(1) That the actual spend to date and the forecast outturn for capital schemes to 31 December 2012 is noted. (2) That the re-scheduling of capital schemes to 2013/14 (see note 6) is approved. (3) That the variations set out in notes 8 to 12 are approved. (4) That the newly approved budget as set out in note 7 and the current capital requirement from reserves as detailed in note (21) are noted. REASON FOR RECOMMENDATIONS: All of the increases reported have either been approved at other Cabinet meetings or spent already. (1) That the actual spend to date and the forecast outturn for capital schemes to 31 December 2012 is noted. (2) That the re-scheduling of capital schemes to 2013/14 (see note 6) is approved. (3) That the variations set out in notes 8 to 12 are approved. (4) That the newly approved budget as set out in note 7 and the current capital requirement from reserves as detailed in note (21) are noted. REASON FOR RECOMMENDATIONS: All of the increases reported have either been approved at other Cabinet meetings or spent already.
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
This report compares capital projects approved by Cabinet with actual capital expenditure to the 31 December 2012 and the projected outturn for the year. The Capital Programme for the years to 2015/16 has been created through a formal application and approval process. All new schemes must be agreed by Cabinet before they can be included in the Capital Programme. In Quarter 2 Cabinet approved a total of £26,266,000 capital spending, of which £22,280,000 was due to be spent in 2012/13. The actual expenditure to December 2012 was £1,767,000, £341,000 of which was spent in Quarter 3. The forecast outturn for the year is now £3,473,000. This indicates that a further £1,706,000 is expected to be spent in the following 3 months. This report seeks to inform Cabinet of the level of capital expenditure for the Quarter 3 and to obtain formal approval for the adjustments to the 2012/13 forecast outturn.
LINK TO STRATEGIC COMPASS
This report supports the Value and Community quadrants of the strategic compass in particular that we manage public finances effectively.
Report status
For decision
Route to Implementation/Timetable:
Cabinet can make these decisions Portfolio Holder Decisions I confirm that I have read the report and approve it for publication
Signed: Councillor James Scholes Dated: 7 February 2013
BACKGROUND/INTRODUCTION
(1)At their meeting on 14 June 2012, Cabinet approved schemes to be met from the Capital Programme for the years from 2012/13 to 2015/16.
(2)The figures approved by Cabinet were on the basis of the net cost to be met by the Council, either from reserves or from the sale of existing assets. These have been adjusted to a gross basis, showing the total proposed capital investment of £26,988,000 during that period, of which £23,991,000 was to be spent during 2012/13.
(3)Appendices B and C set out in gross and net terms the amounts approved against the forecast outturn to 31 March 2013. They also show variances of actual to forecast and detail that expenditure which is re-scheduled to 2013/14.
WHAT IS THE ISSUE THAT REQUIRES A DECISION AND WHAT DOES THIS MEAN FOR THE PEOPLE OF TUNBRIDGE WELLS?
Budget Approved since Q2
(4)In Quarter 2, Cabinet approved £50,000 to install public art works along the cycle route that runs from the town centre to North Farm (TFD).
(5)The table below shows how the approved capital expenditure has evolved; incorporating approvals obtained up to and including the December 2012 Cabinet.
Approved Capital Spend as at £000's 31 December 2012
Original gross approvals 23,991 Lagan CRM System Upgrade CAB205/11 20 Museum redevelopment CAB218/11 32 CCTV safety car CAB206/11 60 MKIP Shared Service CAB193/11 100 Total approvals as at Quarter 1 24,203
Disbled Facilities Grant CAB61/12 (107) Housing Renewal Grants CAB61/12 (100) CPO 18 Victoria Road CAB61/12 (28)
Total approvals as at Quarter 2 23,968 £000's Assembly Hall replacement lighting desk CAB74/12 35 Permit Gateway CAB61/12 26 8 Dudley Road CAB23/12 300 Calverley Grounds events infrastructure CAB49/12 60 Repayment of loan CAB105/12 (1,000) Re-scheduled to 2013/14 CAB105/12 (989) Heritage Partnership Grants CAB105/12 (40) Conservation Area Enhance CAB105/12 (75) CPO 18 Victoria Road CAB105/12 2 Streetlighting Columes CAB76/12 40 Bowling Green Watering System CAB105/12 (4) DFG CAB105/12 (100) Sherwood Lake redevelopment CAB46/11 43 IT CAB105/12 14 North Farm Art Work CAB105/12 50
Total approvals as at Quarter 3 22,330
Rescheduling of Capital Schemes
(6)In Quarter 3, Officers have reported deferrals in expenditure on a number of projects. This has reduced the gross expenditure forecast by £17,918,000. The details can be seen in Appendix D.
New budget Approvals
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.