RESOLVED - That the Executive agrees the proposals contained within the report be agreed as the detailed capital programme for 2021/22, specifically: 1. Note the demand for primary and secondary school places in Section 2 and 4 of the report. 2. Note the feasibility study and options appraisal in Section 3 of the report for refurbishment and expansion of the now amalgamated Stamford Park Primary School and approve the proposal not proceed with the expansion of Stamford Park Primary School and to reallocate the £8m budget and instead proceed with the expansion of The Willows Primary School. 3. Approve the expansion proposals detailed in Section 6 of the report: Willows Primary School (PAN 45 to 60) Templemoor Infant School (PAN 60 to 90) Moorlands Junior School (PAN 60 to 90) Davyhulme Primary School (PAN 70 to 90) 4. Note and agree the completion of previous schemes and the demand for early years places in Section 5 of the report.
Word for word from the decision Trafford published for this meeting.Source: democratic.trafford.gov.uk
The Council has a statutory duty to provide sufficient places in schools and early years settings. To support the achievement of this duty, and to meet any risks in relation to school conditions and access, the Council has received Basic Need capital funding (for expansion of pupil places) of £7.842m for 2021/22 and a nil allocation for 2022/23. This report further details and updates on the progress that has been made on existing projects to meet demand for places as projected in January 2021. Section 6 sets out the Council’s proposals to address the shortfall of places. All proposals are at the budget estimate stage and will be met from within the grant allocation available.
Recommendation
That the Executive agrees the proposals contained within this report as the detailed capital programme for 2021/22, specifically:
1. Note the demand for primary and secondary school places in Section 2 and 4
2. Note the feasibility study and options appraisal in Section 3 for refurbishment and expansion of the now amalgamated Stamford Park Primary School and approve the proposal not proceed with the expansion of Stamford Park Primary School and to reallocate the £8m budget and instead proceed with the expansion of The Willows Primary School.
3. Approve the expansion proposals detailed in Section 6: Willows Primary School (PAN 45 to 60) Templemoor Infant School (PAN 60 to 90) Moorlands Junior School (PAN 60 to 90) Davyhulme Primary School (PAN 70 to 90)
4. Note and agree the completion of previous schemes and the demand for early years places in Section 5. Contact person for access to background papers and further information:
Name: Sarah Butters, Head of Service – Early Years, School Places and Access Karen Samples, Director of Education Standards, Quality & Performance
Extension: 912 1056 / 912 5100
Background Papers: None
Relationship to Policy Ensuring a fair start for all children and young Framework/Corporate Priorities people Supporting our residents when they need it most
Relationship to GM Policy or Not Applicable Strategy Framework Financial The estimated capital cost of the schemes, now recommended for approval in Appendix A, is £11.8m which can be financed by capital grant from the DfE. Legal Implications: All changes to schools’ status, closure, expansion and amalgamation, and new schools, are subject to statutory processes, which will need to be adhered to as appropriate for each scheme. In addition, the Council has statutory duties in relation to the provision of school and early education places, including using its planning powers to secure provision. Equality/Diversity Implications Schools are subject to current legislation regarding Equality and Diversity Sustainability Implications School buildings are procured requiring successful contractors to meet required sustainability criteria. Carbon Reduction Improving the quality of our School buildings helps to reduce energy and carbon consumption. Resource Implications e.g. Staffing School buildings are assets that need to be / ICT / Assets maintained Risk Management Implications Operational risk of buildings closing if capital maintenance works not undertaken and insufficient school places Health & Wellbeing Implications The condition of School buildings affects the Health and Wellbeing of all staff and pupils. Health and Safety Implications All building work is subject to appropriate current Health and Safety/CDM regulations. Failure to respond to condition issues, which have health and safety implications, will find the Council in breach of the Health and Safety at Work Act. 1. Background
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.