Resolved
RESOLVED – That the report be noted for information only with any responses to queries included on the ‘tracker’ reported to the next meeting.
Joint Transportation Board noted this item on Monday 16 April 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the report be noted for information only with any responses to queries included on the ‘tracker’ reported to the next meeting.
1. This report describes the current progress with the Kent Freight Action Plan (FAP) and the next steps in the process before it is formally adopted.
2. To update Members on the Kent FAP and the consultation process.
3. The Traffic Management Team has been working to form a draft Kent FAP that will effectively help to address concerns with the movement of freight both through and within the county.
4. The FAP sets out the vision to:
Promote safe and sustainable freight distribution networks into, out of and within Kent, which support local and national economic prosperity and quality of life, whilst working to address any negative impacts on local communities and the environment both now and in the future.
5. The draft FAP has been specifically written to include actions achievable by Kent County Council (KCC), albeit some of them by working with partner organisations. Hence, schemes like Foreign Lorry Road User Charging have been omitted because the decision to implement such a tax regime lies with central government and KCC does not have a direct influence over it. Furthermore, the emphasis of the FAP is on road haulage as this has the greatest impact on our residents and, clearly, the highway.
6. The draft FAP has at its heart six objectives under which a number of action points sit. Some of these actions are already being undertaken, others are beginning to take shape and the rest are for the future development. Timeframes for all actions will be assigned.
Objectives and selected action points
7. This section will outline the six objectives and provide example action points for each.
8. Objective 1: To find a long-term solution to Operation Stack.
8.1Operation Stack is a relatively rare occurrence. Aside from the financial burden on Kent Police and other agencies, the primary negative effect is on business activities in East Kent. 8.2 Action point: KCC will continue to progress the Operation Stack lorry park scheme adjacent to the M20.
9. Objective 2: To take appropriate steps to tackle the problem of overnight lorry parking in Kent.
9.1In 2005, the Kent Overnight Lorry Parking Study found there was demand for 1000 spaces in the county but a supply of only 450 official and 220 unofficial spaces. It was also found that signing on trunk roads was poor, likely resulting in greater use of unofficial and unsuitable sites to avoid the possibility of getting lost.
9.2Action point: KCC are working on updating the recommended lorry route maps for Kent that will also show lorry parking facilities. These will be distributed online and through industry associations.
9.3Action point: KCC will continue investigating the feasibility of new truck stops at various locations along the M20/A20 and M2/A2 corridors.
10. Objective 3: To effectively manage the routing of HGV traffic to ensure that such movements remain on the strategic road network for as much of their journey as possible.
10.1Probably the most widely recognised issue with HGV routing is overreliance on satellite navigation systems that have been designed with cars in mind resulting in large vehicles using inappropriate routes or getting stuck.
10.2Action point: KCC are investigating the development of a lorry route journey planner that would sit on the KCC website so that hauliers would be able to input specific vehicle details, such as weight and height, and generate a suitable route.
10.3Action point: KCC are working with some boroughs and districts, including Maidstone Borough Council, as they start the procurement process for waste collection. Advice is being provided on key routes to keep refuse vehicles off at peak times.
11. Objective 4: To take steps to address problems caused by freight traffic to communities.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Kent Freight Action PlanReport | 72 KB | DownloadRead as text |
Follow Joint Transportation Board at Tunbridge Wells and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Jul 2026 | Minutes of the meeting dated 20 April 2026RESOLVED : That the minutes of the Joint Transportation Board meeting dated 20 April 2026 be accepted as an accurate ... | Decided | Open |
| 13 Jul 2026 | Parking Consultation York Road and Dudley Road, Tunbridge WellsRESOLVED – That the Joint Transport Board notes the results of a public consultation proposing changes to waiting res... | Decided | Open |
| 13 Jul 2026 | Active Travel UpdateRESOLVED – The report was noted. | Noted | Open |
| 20 Apr 2026 | Minutes of the meeting dated 2 February 2026RESOLVED – That the minutes of the meeting dated 2 February 2026 be approved as a correct record. | Approved | Open |
| 20 Apr 2026 | Parish Highways Improvement Projects GrantsRESOLVED – The report was noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.