RESOLVED 1. That the retention by Council of the freehold and redevelopment of the John Street car park site be approved; 2. That it be recommended to Full Council that a £2.521 million capital budget for this project as set out in exempt Appendix E to the report, be approved; 3. That, subject to Full Council’s approval of a £2.521 million capital budget for the project, progression of the design and construction of the John Street car park development as described in this report, be approved; 4. That the Development be recognised as a strategic risk to the Council; 5. That, subject to Full Council approval of a £2.521 million capital budget for the project, the Deputy Chief Executive and the Section 151 Officer in consultation with the Leader of the Council and the Portfolio Holder for Finance and Governance be authorised to submit details to discharge the conditions of the outline planning approval, invite competitive tenders for the development and accept a tender within the costs given in this report, and oversee the development to completion; and 6. That the Deputy Chief Executive, Section 151 Officer and Head of Legal Partnership in consultation with the Leader of the Council and the Portfolio Holder for Finance and Governance be authorised to investigate whether there would be advantages to establishing a company wholly owned by the Council to progress some or all the aspects of the development including being the eventual vehicle for holding the freehold or leasehold interest of the site. REASON FOR DECISIONS: To progress the John Street car park redevelopment opportunity to enhance the site, provide additional revenue and to meet the objectives of the Council as stated in the Five Year Plan and strategically summarised in the Asset Management Plan approved by Full Council.
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
In its decision CAB 43/13, on 1 August 2013 Cabinet approved funding to progress a number of development opportunities, including the car park at John Street, through initial design and cost stage to present to Cabinet for approval to tender and redevelop such sites.
The cost of this development is currently outside of the Budget and Policy Framework and will require the approval of Full Council for a Capital Budget of £2.521 million.
This report seeks approval of the concept design and draft programme for the proposed redevelopment of John Street Car Park; approval to the Council retaining the freehold of the asset and redeveloping the site and that Cabinet recommends to Full Council that capital funding to be allocated to enable the redevelopment of John Street car park in accordance with the proposals.
The proposed redevelopment will assist in the delivery of the Council’s Five Year Plan and Strategic Compass as described below. It will also help to achieve Local Plan targets and assist in making the Council more self sufficient.
Authority is sought to delegate approval to the Deputy Chief Executive and the Section 151 Officer in consultation with the Leader of the Council and the Portfolio Holder for Finance and Governance to progress the scheme and award a contract for the construction works and to oversee the development to completion.
Authority is also sought to delegate approval to investigate whether there would be advantages to establishing a company wholly owned by the Council to progress some or all the aspects of the development including being the eventual vehicle for holding the freehold interest of the site. LINK TO STRATEGIC COMPASS
The proposed development will support the Community and Value priorities of the Council by supporting a prosperous and confident Tunbridge Wells. It will demonstrate delivery of value through innovation and will seek to optimise income. The proposed development will enhance the built environment, provide business opportunities, increase employment and provide new residential properties. In addition, the proposed redevelopment will help to achieve Local Plan targets, contribute to the New Homes Bonus, increase the Council Tax base and Business Rate base and assist in making the Council more self sufficient. Finally, the proposals will make better use of Council assets.
Report status For decision by Cabinet and for recommendation to Full Council for a decision on Recommendation 2.
Route to Implementation/Timetable:
Comments from the Development Advisory Panel and the Finance and Governance Cabinet Advisory Board have been incorporated within this report. If this report is approved by Cabinet a further report will go to Full Council on 15 October 2014 to seek approval for an additional capital budget. If the capital budget is approved the project will proceed as shown in the Draft Programme at Appendix C.
Portfolio Holder Declaration:
I confirm that I have read the report and approve it for publication.
Signed: Councillor David Jukes Dated: 4 September 2014
BACKGROUND / INTRODUCTION
1 On the 1 August 2013 Cabinet approved funding to progress a number of development opportunities including John Street car park. Under the framework of the approved budget external consultants were appointed through the SCAPE framework and produced an initial design and feasibility which obtained outline planning approval from the Planning Committee in January 2014. A draft timeline was produced for the design and construction process.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.