AI summaryTrafford Executive approves progression of 33 home scheme on land at Partington Shopping Centre to RIBA Stages 3 and 4, with planning application due in January 2026.
Written from the decision and the officer reportPDF Pro
OutcomeNotedRIBA Stage 3 and 4 design then delivery
MoneyGrants fund design stageBorrowing sought for build costs above grant
What happens nextPlanning application January 2026Start on site Summer 2026
Who it affectsPartington residents and community33 new homes on shopping centre land
What was decided
The Executive noted the proposals for the 33 home Development on land to the rear of Partington Shopping Centre.
The Executive approved and authorised progression to RIBA Stage 3 and 4 design and then delivery of 33 homes on the site.
The Executive delegated authority to the Corporate Director of Place to submit a planning application, engage external resources, negotiate contracts, agree licences, easements, leases or disposals, and authorise a marketing, pricing and disposal strategy, including plot sales where the capital receipt exceeds £499,999; and authorised the Director of Legal and Governance to enter into all legal agreements.
Why
The scheme supports the Council's corporate priorities by delivering quality new family housing, including 7 M4(3) fully accessible homes, and addresses Partington's identified need for 1 and 2 bedroom rented and affordable sale products. Report P7, P8, P9, 2.2
The development is intended to generate a capital receipt and developer profit to be reinvested in other priority capital schemes, and fits with the Strategic Land Sales programme approved in February 2025. Report P10, P12, 2.15
The site is not being delivered by the private sector or Registered Providers, and the scheme offers up to 100% affordable housing subject to Homes England funding, with at least 50% expected to be affordable or social rent. Report 2.1, 2.7
What happens next
A planning application will be submitted in January 2026, with start on site anticipated for Summer 2026 and completion in Late 2027, giving an estimated 70 week build programme. Report 2.9, 2.10, P32
The Council will procure a contractor, complete RIBA Stage 3 and 4 design with the contractor, and consult residents and community groups during Stage 3. Report 2.10, 2.11, 6.1
A further report will go to the Council's Investment Management Board to secure capital investment for the delivery stage, post planning and Stage 4 design, with approval for prudential borrowing to be sought there. Report P11, 2.14
The money
£499,999 Threshold above which disposal of plots requires authorisation under the delegated authority granted to the Corporate Director of Place
Options considered
Rejected: Expand the shopping centre. Retailers confirmed the location was not suitable for their business
Rejected: Do nothing. The site would remain undeveloped with no capital receipt Report 5.2
Rejected: Sell the site. Would not guarantee delivery and would deliver a reduced receipt to the Council Report 5.3
Implications
Financial: Costs to the end of RIBA 4 will be funded from grants. The cost of development above that funded externally by grant will be funded by prudential borrowing, subject to Investment Management Board approval. Report P11, 2.14
Legal: The Council will enter into numerous contracts and professional appointments, all to be carried out in accordance with accepted procurement protocols and the Council's statutory obligations. Report P12
Equalities: The development incorporates 7 M4(3) fully adapted dwellings for residents who require accessible housing, addressing a product not currently being delivered in the area. Report P12
Climate: A carbon assessment has been commissioned. The scheme uses passive design, air source heat pumps for a gas free energy solution, timber frame construction, sourcing of local materials, EV charging facilities, and targets a minimum EPC B rating and a 5% improvement under Trafford Core Strategy Policy L5. Report P12, 2.5
Risk: Delivery is supported by a risk plan with key risks and mitigations, monthly risk workshops, monthly development team meetings, and full due diligence at the Investment Management Board. Report P12, 2.16
Other: Existing resources have been identified to support the scheme; additional external professional support may be brought in and factored into scheme costs. Report P12, P13
Who and where
Partington residents and families on the Housing Register, particularly those needing 1 or 2 bedroom rented or affordable sale products Report 2.2
Future residents requiring fully wheelchair accessible housing, served by the 7 M4(3) dwellings
Partington and Carrington local community groups, who will be consulted during Stage 3 Report 2.11, 6.1
Trafford Council, as developer and recipient of the capital receipt reinvested in the Capital Programme Report P10, 2.15
Homes England, with whom discussions on grant and the level of affordable housing will continue in Stage 3 Report 1.3, 2.7
Timeline
March 2016: Executive approved acquisition of the land to the rear of Partington Shopping Centre from Peel Holdings using Homes England grant Report 1.1
August 2024: Council secured Brownfield development fund grant for a RIBA Stage 2 report and cost plan Report 1.2
January 2026: Planning application to be submitted Report P32
Summer 2026: Start on site anticipated, subject to planning determination Report 2.9, P32
Late 2027: Completion anticipated Report P32
70 weeks following start on site: Estimated delivery programme for the build Report 2.9
Plain English for the jargon
RIBA Stage 3 and 4: Royal Institute of British Architects design stages covering detailed design and technical design prior to construction.
M4(3): Building regulation standard for dwellings that are fully accessible to wheelchair users and people with mobility needs.
EPC B: Energy Performance Certificate rating, with B indicating a relatively energy efficient home.
Brownfield development fund: Government grant funding supporting the development of previously used land.
Homes England: Government agency that funds new affordable housing in England.
GMCA: Greater Manchester Combined Authority, the regional authority covering the 10 Greater Manchester councils.
Strategic Land Review Programme: Trafford Council programme approved in February 2025 covering identified Council owned sites for disposal or development.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8
Resolved
(1) That the proposals for the Development, be noted. (2) That the Executive approves and authorises the progression to RIBA Stage 3 and 4 design and then the delivery of 33 homes on the site (the Development). (3) That the Corporate Director of Place be delegated authority to: a. Submit a planning application and undertake the Development, subject to the parameters in this report. b. Engage external professional resources as required to assist in implementing the Development. c. Negotiate and finalise any agreement contract or other document required to deliver the Development and any associated disposals. d. Agree any licence or approve the grant of any easement or lease or any other disposal. e. Authorise a marketing, pricing and disposal strategy and authorise the sale of plots including where the anticipated or actual capital receipt exceeds £499,999. (4) That the Director of Legal and Governance be authorised to enter into all legal agreements required to implement the above decisions.
Word for word from the decision Trafford published for this meeting.Source: democratic.trafford.gov.uk
This paper provides an update on the redevelopment of land to the rear of Partington Shopping Centre and seeks approval for the development of 33 homes in Partington.
Recommendations
It is recommended that the Executive:
i) Notes the proposals for the Development. ii) Approves and authorises the progression to RIBA Stage 3 and 4 design and then the delivery of 33 homes on the site (the Development). iii) Delegates authority to the Corporate Director of Place to: a. Submit a planning application and undertake the Development, subject to the parameters in this report. b. Engage external professional resources as required to assist in implementing the Development. c. Negotiate and finalise any agreement, contract or other document required to deliver the Development and any associated disposals. d. Agree any licence or approve the grant of any easement or lease or any other disposal. e. Authorise a marketing, pricing and disposal strategy and authorise the sale of plots including where the anticipated or actual capital receipt exceeds £499,999. iv) Authorise the Director of Legal and Governance to enter into all legal agreements required to implement the above decisions.
Contact person for access to background papers and further information:
Name: Clare Huber Extension: N/a
Background Papers: None
1 CORPORATE PRIORITIES AND GOVERNANCE CONSIDERATIONS The Best Start for our Children and The decision supports the delivery of quality new Young People family housing.
Healthy and Independent Lives for The decision supports the delivery of quality new Everyone family housing.
A Thriving Economy and Homes The decision supports the delivery of quality new for All family housing.
Address the Climate Crisis A carbon assessment has been commissioned for both Design and Construction of the proposed development. Culture, Sport and Heritage for As detailed in the report. Everyone Relationship to GM Policy or The proposed development will provide High Strategy Framework quality housing. Delivery of the Scheme will support the growth ambitions articulated within the emerging Greater Manchester Spatial Framework and the GM Strategy. Financial Considerations This scheme will be developed to support regeneration and generate a financial return to support the Capital Programme, as included in the Strategic Land Review Programme approved in February 2025.
Costs to the end of RIBA 4 will funded from grants. The cost of development, above that funded externally by grant, will be funded by prudential borrowing. The approval for this borrowing will be sought from the Council’s Investment Management Board.
Legal Implications: The development will necessitate the Council entering into numerous contracts and professional appointments, which will all need to be carried out in accordance with accepted procurement protocols ensuring that the Council is compliant with its statutory obligations. Equality/Diversity Implications The development incorporates 7 (seven) M4(3) fully adapted dwellings for residents who require it. Sustainability Implications The scheme is designed to reduce energy demand through passive design measures lowering energy bills for potential occupiers. This will be coupled with low energy building services and supplementary renewable technology where required. The development will be designed to meet the 5% improvement outline in the Trafford Council Core Strategy, Policy L5. Resource Implications e.g. Staffing Existing resources have been identified to support / ICT / Assets the delivery of the scheme and related activity.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.