John Street Car Park Redevelopment

Approved Committee 3 papers

Full Council approved this item on Wednesday 15 October 2014. Below is the council's own wording, with the papers it was decided on.

ItemFC36/14

Resolved

RESOLVED – That a £2.521 million capital budget be approved for the John Street car park project as set out in the exempt Appendix C of the report. REASON FOR RECOMMENDATIONS To progress the John ... view the full minutes text for item FC36/14
Word for word from the decision Tunbridge Wells published for this meeting. Source: democracy.tunbridgewells.gov.uk

Follow this further

Built from Tunbridge Wells's papers

What the report saysPro

Report to Full Council

Summary

In its decision on 1 August 2013 (reference CAB 43/13) Cabinet approved funding to progress a number of development opportunities, including the car park at John Street, through initial design and cost stage to present to Cabinet for approval to tender and redevelop such sites.

On the 18 September 2014 Cabinet approved that the Council should retain the freehold of the asset, redevelop the site as shown in the concept design proposals and the draft programme. The cost of this development is currently outside of the Budget and Policy Framework and will require the approval of Full Council for a Capital Budget of £2.521 million. Cabinet recommends to Full Council that capital funding be allocated to enable the redevelopment of John Street car park in accordance with the proposals.

Cabinet gave delegated approval to the Deputy Chief Executive and the Section 151 Officer in consultation with the Leader of the Council and the Portfolio Holder for Finance and Governance to progress the scheme and award a contract for the construction works and to oversee the development to completion.

Cabinet also gave delegated approval to the Deputy Chief Executive, Section 151 Officer and the Head of Legal Partnership in consultation with the Leader of the Council and the Portfolio Holder for Finance and Governance to investigate whether there would be advantages to establishing a company wholly owned by the Council to progress some or all the aspects of the development including being the eventual vehicle for holding the freehold interest of the site.

The proposed redevelopment will assist in the delivery of the Council’s Five Year Plan and Strategic Compass as described below. It will also help to achieve Local Plan targets and assist in making the Council more self sufficient. LINK TO STRATEGIC COMPASS

The proposed development will support the Community and Value priorities of the Council by supporting a prosperous and confident Tunbridge Wells. It will demonstrate delivery of value through innovation and will seek to optimise income. The proposed development will enhance the built environment, provide business opportunities, increase employment and provide new residential properties. In addition, the proposed redevelopment will help to achieve Local Plan targets, contribute to the New Homes Bonus, increase the Council Tax base and Business Rate base and assist in making the Council more self sufficient. Finally, the proposals will make better use of Council assets.

Report status For decision by Full Council.

Route to Implementation/Timetable:

If this report is approved by Full Council the project will proceed as shown in the Draft Programme agreed by Cabinet on the 18 September 2014. BACKGROUND / INTRODUCTION

1 On the 1 August 2013 Cabinet approved funding to progress a number of development opportunities including John Street car park. An initial design and feasibility obtained outline planning approval from the Planning Committee in January 2014.

2 On the 18 September Cabinet approved the concept design for a development comprising of three retail units, four number two bedroom flats, one number three bedroom flat, servicing area for the retail units and 63 parking spaces. The plan at Appendix B shows the location of the proposed scheme.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
App A /14Appendix 103 KB Download
PDF
App B Plan /14Appendix 248 KB Download
PDF
John Street Car Park RedevelopmentReport 122 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Tunbridge Wells

Search all
  1. John Street Car Park RedevelopmentThis decision
  2. John Street and Yew Tree Road Car Parks - Issue of Season TicketsDecided
  3. John Street Car ParkDecided
  4. Application for Consideration - 18/01493/FULL - 2 John Street, Royal Tunbridge Wells, Kent TN4 9RUApproved
  5. Application for Consideration - 15/510585 - Car Park, John Street, Royal Tunbridge WellsApproved
  6. John Street Car ParkApproved

More from Tunbridge Wells Full Council

All decisions
MeetingDecisionOutcome
15 Jul 2026 Minutes of the meetings dated 22 April and 20 May 2026RESOLVED – That the minutes of the meetings dated 22 April and 20 May 2026 were approved as a correct record. Approved Open
15 Jul 2026 Forward Plan as at 24 June 2026RESOLVED – That the Forward Plan as at 24 June 2026 be noted. Noted Open
15 Jul 2026 Reappointment of Independent Member to Audit and Governance CommitteeRESOLVED – That [name removed] be re-appointed to the Audit and Governance Committee as Independent Member for a furt... Decided Open
15 Jul 2026 Southborough and High Brooms Neighbourhood Development PlanRESOLVED – 1. That the Southborough and High Broom Neighbourhood Development Plan (SHBNDP) be formally ‘made’ (adopte... Approved Open
15 Jul 2026 Sandhurst Neighbourhood Development PlanRESOLVED – 1. That the Sandhurst Neighbourhood Development Plan (SNDP) be formally ‘made’ (adopted) and become part o... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies