Trafford Council’s Reprioritised Mayors Challenge Fund (MCF) Active Travel Scheme Programme

Noted Executive 1 paper

AI summaryTrafford Executive noted the status of 4 Mayor's Challenge Fund active travel schemes, totalling £13,092,383, and delegated authority to accept Transport for Greater Manchester funding and award construction contracts for the 2025/26 and 2026/27 pipeline.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNoted4 MCF schemes and proposed pipeline noted, contract authorities delegated
Money£13,092,383Total of 4 MCF schemes as at October 2025
What happens next2025/26 to 2026/27 pipelineSchemes in design, consultation and initiation stages
Who it affectsTrafford residents and road usersWalking, cycling, wheeling and bus users across the borough

What was decided

The Executive noted the current status of the 4 Mayor's Challenge Fund active travel schemes and noted the proposed 2025/26 and 2026/27 active travel scheme pipeline. Report P3, P4

The Executive delegated authority to the Corporate Director of Place, in consultation with the Director of Finance and Systems, to accept Transport for Greater Manchester funding scheme by scheme for the pipeline. Report P5

The Executive delegated authority to the Corporate Director of Place to negotiate grant delivery agreements, construction contracts and other documents, and to award contracts to recommended contractors, with the Director of Legal and Governance authorised to enter into the required contracts and documents. Report P6, P7, P8

Why

Accepting the grant allows active travel schemes to be built, supporting the council's Walking, Wheeling and Cycling Strategy and Greater Manchester's Active Travel Mission under the 2040 Transport Strategy. Report P11, 1.1, 1.4

Improved walking, wheeling and cycling infrastructure is expected to support carbon reduction, health and wellbeing, and air quality, and to provide inclusive access for people with disabilities or mobility issues. Report P11, P14, P15

Not accepting the funding would risk incomplete, non-compliant cycle schemes, missed Walking, Wheeling and Cycling strategy outcomes, reputational damage for future bids, and likely further increases in development and construction costs. Report 4.1, 4.2

What happens next

Designs for pipeline schemes will be finalised, business cases completed and funding secured through Transport for Greater Manchester governance processes, with some schemes going to Detailed Designs Review Panel approval. Report P36, P37, P38

Public consultation will be carried out at required milestones on each scheme, with further engagement of local councillors, affected residents and businesses before and during delivery. Report 5.1

Once a Delivery Agreement is in place for each scheme, the Corporate Director of Place will award a contract to a recommended contractor and the Director of Legal and Governance will enter into the required contracts. Report P7, P8, P12, P13

The money

  • £13,092,383 Total cost of the 4 reprioritised MCF active travel schemes, as at October 2025 Report P24
  • £4,751,389 Talbot Road combined scheme, complete Report P23
  • £2,072,123 A56 Phase 2 scheme, complete Report P24
  • £4,994,104 Seymour Grove Phase 1, currently on site, completion due Dec 2025 Report P24
  • £1,274,767 Urmston Active Neighbourhood, post trial decision not to progress further Report P24
  • £1.07bn City Region Sustainable Transport Settlement awarded across Greater Manchester Report 1.3
  • £1,100,000 A56 Junction Improvements at Sinderland Road and Barrington Road, complete end of September 2025 Report P33

Options considered

  • Chosen: Accept grant funding and proceed with the active travel scheme pipeline as set out. Enables delivery of the council's Walking, Wheeling and Cycling Strategy, supports carbon reduction and protects future funding bids Report P5, 4.1, 4.2
  • Rejected: Do not accept the grant funding. Would risk incomplete, non-compliant cycle schemes, miss strategy outcomes, harm future bid reputation and let costs rise Report 4.1, 4.2

Implications

  • Financial: Funding comes from the Mayor's Challenge Fund and City Region Sustainable Transport Settlement via Transport for Greater Manchester, drawn down scheme by scheme, with revenue monitored through Executive budget reporting. Report P11, P5
  • Legal: Standard Delivery Agreements must be agreed with all Greater Manchester local authority legal teams, and the council must put in place required legal frameworks such as reporting structures and traffic orders. Report P12, P13
  • Equalities: Schemes aim to address inequalities by providing inclusive active travel and accessibility improvements for disabled and mobility impaired users. Report P14
  • Climate: Improved walking, wheeling and cycling infrastructure is expected to support carbon reduction by enabling short car journeys to be replaced with active travel. Report P11, P14
  • Risk: Risks include design and safety assurance, construction risks including inflation, and monitoring of time, cost, quality, and impact on the public highway network. Report P14
  • Staffing: Schemes will be delivered on Trafford's highways and overseen by Client and Amey staff within the One Trafford Partnership Team. Report P14
  • Other: After implementation, the council must include the new infrastructure in its Highways Infrastructure Asset Management Plan and provide annual highways maintenance capital investment. Report P12

Who and where

  • Trafford residents, including school pupils, students and visitors using the new routes Report P28
  • Walking, wheeling, cycling and bus users across the borough Report P11, P14, P15
  • Local businesses and community groups receiving activation grants and engagement Report P28
  • Transport for Greater Manchester and Department for Transport through 12 to 24 month monitoring and evaluation reporting Report 2.3
  • Local councillors in affected wards, engaged before and during scheme development and delivery

Timeline

  • July 2025: Chester Road and Talbot Road recorded a > 300% increase in cyclists compared with Sep 2024 Report P24
  • 12 to 24 months after scheme completion: Trafford must report to Transport for Greater Manchester and Department for Transport against monitoring, evaluation and activation plans Report 2.3
  • 2025/26 and 2026/27: Indicative delivery window for the proposed active travel scheme pipeline Report P1, P4, 6.1
  • As at October 2025: Total MCF scheme costs reported at £13,092,383 Report P24
  • Dec 2025: Seymour Grove Phase 1 final projected completion Report P24

Plain English for the jargon

  • MCF: Mayor's Challenge Fund, the Greater Manchester active travel grant programme managed via Transport for Greater Manchester
  • TfGM: Transport for Greater Manchester, the body that allocates and administers active travel funding on behalf of Greater Manchester Combined Authority
  • CRSTS: City Region Sustainable Transport Settlement, government funding awarded to support the Bee Network and wider transport schemes
  • WWC: Walking, Wheeling and Cycling, the council's approved strategy for active travel in Trafford
  • SWANI: Sale West to Altrincham Network Improvements, a programme of bus and active travel schemes in west Trafford
  • Delivery Agreement: The formal funding agreement required between the council and Transport for Greater Manchester before MCF or CRSTS money can be drawn down
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

(1) That the status of the 4 MCF active travel schemes as set out in Section 2 of the report, be noted. (2) That the proposed active travel scheme pipeline as set out in Section 3 of the report, be noted. (3) That the Corporate Director of Place be delegated authority, in consultation with the Director of Finance and Systems, to accept funding made available from Transport for Greater Manchester (TfGM), on a scheme-by-scheme basis, for the development and delivery pipeline as set out in Section 3 of the report. (4) That the Corporate Director of Place be delegated authority, in consultation with the Director of Legal and Governance, to negotiate and finalise the grant delivery agreements, construction contracts and any other contracts or documents required to implement this decision. (5) That the Corporate Director of Place be delegated authority, in consultation with the Director of Legal and Governance, to award a contract to a recommended contractor for each Scheme once an agreed delivery agreement is in place. (6) That the Director of Legal and Governance be delegated authority to enter into any contracts or other documents required to implement this decision.
Word for word from the decision Trafford published for this meeting. Source: democratic.trafford.gov.uk

Follow this further

Built from Trafford's papers

What the report saysPro

Report to Executive

Summary

The report provides an update on Trafford Council’s 4 Reprioritised Mayors Challenge Fund (MCF) Active Travel Schemes and provides an indicative 2025/26 and 2026/27 pipeline.

Recommendations

The Executive is recommended to:

a) Note the status of the 4 MCF active travel schemes as set out in Section 2 of this report.

b) Note the proposed active travel scheme pipeline as set out in Section 3 of this report.

c) Delegate authority to the Corporate Director of Place, in consultation with the Director of Finance and Systems, to accept funding made available from Transport for Greater Manchester (TfGM), on a scheme-by-scheme basis, for the development and delivery pipeline as set out in Section 3 of this report.

d) Delegate authority to the Corporate Director of Place, in consultation with the Director of Legal and Governance, to negotiate and finalise the grant delivery agreements, construction contracts and any other contracts or documents required to implement this decision.

e) Delegate authority to the Corporate Director of Place, in consultation with the Director of Legal and Governance, to award a contract to a recommended contractor for each Scheme once an agreed delivery agreement is in place.

f) Delegate authority to the Director of Legal and Governance to enter into any contracts or other documents required to implement this decision.

Contact person for access to background papers and further information:

1 Name: Douglas Cohen Telephone No: [phone removed] Background Papers Active Travel Fund (ATF) Tranche 2 Update on Trafford Council’s Mayoral Challenge Fund (MCF) Active Travel Reprioritisation & Indicative 2023/24 Active Travel Scheme Delivery Programme Implications:

Relationship to Policy Alignment with the approved Council’s strategy to Framework/Corporate Priorities increase the numbers of people walking, wheeling, and cycling across Trafford through the development and delivery of improved, accessible, and safer cycling and walking infrastructure. By providing alternative forms of travel and having effective and efficient transport infrastructure also supports the corporate objective of Supporting People out of Poverty and Addressing our Climate Crisis. Relationship to GM Policy or The provision of improved and safer active travel Strategy Framework infrastructure aligns with the Greater Manchester Transport 2040 Strategy, delivers on Greater Manchester’s Active Travel Mission through the Mayor’s Challenge Fund and City Region Sustainable Transport Settlements grant. Financial The funding to support the implementation of the active travel schemes is through the MCF and City Region Sustainable Travel Settlement (CRSTS) funding from GMCA via Transport for Greater Manchester (TfGM). The individual schemes are drawn down following specific Executive or delegated decision approvals and are included in the capital programme accordingly. Revenue spending will be monitored against the relevant grant approvals as part of the Executive budget monitoring reporting.

Post implementation, the Council is responsible for including this active travel infrastructure as part its Highways Infrastructure Asset Management Plan (HIAMP) and providing for an annual level of highways maintenance capital investment. Legal Implications: There will be a need for Delivery Agreements (DA) to be in place at the point the funding is approved.

Standard DAs which need to be agreed following consultation between all GM/LA legal teams.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Trafford Council’s Reprioritised Mayors Challenge Fund (MCF) Active Travel Scheme ProgrammeReport 427 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 12 attended
TR
Councillor Tom RossChair, present
LP
Councillor Liz PatelDeputy Leader, present
SA
Councillor Stephen AdsheadCommittee Member, present
KC
Councillor Karina CarterCommittee Member, present
GD
Councillor George DevlinCommittee Member, present
JH
Councillor Joanne HardingCommittee Member, present
EP
Councillor Eve ParkerCommittee Member, present
JS
Councillor Jane SlaterCommittee Member, present
RT
Councillor Rose ThompsonCommittee Member, present
AW
Councillor Aidan WilliamsCommittee Member, present
JA
John AddisonDemocratic Services Officer, expected
MD
Martin DillonOfficer, expected

More from Trafford Executive

All decisions
MeetingDecisionOutcome
21 Sep 2026 Greater Manchester End to End Fostering Recruitment Hub1) That the national and Greater Manchester context supporting the developments of the Greater Manchester End-to-End ... Approved Open
21 Sep 2026 Sale Waterside Private Finance Initiative Exit1) That the hand back of the Sale Waterside PFI assets to Council ownership on expiry of the PFI contract on 28 th Oc... Approved Open
20 Jul 2026 Wharfside Strategic MasterplanThat the Executive: (i) Approves the draft Trafford for consultation. (ii) (ii) Delegates authority to the Corporate ... Approved Open
20 Jul 2026 Local Plan Regulation 19 Consultation ApprovalThat the Executive: (i) Approves the Trafford Local Plan (Publication Version) 2026, including allocations, designati... Approved Open
15 Jun 2026 Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2... Noted Open