RESOLVED - (1) That the outcome of the public engagement process be noted. (2) That Option F be approved as the route for the new Carrington Relief Road and that the Corporate Director of Place be authorised to: a. engage external resources where this will assist in implementing the relief road, including a professional team where reasonably required. b. Commission, submit and/or authorise as appropriate: i ) an application for planning permission to deliver the relief road; and ii) any surveys/investigations where such surveys will reduce risks and/or assist with the preparation, submission and resolution of any planning permission application, or any other usual pre-construction survey or investigation. c. authorise community engagement and consultations where the Corporate Director deems it necessary or advantageous (3) That the funding position for the next development phase be noted. (4) That the current funding gap and strategy for securing further funds be noted.
Word for word from the decision Trafford published for this meeting.Source: democratic.trafford.gov.uk
The 2012 Trafford Core Strategy proposed a number of transport improvements around Carrington – including the provision of a new link road to provide better capacity, alleviate congestion and improve public transport and cycling.
The Council has undertaken further appraisal of route options for the proposed new link road and has identified that the offline route (Option F) as the preferred option to be taken forward to submission of a planning application. This report sets out the rationale for selection and the strategy for progressing the scheme.
Recommendation(s)
It is recommended that the Executive:
1. note the outcome of the public engagement process 2. approve Option F as the route for the new Carrington Relief Road and authorise the Corporate Director of Place to: a. engage external resources where this will assist in implementing the relief road, including a professional team where reasonably required. b. Commission, submit and/or authorise as appropriate: i) an application for planning permission to deliver the relief road; and ii) any surveys/investigations where such surveys will reduce risks and/or assist with the preparation, submission and resolution of any planning permission application, or any other usual pre-construction survey or investigation. c. authorise community engagement and consultations where the Corporate Director deems it necessary or advantageous 3. note the funding position for the next development phase 4. note the current funding gap and strategy for securing further funds
Contact person for access to background papers and further information:
1 Adrian Fisher (Director of Growth and Regulatory Services) x 4621 Mark Riordan (Amey - Projects Director) [phone removed]
Appendices
Appendix 1 – Route Options Drawing
Appendix 2 – Preferred Option Report
Appendix 3 – Public Engagement Summary Questions and Update
Background Papers: None
2 Implications:
Relationship to Policy Carrington Relief Road is a requirement of Trafford Core Strategy (2012) Policy SL5, ‘Carrington Strategic Location’ and stated Framework/Corporate Priorities component of The Local Plan and it forms the b aseline of new highway infrastructure set out in the emerging Places for Everyone (PfE) New Carrington allocation policy. Relationship to GM Policy or Delivery of the scheme will support the growth ambitions Strategy Framework articulated within the emerging Paces for Everyone Plan and the GM Strategy. The scheme will be delivered in the context of the GM 2040 Transport Strategy, GM Congestion Plan, and Made to Move walk ing and cycling plan to identify improvements tack ling traffic congestion, promote sustainable modes of travel and better integrate transport and new developments. Financial The estimated capital cost of the scheme is £29.4m. The scheme has received approval for grants of £6.0m and £8.4m from the Growth Deal fund and Housing Infrastructure Fund respectively. Further S106 contributions from forthcoming developments amount to approximately £2.8m and The Council is exploring mechanisms for addressing the residual funding gap. Legal Implications: None as a consequence of this report Equality/Diversity Implications None as a consequence of this report
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.