Annual Risk Management Report 2011/12

Noted Finance 6 papers

Audit Committee noted this item on Tuesday 26 June 2012. Below is the council's own wording, with the papers it was decided on.

ItemAC11/11

Resolved

RESOLVED – that the Annual risk management report is noted and arrangements for managing strategic risks as set out in the report are approved. REASON FOR RECOMMENDATION: To provide assurance in relation to the control environment and inform the Annual Governance statement.
Word for word from the decision Tunbridge Wells published for this meeting. Source: democracy.tunbridgewells.gov.uk

Follow this further

Built from Tunbridge Wells's papers

What the report saysPro

Report to Audit Committee

Summary

This report sets out the annual report on the Council’s risk management arrangements in accordance with the requirements of the Risk Management Strategy.

LINK TO STRATEGIC COMPASS

The report supports all of the Corporate priorities by ensuring that we are well managed, proactive and deliver value for money services. Risk management also forms part of the Corporate Governance framework.

Report status

For decision.

Route to Implementation/Timetable:

Specific action plans have been developed to identify and manage the authority’s strategic risks which are subject to review and monitoring by Management Board, Cabinet and Audit Committee throughout the year. BACKGROUND/INTRODUCTION

1. The Council is committed to effective management of risk and has a Risk Management Strategy (Appendix E) that sets out the authorities approach and requires an annual report to members on risk.

2. As part of the authority’s governance arrangements the authority is required to manage risks effectively. This report sets out the current position with regard to strategic risks and provides members with an updated position of the current risks.

3. This report updates members on the approach to risk management within the Council and the developments over the last twelve months.

Developments in the last year

4. The Council has monitored and reviewed the Strategic Risk register throughout the year and has adjusted the risk profile accordingly to reflect the changing risk environment. Regular reports have been taken to Cabinet and the Audit Committee for consideration during the year.

5. It was acknowledged that the risk environment had changed significantly over the previous twelve months (2010-2011). It was therefore determined that the Authority commission Zurich Management Services to undertake a fundamental review of Strategic Risks within the organisation to ensure they remained ‘fit for purpose’.

6. This piece of work was undertaken in March/April 2011 which involved Zurich Management Services facilitating a risk workshop with Management Board and the Leader of the Council. This session built on some previous work undertaken earlier in 2011 with a wider audience of officers and Members.

7. As part of this review, risks were refocused /rationalised to align with the current corporate priorities. The review reduced the number of risks from 15 to the 7 current key risk areas which are set out below. The detailed Zurich report was previously considered by Cabinet 16 June 2011. (CAB24/11) however it is reproduced as Appendix B.

8. The table below sets out the movements in the revised risks over the last financial year and shows the current risk rating as at the 31st March 2012.

Risk Target April November March Description Movement Movement Likelihood Impact No. Score 2011 2011 2012 CSR Growth D2 C2 C2 C2 Significant Critical 01 CSR Funding Streams D2 D2 A2 B2 High Critical 02 CSR Partnerships C3 C3 C3 C3 Significant Marginal 03a CSR Joint Services C2 B2 B2 B2 High Critical 03b CSR Organisational Resilience C3 B2 B2 B2 High Critical 04a CSR Information & C2 B2 B2 B2 High Critical 04b Communication Technology CSR Political Environment C3 C3 B2 B2 High Critical 05

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
1 Strategic Risk March 310312 appendix a cross cutting issues /11Appendix 60 KB Download
PDF
Annual Risk Management Report 2011/12Report 91 KB DownloadRead as text
PDF
Risks March 2012: 1 Growth2 /11Report 114 KB Download
PDF
Risks March12: 2 Funding Streams2 /11Report 110 KB Download
PDF
STRATEGICRISKPROFILEMarch2012AppendixB /11Appendix 87 KB Download
PDF
Tunbridge Wells Strategic Risk Report April 11 /11Report 366 KB Download

At this meeting

Whole meeting

On this subject at Tunbridge Wells

Search all
  1. Annual Risk Management Report 2011/12This decision
  2. Annual Risk Management ReportNoted
  3. Annual Risk Management ReportNoted
  4. Annual Risk Management Report 2010/2011Noted

More from Tunbridge Wells Audit Committee

All decisions
MeetingDecisionOutcome
26 Jun 2012 Minutes of previous meeting held on 6 March 2012RESOLVED – that the minutes of the Audit Committee meeting dated 6 March 2012 be confirmed as a correct record. Decided Open
26 Jun 2012 Strategic Compass Monitoring ReportRESOLVED – 1. That the Council’s performance at the end of the financial year 2011/12 is noted; 2. That the details o... Noted Open
26 Jun 2012 Benefit Fraud Partnership Annual UpdateRESOLVED - That the performance of the Benefits Fraud Team during 2011/12 ... view the full minutes text for item AC6/11 Decided Open
26 Jun 2012 Audit Committee Annual Report 2011/12That the Audit Committee’s Annual report is agreed. REASONS FOR RECOMMENDATION: The Annual Audit Committee report pro... Agreed Open
26 Jun 2012 Internal Audit Annual Report 2011/12That the Head of Audit Partnership’s opinion that substantial reliance can be placed on the Council’s control environ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies