That the be noted and that the arrangements for managing strategic risks set out in the report be approved 2. That the revisions proposed to the risk register once the amendments have been formalised be noted 3. That the risks the Committee wishes to consider at future meetings be identified and that Jonathan MacDonald be invited to the 23 September meeting to discuss risk responsibility
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
This report is the annual report on the Council’s risk management arrangements as required by the Risk Management Strategy.
LINK TO STRATEGIC COMPASS
The report supports all of the Corporate priorities by ensuring that we are well managed, proactive and deliver value for money services. Risk management also forms part of the Corporate Governance framework.
Report status
For information
Route to Implementation/Timetable:
Specific action plans have been developed to identify and manage the authority’s strategic risks which are subject to review and monitoring by Management Board, Cabinet and Audit & Governance Committee throughout the year. BACKGROUND/INTRODUCTION
1. The Council is committed to the effective management of risk and has a Risk Management Strategy that sets out the authority’s approach and requires an annual report to Members on risk.
2. As part of the authority’s governance arrangements the authority is required to manage risks effectively this report sets out the position on strategic risks and provides members with an updated position.
3. This report informs members on the approach to risk management within the Council and the developments over the last twelve months.
Developments in the last year
4. Acknowledging that the risk environment had changed significant since the last review, Management Board commissioned Zurich Management Services to facilitate a risk refresh workshop.
5. The workshop was held in December 2013 and was attended by Management Board, Heads of Service and Members. .
6. As part of this review, risks were refocused to align to the corporate priorities and a revised Strategic Risk Register was created. The draft register was considered by the Audit & Governance Committee on 25 March 2014 (AG51/13) and subsequently approved by Cabinet on 16 May 2014 (CAB177/13)
7. The review identified nine key risks.
8. Appendix 1 below summarises the Strategic Risks as at 31 March 2014
No Risk Scenario Likelihood Impact
1 Cinema site Remains undeveloped (5) High (3) Severe 2 Being unable to maximise economic opportunities and resolve infrastructure (5) High (3) issues Severe 3 Resident Engagement (4) (3) Significant Severe 4 Unable to plan financially over the longer term (6) Very (3) High Severe 5 National policy changes in short term that impact negatively on TWBC, and (6) Very (2) on direction High Medium 6 Missing something significant (4) (2) Significant Medium 7 Being unable to meet expectations within resources (5) High (2) Medium 8 Inspection decision which challenges housing targets Vs supply (4) (4) Significant Major 9 Not managing control and change effectively – Staff , Management & (4) (3) Political Significant Severe 9. The risk register is a living document and is kept under review throughout the year and amended when necessary to reflect changes in the risk environment and responses to continuing mitigating actions. Management Board met recently to review the register. This review identified a number of further amendment and adjustments to reflect the changing risk environment and developments since earlier review. The details of these amendments are still being finalised however an outline summary is set out below.
No Risk Scenario Proposed Amendments 1 Cinema site Remains undeveloped • Update with demolition details and note increased risk as possible intervention gets closer. • Raise at September Audit Committee (diarise for JMD) 2 Being unable to maximise economic • MB confirmed that ranking was correct but opportunities and resolve infrastructure issues need to acknowledge that there is no solution to congestion problems. 3 Resident Engagement • no amendments 4 Unable to plan financially over the longer term Change Member Risk Owner to Cllr Rusbridge
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.