That the Executive: 1. Noted the update in respect of the process to secure the leasehold disposal of Altrincham Town Hall as a site which has been approved and included within the Council’s Strategic Land Review Programme for 2022/23 as detailed in the report; 2. Approved the commencement of a formal open tender process to explore the disposal of Altrincham Town Hall via a lease; 3. Delegated approval to the Corporate Director for Place, in consultation with the Executive Member for Economy and Regeneration, to agree the final tender assessment criteria; 4. In accordance with previous delegations, reaffirmed the approval to delegate to the Corporate Director for Place, in consultation with the Executive Member for Economy and Regeneration, the authority to identify and confirm the successful bidder following the conclusion of the open tender process; 5. In accordance with previous delegations, reaffirmed the approval to delegate to the Corporate Director of Place, in consultation with the Director of Legal and Governance, the authority to agree the terms and conditions of, and to enter into, all legal documents and/or agreements in respect of the leasehold disposal of Altrincham Town Hall; 6. Noted the previous approvals and delegations in respect of the disposal of Altrincham Town Hall as detailed in the report.
Word for word from the decision Trafford published for this meeting.Source: democratic.trafford.gov.uk
Following the inclusion of Altrincham Town Hall in the Council’s 2022/23 Strategic Land Review Programme and the subsequent nomination of the Town Hall as an Asset of Community Value (ACV), this report provides an update on the position in respect of Altrincham Town Hall.
The report provides an overview of activities to date and contains details of steps which will be taken next.
Recommendation(s)
The Executive is recommended to:
i) Note the update in respect of the process to secure the leasehold disposal of Altrincham Town Hall as a site which has been approved and included within the Council’s Strategic Land Review Programme for 2022/23 as detailed in the report;
ii) Approve the commencement of a formal open tender process to explore the disposal of Altrincham Town Hall via a lease;
iii) Delegate approval to the Corporate Director for Place, in consultation with the Executive Member for Economy and Regeneration, to agree the final tender assessment criteria;
iv) In accordance with previous delegations, reaffirm the approval to delegate to the Corporate Director for Place, in consultation with the Executive Member for Economy and Regeneration, the authority to identify and confirm the successful bidder following the conclusion of the open tender process;
v) In accordance with previous delegations, reaffirm the approval to delegate to the Corporate Director of Place, in consultation with the Director of Legal and Governance, the authority to agree the terms and conditions of, and to enter into, all legal documents and/or agreements in respect of the leasehold disposal of Altrincham Town Hall;
1 vi) Note the previous approvals and delegations in respect of the disposal of Altrincham Town Hall as detailed in the report.
Contact person for access to background papers and further information:
Name: Steve Tranter
Implications:
Relationship to Policy Supporting People out of Poverty and Addressing our Climate Crisis through investment in this key Town Centre Framework/Corporate Priorities asset.
Relationship to GM Policy or N/a Strategy Framework Financial The disposal (via a lease) of the asset will be at best value. This will result in revenue savings as set out in this report. Legal Implications: As part of this process the Council will need to ensure it achieves best value through the process whilst adhering to the ACV process. Equality/Diversity Implications Through the process the Council will consider the extent to which the proposed use provides equality of access for all members of the local community. Sustainability Implications The building is currently inefficient, and it is expected that through the process investment in the building will be achieved. Carbon Reduction The recommendations will enable investment in an asset which will have a positive net impact on the efficiency of the asset. Resource Implications e.g. Staffing None, there are no direct Council staff employed at the TH / ICT / Assets as it is managed through the Amey Facilities Management Contract.
The impact on staffing will need to be considered once the outcome of the tender process is known. Risk Management Implications Transfer of the asset will reduce the Council’s exposure to the day-to-day risks of asset management. The Council will be exposed to other risks such as the performance of the business/ group and their ability to pay rent. Health & Wellbeing Implications The building is currently underused and so the proposal will enable the building to make a more significant contribution towards the Council’s objectives including improved Health and Wellbeing Health and Safety Implications Through the disposal process the lease arrangements will ensure that the building is operated safely.
Background
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.