Resolved
DECISION: That each recommendation is dealt with individually within each of the reports. Individual decisions are noted at 8b, 8c, 8d and 8e below. REASON: Each report contains its own recommendations.
Cabinet noted this item on Thursday 23 February 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
DECISION: That each recommendation is dealt with individually within each of the reports. Individual decisions are noted at 8b, 8c, 8d and 8e below. REASON: Each report contains its own recommendations.
Cabinet has for some time received a range of reports on a regular basis that amongst them paint a picture of the way in which the Council is performing and being governed. These reports are coordinated at quarterly ‘governance’ meetings of Cabinet and the covering report identifies the main issues that Cabinet need to consider arising from the following reports:
Quarter 3 2011/12 Performance Report Quarter 3 2011/12 Capital Management Report Quarter 3 2011/12 Revenue Management Report Quarter 3 2011/12 Treasury and Prudential Indicator Management Report.
LINK TO STRATEGIC COMPASS
This covering report and the reports to which it relates support all of the areas of our strategic compass by ensuring that the Council is well governed, that the financial position is sound, and that key performance indicators are on track and that the risks are being proactively managed.
Report status
For decision.
Route to Implementation/Timetable:
All of the recommendations are within budgetary and policy framework so any recommendations will be implemented after the call-in period has expired. BACKGROUND/INTRODUCTION
1. Each quarter Cabinet considers performance reports and reports on the financial health of the Council. Every six months Cabinet also considers reports related to complaints and Strategic Risks. These reports also get considered by the Corporate Services Select Committee, the Audit Committee and Standards Committee (where relevant).
WHAT IS THE ISSUE THAT REQUIRES A DECISION?
Performance
2. In the third quarter of financial year 2011/12 we monitored the performance for 38 indicators against their agreed targets. In addition to this we collected data for 18 other key indicators and are still awaiting input for one remaining performance indicator.
3. Overall our performance for quarter 3 shows that 30 performance indicators are on target or exceeding their target whereas 8 performance indicators are failing to achieve their targets. Further detail is provided in the Quarter 3 Performance Report.
Capital Management
4. The Capital Programme for the years to 2014/15 has been created through a formal application and approval process. All new schemes must be agreed by Cabinet before they can be included in the Capital Programme. In Quarter 2 Cabinet approved total capital expenditure of £28,397,000, of which £23,341,000 was due to be spent in 2011/12. The actual expenditure to December 2011 was £736,000, £319,000 of which was spent in Quarter 3. The forecast outturn for the year is now £2,152,000 as £20,500,000 budgeted for property investment has been rescheduled into 2012/13. This indicates that a further £1,416,000 is expected to be spent in the following 3 months. The majority is Disabled Facilities and Housing Renewal Grants, so significant work is being carried out with Kent County Council and Town and Country Housing Group to bring forward applications and ensure building works are completed by year end.
Revenue Management
5. The forecast outturn, as at quarter 3, shows an overspend to the revised Services budget of £169,000 which will need to be funded from the General Fund. This comprises a £623,000 reduction in revenue partially offset by a £269,000 saving on staff costs and £185,000 in other expenditure. There has also been an improvement in the net interest forecast outturn of £26,000 since quarter 2 bringing it back to budget, creating a total impact on the General Fund of £169,000.
6. £1,121,000 has been transferred from Earmarked Reserves to fund revenue projects, reducing them from £3,834,000 at the beginning of the year to £2,713,000.
Treasury and Prudential Indicator Management
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Item 8a: Q3 Governance Appendix A /11Appendix | 63 KB | Download |
PDF |
Quarter 3 Governance ReportReport | 115 KB | DownloadRead as text |
Follow Cabinet at Tunbridge Wells and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Sep 2026 | Treasury and Prudential Indicator Management Report Quarter 1RESOLVED – 1. That the Treasury Management and Prudential Indicator position for 2026/27 be noted. 2. That the foreca... | Noted | Open |
| 24 Sep 2026 | Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s... | Noted | Open |
| 24 Sep 2026 | Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th... | Noted | Open |
| 24 Sep 2026 | New Updated Planning Validation Checklist (Post Public Consultation)RESOLVED – 1. That the Draft Tunbridge Wells Local Validation List be adopted and used in the validation and processi... | Approved | Open |
| 24 Sep 2026 | Update on the Full Council Motion regarding the Maintenance of The Pantiles ColonnadeRESOLVED – 1. That the report covering the updates on the Full Council motion (FC103/25) on the Pantiles be noted. 2.... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.