DECISION: 1. That Cabinet considers and notes the actual expenditure on capital schemes to 31 December 2011; 2. That Cabinet approves the increases and decreases to the capital programme as set out in paragraphs 8 to 13; 3. That Cabinet approves the re-scheduling of capital schemes in 2012/13 as set out in paragraphs 7 and Appendix D; 4. That Cabinet notes that work is in hand with the aim of delivering Disabled Facilities Grants (TAC) and Housing Renewal Grants (TAD) by year end as set out in paragraphs 15 and 16; and 5. That Cabinet notes and considers the available Section 106 funding as set out in paragraph 14 and Appendix I. REASONS: 1. All of the increases reported have either been approved at other Cabinet meetings or have been spent. 2. The Capital Application is considered essential.
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
This report compares capital projects approved by Cabinet with actual capital expenditure to the 31 December 2011 and the projected outturn for the year. The Capital Programme for the years to 2014/15 has been created through a formal application and approval process. All new schemes must be agreed by Cabinet before they can be included in the Capital Programme. In Quarter 2 Cabinet approved a total of £28,397,000 capital spending, of which £23,341,000 was due to be spent in 2011/12. The actual expenditure to December 2011 was £736,000, £319,000 of which was spent in Quarter 3. The forecast outturn for the year is now £2,152,000. This indicates that a further £1,416,000 is expected to be spent in the following 3 months. Significant work is being carried out with Kent County Council and Town and Country Housing Group to bring forward applications and ensure building works are completed by year end with the aim of delivering Disabled Facilities Grants and Housing Renewal by year end. This report seeks to inform Cabinet of the level of capital expenditure for Quarter 3 and to obtain formal approval for the adjustments to the 2011/12 forecast outturn.
LINK TO STRATEGIC COMPASS
This report supports the Value and Community quadrants of the strategic compass; in particular that we manage public finances effectively.
Report status
For decision
Route to Implementation/Timetable:
Cabinet can make these decisions. BACKGROUND/INTRODUCTION
1. At their meeting on 16 June 2011 Cabinet approved schemes to be met from the Capital Programme for the years from 2011/12 to 2014/15.
2. The figures approved by Cabinet were on the basis of the net cost to be met by the Council, either from reserves or from the sale of existing assets. These have been adjusted to a gross basis, showing the total proposed capital investment of £28,683,000 during the period, of which £25,686,000 was to be spent during 2011/12.
3. Appendices B and C set out in gross and net terms the amounts approved against the forecast outturn to 31 March 2012. They also show variances of actual to forecast and detail that expenditure which is re-scheduled to 2012/13.
WHAT IS THE ISSUE THAT REQUIRES A DECISION AND WHAT DOES THIS MEAN FOR THE PEOPLE OF TUNBRIDGE WELLS?
New Budget Approvals
4. In the October 2010 Cabinet, approval was given for £25,000 to fund a village hall extension for the Langton Green Charitable Trust (CAB083/10). This is in addition to the annual Community Capital Grants (TCE) allocation of £125,000 agreed by Cabinet in June 2011. The extension project has now been completed.
5. In the April 2011 Cabinet, approval was given for £16,399.20 to be spent on the supply and delivery of the Ice Rink Chalets (CAB206/10 Exempt). The chalets can be used for other events in the future. The useful economic life of the chalets is anticipated to be 5 years and therefore the capitalised assets will be depreciated over the next 5 years, in line with the Council’s depreciation policy. 6. The table below shows how the approved capital expenditure has evolved; incorporating the approvals obtained up to and including the November 2011 Cabinet. Approved Capital Spend as at £000's 31 December 2011
Original gross approvals 25,686 Community Investment Fund Cabinet (110203/CAB011) 92 Cranbrook Demolition Cabinet (CAB039/09) 40 Total approvals as at Quarter 1 25,818
Training Facility at Town Hall Cabinet (CAB61/11) 10 Upgrade to Corporate Server & Network Cabinet (CAB61/11) 175 St Johns Woodlands Play Areas equipment Cabinet (CAB61/11) 45 Re-scheduled to 2012/13 Cabinet (CAB61/11) (1,214) Cremators Cabinet (CAB72/11) 460 Software Upgrade for e-payments Cabinet (CAB76/11) 30
Total approvals as at Quarter 2 25,324
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.