(1) That the forecast outturn position for the year and the variances to the revised budget and forecast outturn as at quarter 3 are acknowledged. (2) That the write off of £476,452.01 of Business Rates debts and £10,541.68 of housing rents debts are approved. REASON FOR RECOMMENDATIONS: To recognise the revenue expenditure and impact on reserves for the year ending 31 st March 2013. (1) That the forecast outturn position for the year and the variances to the revised budget and forecast outturn as at quarter 3 are acknowledged. (2) That the write off of £476,452.01 of Business Rates debts and £10,541.68 of housing rents debts are approved. REASON FOR RECOMMENDATIONS: To recognise the revenue expenditure and impact on reserves for the year ending 31 March 2013.
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
This report shows the actual expenditure on services compared to the revised budget for the period ended 31 December 2012, and the forecast outturn position, highlighting significant variances from the revised annual budget.
The forecast outturn shows that additional funding of £82,000 will be required from the General Fund in order to balance the budget. Whilst a £188,000 overspend is forecast on the cost of services, £93,000 has been funded by additional government grants and £13,000 by surplus interest income over expenditure from the loan. This report provides full details of all variances.
This is an improvement of £51,000 in the position since Quarter 2. However, this is a considerable achievement as it includes the impact of the dissolution of the John Laing partnership at a cost of £292,000 and a new provision for £50,000 due to recent information made available by Municipal Mutual Insurance Limited regarding asbestosis claim liability run-offs. Officers are working very hard to remedy the remaining shortfall.
LINK TO STRATEGIC COMPASS
This report supports the Value and Community quadrants of the strategic compass in particular that we manage public finances effectively.
Report status
For decision
Route to Implementation/Timetable:
Cabinet can make these decisions
Portfolio Holder Decisions I confirm that I have read the report and approve it for publication
Signed: Councillor James Scholes Dated: 7 February 2013 BACKGROUND/INTRODUCTION
(1) This report shows the revenue actual outturn for the period ended 31 December 2012 and highlights the significant changes from the approved revised budget.
(2) The forecast outturn Net Expenditure on Services shows an increase from the revised budget of £188,000. However, only £82,000 will need funding from the General Fund as an additional £93,000 has been received in New Burdens Grants and a further £13,000 can be funded from surplus loan interest.
WHAT IS THE ISSUE THAT REQUIRES A DECISION AND WHAT DOES THIS MEAN FOR THE PEOPLE OF TUNBRIDGE WELLS?
Summary Outturn – See Appendix B (3) Appendix B shows the overall income and net expenditure on services outturn position as at 31 December 2012. Total income and expenditure on services can be seen in greater detail within Appendix C, which provides further detail per service area. The approved budget was set by Council on 22 February 2012 and does not change. The revised budget is used to record virements amongst service areas and to/from reserves, whilst the forecast outturn is used to record the reporting of savings, overspends and allocations from reserves.
(4) It can be seen that the forecast outturn for expenditure on services has increased by £188,000 compared to the revised budget. This is due to many variances detailed in the Key Variances table in Appendix D.
(5) The net interest forecast from investments increased by a further £20,000 in quarter 3, totalling £120,000 over budget. This is because a further £2.9m has been made available for investment in quarter 3, due mainly to the re-scheduling of the capital programme. However, the remaining investment options that ensure compliance with the investment strategy give very poor rates of return and the average interest rate has fallen from 1.99% in quarter 1 to 1.93% in quarter 3. Considering the state of the market and the budgeted average rate of 1.72%, this is still an exceptional investment performance over the year. The additional interest forecast is transferred to the Strategic Plan Reserve.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.