CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Tunbridge Wells Borough Council
Joint Transportation Board, Monday 16 April 2012 at 6.00pm

A21 Tonbridge - Pembury Dualling - Update

Noted Committee 1 paper

Joint Transportation Board noted this item on Monday 16 April 2012. Below is the council's own wording, with the papers it was decided on.

ItemTB53/11

Resolved

RESOLVED – That the report be noted for information only.
Word for word from the decision Tunbridge Wells published for this meeting. Source: democracy.tunbridgewells.gov.uk

Follow this further

Built from Tunbridge Wells's papers

What the report saysPro

Report to Joint Transportation Board

A21 Tonbridge – Pembury Dualling - Update

A report by Kent County Council, Highways & Transportation, Head of Programmed Work to the Tunbridge Wells Joint Transportation Board on 16 April 2012 – For Information only

Summary: This report updates on the efforts being made to persuade the Government to progress the A21 Tonbridge – Pembury scheme.

1.0Introduction 1.1 The A21 between the Tonbridge and Pembury is a trunk road and under the responsibility of the Highways Agency (HA). It is an unsatisfactory stretch of single carriageway road with very poor vertical and horizontal alignments. It links two busy sections of dual carriageway and carries over 40,000 vehicles per day which is significantly over its capacity. There are serious delays with a significant cost to the local economy and it has a very poor accident record.

1.2Serious delays on this section of the A21 hinder economic growth in Kent and East Sussex, not only because of the increase in journey time but also because of the inherent unreliability of travelling along its length.

1.3The problem has worsened over recent years. The construction of a new flagship NHS hospital as well as a large retail park have both increased traffic flow and will continue to do so. Reasonable accessibility to and from the north to the new hospital at Pembury is entirely dependent on the improvement to this road. The concentration of a number of key services to this hospital from Maidstone increases the need to have good accessibility.

1.4In the post election Comprehensive Spending Review on 26 October 2010, all A21 schemes were cancelled with the exception of A21 Tonbridge - Pembury Dualling which was deferred into the post 2015 funding review period despite a date having been set for the public enquiry into the statutory orders. 2.0 Current Situation 2.1 The scheme has been under consideration since 1984 and over the past twenty years it has been repeatedly delayed. It has a good Cost Benefit ratio which is well above the threshold for good value for money schemes.

2.2Given the significance of the scheme to the economies of Kent and East Sussex, Paul Carter, Leader of KCC, ordered a review of the project with the view to developing a common sense affordable proposal. This review has identified that significant savings could be made using value Engineering to reduce the cost of the scheme with larger savings in the treatment of risk and inflation. The outcome was an estimated cost of less than £70m for the delivery of the scheme as opposed to the HA estimate of over £120m, a difference of over £50m.

2.3This work was the subject of discussion between the Under Secretary of State, Mike Penning and Paul Carter in June 2011. It was agreed that KCC would work with the HA to review the scheme to reach a consensus on the estimated cost to be used as a comparator with competing schemes for development funding of future schemes.

2.4Using KCC’s extensive knowledge of successfully delivering major projects to time and budget. Officers worked with the HA using Value Engineering within the context of Treasury and DFT rules to evaluate the scheme. The outcome was that even using Government criteria the scheme would have an estimated cost of around £88m, some £32m less than the HA’s previous estimate. This was subsequently the subject of HA’s report to the Minister.

2.5KCC has now undertaken two separate reviews of the Highways Agency’s (HA) A21 scheme and each review has shown that it could be delivered for less £70m, approximately £50m less the HA’s estimated cost. This has been reported separately by KCC to the Minister with the recommendation that to achieve the savings, funding should be provided in January 2012 with construction starting in July 2013. To kick start the scheme the Leader of KCC offered to inject some £2m - £4m.

2.6The Minister has considered the report and has raised a number of queries. The Leader of the County Council has replied giving the required clarification, the Minister’s response is awaited.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
A21 Tonbridge: Pembury Dualling: UpdateReport 125 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Tunbridge Wells

Search all
  1. A21 Tonbridge - Pembury Dualling - UpdateThis decision
  2. Application for Consideration - 15/505823/FULL - Owlsnest Wood Tonbridge Road Pembury Tunbridge Wells Kent TN2 4QNRefused

More from Tunbridge Wells Joint Transportation Board

All decisions
MeetingDecisionOutcome
13 Jul 2026 Minutes of the meeting dated 20 April 2026RESOLVED : That the minutes of the Joint Transportation Board meeting dated 20 April 2026 be accepted as an accurate ... Decided Open
13 Jul 2026 Parking Consultation York Road and Dudley Road, Tunbridge WellsRESOLVED – That the Joint Transport Board notes the results of a public consultation proposing changes to waiting res... Decided Open
13 Jul 2026 Active Travel UpdateRESOLVED – The report was noted. Noted Open
20 Apr 2026 Minutes of the meeting dated 2 February 2026RESOLVED – That the minutes of the meeting dated 2 February 2026 be approved as a correct record. Approved Open
20 Apr 2026 Parish Highways Improvement Projects GrantsRESOLVED – The report was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies