of risk exposure in terms of impact and likelihood. The number of strategic risks for each risk level is shown. There are currently 15 strategic risks (there were 16 in March 2021 – see 2.5 below re: removal of UA92 risk). For each risk listed in Section 3, this includes the relevant Executive Portfolio and Service Directorate.
2.3Since March 2021, there has been an increase in one of the risk scores. This relates to the following:
Risk 5 – Demand for School Places has changed from a score of 15 (Medium) to a score of 20 (High). This reflects the increase in demand for school places in recent months, particularly in the Sale and Altrincham areas.
2.4There has been a decrease in score for the following risk: Risk 9 – Breach of Health and Safety has changed from a score of 20 (High) to a score of 15 (Medium).
Further information on the above risks are provided in Section 3.
2.5The UA92 project has moved on substantially since it was initially added to the Strategic Risk Register. UA92 have now signed a lease and taken occupation of two floors of the former Kellogg’s building, and are recruiting for their third intake of students. UA92 was envisaged as a catalyst for regeneration in Old Trafford and Clifford, and these plans have also progressed. Outline planning permission has
Strategic Risk Register Report – July 2021 Page 2 been achieved for the Lumina Village development and the Civic Quarter Area Action Plan is progressing. In Stretford a Joint Venture between the Council and Bruntwood have acquired Stretford Mall, and are bringing forward proposals for the redevelopment of the Mall and an Area Action Plan for the wider town centre. Whilst there is still much work to be done the risks associated with UA92 have been addressed and it is therefore appropriate to move this from the Strategic Risk register to the Place Directorate register.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
STRATEGIC RISK REGISTER UPDATE REPORTReport | 617 KB | DownloadRead as text |
Follow Accounts and Audit Committee at Trafford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Mar 2022 | MINUTESRESOLVED – That the Minutes of the Meeting held on 2 nd February 2022 be approved as a correct record and signed by t... | Approved | Open |
| 22 Mar 2022 | 2021/22 annual governance statement - approach / timetableRESOLVED - (1) That the timetable / action plan be noted. (2) That it be noted that the Committee would have input in... | Noted | Open |
| 22 Mar 2022 | Audit progress reportRESOLVED – That the content of the report be noted. | Noted | Open |
| 22 Mar 2022 | Budget monitoring report 2021/22 - period 10 (april 2021 - january 2022RESOLVED – That the updated positions on the revenue budget, collection fund and capital programme, and the observati... | Noted | Open |
| 22 Mar 2022 | Accounting concepts and policiesRESOLVED - (1) That the accounting concepts and policies that will be used in completing the 2021/22 annual accounts ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.