That the Executive: i) Approved that the Council enters into a grant agreement with the DLUHC to access grant award from the Levelling Up Fund to support the delivery of the programme of works. ii) Delegated authority to the Corporate Director for Place, in consultation with the Director of Legal and Governance and Director of Finance and Systems, to agree the terms and conditions of the grant funding agreement. iii) Delegated authority to Director of Legal and Governance to enter into the grant agreement required to finalise the transaction. iv) Delegated authority to the Corporate Director of Place to negotiate and award any contracts which may be required to implement this decision. v) Noted that the outcomes of the RIBA Stage 2 report for Partington Leisure Centre will be presented to the Executive prior to submitting a planning 2 application in 2024.
Word for word from the decision Trafford published for this meeting.Source: democratic.trafford.gov.uk
The Council has been allocated grant funding by DLUHC from the Levelling Up Fund (LuF2) to support the delivery of the Redevelopment of Partington Sports Village.
This report seeks approval to enter into an agreement with DLUHC to secure grant funds of £18.3m. The scheme also includes an additional £1.2m match funding from the Council’s approved Leisure Investment Programme capital budget and £1.25m match funding from external stakeholders. This will support delivery of a programme of improved leisure facilities in Partington including the refurbishment of Partington Leisure Centre, Cross Lane Changing Rooms, Pump Track, Trim Trail and improved public realm.
Recommendation(s)
That the Executive:
i) Approves that the Council enters into a grant agreement with the DLUHC to access grant award from the Levelling Up Fund to support the delivery of the programme of works.
ii) Delegates authority to the Corporate Director for Place, in consultation with the Director of Legal and Governance and Director of Finance and Systems, to agree the terms and conditions of the grant funding agreement.
iii) Delegates authority to Director of Legal and Governance to enter into the grant agreement required to finalise the transaction.
iv) Delegates authority to the Corporate Director of Place to negotiate and award any contracts which may be required to implement this decision.
v) Notes that the outcomes of the RIBA Stage 2 report for Partington Leisure Centre will be presented to the Executive prior to submitting a planning
1 application in 2024.
Contact person for access to background papers and further information:
Relationship to Policy It supports implementation of the Council’s Framework/Corporate Priorities Corporate Plan (2021-24), including the priority to reduce health inequalities and addressing climate crisis. Relationship to GM Policy or The decision relates to the GM Moving strategy in Strategy Framework terms of the aim to increase physical activity levels, Pivot to Wellbeing regarding leisure outcomes and GM Gear Change in relation to Active Travel. Financial The DLUHC has agreed to provide grant funding of £18.3m to support delivery of Levelling Up in Partington. There is also £1.2m match funding in the Council’s capital programme approved in February 2023 and a further £1.25m from external stakeholder contributions. The outcomes of the programme will contribute to improved health and wellbeing and energy efficiencies and associated costs post-delivery, expected from March 2025. The refurbished facilities will also improve financial outcomes for the operator for this site, (Trafford Leisure CIC), which will be reinvested to finance the Council’s match funding element. Legal Implications: The Council will have to abide by the terms of the grant agreement. It will need to undertake a robust lawful procurement exercise and will need to enter satisfactory contracts and appointments, which manages cost and delivery risk within budget.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.