Resolved
RESOLVED - That the works programmes associated with the allocation of KRN capital funds for 2022/27 as outlined at Appendix A of the report be approved.
Executive approved this item on Monday 25 July 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED - That the works programmes associated with the allocation of KRN capital funds for 2022/27 as outlined at Appendix A of the report be approved.
This report seeks to update the Executive in more detail which schemes are being proposed as part of the current capital programme for the Key Route Network (KRN) that includes
1. Proposed list of KRN highway capital works to be delivered during the next 5 years following allocation of funds via TfGM.
2. Update on how the schemes will be delivered with the funds available
Recommendation(s)
The Executive is recommended:
To approve the works programmes associated with the allocation of KRN capital funds for 2022/27 as outlined at Appendix A of this Report.
Contact person for access to background papers and further information:
Name: Sharon Walls Email: [email protected]
1 Implications:
Relationship to Policy Value for Money Framework/Corporate Priorities Relationship to GM Policy or Improved and safer facilities for road users Strategy Framework including cyclists aligns with the Greater Manchester Transport 2040 Strategy and complements work on the Mayor’s Challenge Fund Financial Planned capital expenditure over the next 12month and 5year period will be contained within available capital resources allocated by TfGM Legal Implications: None arising out of this report. Equality/Diversity Implications In approving the detail of schemes proposed through the capital programme the Council will need to ensure that any decisions are made fully in accordance with its Public Sector Equality Duty Sustainability Implications The indicative capital programme includes a number of proposals that will aid the Council in its environmental sustainability objectives, Resource Implications e.g., Improvement schemes are being undertaken in Staffing / ICT / Assets 2022/23 and beyond by Amey as part of the OTP contract with resources managed by them Risk Management Implications None directly arising Health & Wellbeing Implications The proposed capital programme includes a number of schemes that seeks to provide a positive impact on the highway network ensuring safe and sustainable infrastructure across the borough is maintained for continues access to essential services and locations Health and Safety Implications A number of schemes are being undertaken on the grounds of health and safety including resurfacing roads Various surfacing techniques and proposals are Carbon Reduction being explored and will be utilised where appropriate to support the carbon neutral action plan.
1.1The Council approved the Council’s budget including capital allocations as contained in the budget report of 16th February 2022 that included highway related capital investment on the local road network.
1.2Attached is an additional programme of works for the Key Route Network (KRN) highways capital programme following approval of bids to TfGM for award of grant from the Dft which is specific to the KRN network.
1.3KRNs are a network of some of the most important roads in a combined authority area for which a mayoral authority and its constituent district authorities both hold powers. KRNs are typically the busiest main roads; side streets do not, and some other main roads may not, form part of the KRN. The KRN makes up nearly 400 miles of Greater Manchester’s busiest roads and whilst this is just seven per cent of 2 the total length of the highway network across the region, it carries some two-thirds of peak-time traffic including many strategic bus routes.
1.4The KRN is a network of corridors, managed and maintained in partnership with Transport for Greater Manchester (TfGM) and hence funded centrally, that will support the Greater Manchester Transport Strategy and enable growth.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CAPITAL PROGRAMME 2022/23: KEY ROUTE NETWORK SCHEME APPROVALSReport | 500 KB | DownloadRead as text |
Follow Executive at Trafford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Sep 2026 | Greater Manchester End to End Fostering Recruitment Hub1) That the national and Greater Manchester context supporting the developments of the Greater Manchester End-to-End ... | Approved | Open |
| 21 Sep 2026 | Sale Waterside Private Finance Initiative Exit1) That the hand back of the Sale Waterside PFI assets to Council ownership on expiry of the PFI contract on 28 th Oc... | Approved | Open |
| 20 Jul 2026 | Wharfside Strategic MasterplanThat the Executive: (i) Approves the draft Trafford for consultation. (ii) (ii) Delegates authority to the Corporate ... | Approved | Open |
| 20 Jul 2026 | Local Plan Regulation 19 Consultation ApprovalThat the Executive: (i) Approves the Trafford Local Plan (Publication Version) 2026, including allocations, designati... | Approved | Open |
| 15 Jun 2026 | Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.