Planned Audit Fee 2015/16

Agreed Finance 3 papers

Audit and Governance Committee agreed this item on Tuesday 30 June 2015. Below is the council's own wording, with the papers it was decided on.

ItemAG11/15

Resolved

That the planned audit fee as seen in Appendix B of this report be agreed.
Word for word from the decision Tunbridge Wells published for this meeting. Source: democracy.tunbridgewells.gov.uk

Follow this further

Built from Tunbridge Wells's papers

What the report saysPro

Report to Audit and Governance Committee

Summary

This report outlines the planned audit fee for 2015/16 as notified by the External Auditor, Grant Thornton. The scale of fees had been set by the Audit Commission just before it closed on 31 March 2015.

LINK TO STRATEGIC COMPASS

This report supports the ‘value’ quadrant on the Strategic Compass.

Report status

For decision.

Route to Implementation/Timetable:

For consideration and agreement by the Audit and Governance Committee. BACKGROUND/INTRODUCTION

1. Each year the External Auditor undertakes the following pieces of work:

 Audit of financial statements;  Value for money conclusion;  Whole of government accounts return; and  Certification of grant claims and returns.

2. The Council is charged for this work in accordance with the scale of fees set by the Audit Commission.

3. The scale of fees for 2015/16 has been set at £51,230, which compares to the audit fee of £68,306 for 2014/15.

WHAT IS THE ISSUE THAT REQUIRES A DECISION AND WHAT DOES THIS MEAN FOR THE PEOPLE OF TUNBRIDGE WELLS?

4. The comprehensive and independent auditing of public bodies is part of the assurance process to ensure that the public have confidence in the financial reporting and management of the Council.

5. The estimated fee for 2015/16 is a saving of £17,076 over the audit fee for 2014/15. This assumes that the Council has no significant audit risks and has in a place a sound control environment that ensures the auditor is provided with complete and materially accurate financial statements with supporting working papers within agreed timeframes.

6. In addition to this Council’s strong financial track record the procurement process undertaken in 2012 also contributed to the reduction in audit fees. Grant Thornton UK LLP were appointed to audit the accounts of the Council from 1 September 2012 for five years.

7. The audit work will be undertaken in compliance with the statutory requirements governing audit work, in particular:

 The Audit Commission Act 1988; and  The Code of Audit Practice for Local Authorities.

8. A schedule of the expected audit reports is set out in Appendix B; these will be considered by the Audit and Governance Committee and made publicly available on the Council’s website.

WHO HAVE WE CONSULTED AND HOW? (OR WHO WILL WE CONSULT FOLLOWING THE DECISION?)

9. The External Auditor has consulted with the Chief Executive and the Finance Director; the Audit and Governance Committee is now being asked for their approval.

HOW WILL THE DECISION BE COMMUNICATED?

10. This report will be published on to the Council’s website. WHAT ALTERNATIVE ACTION COULD WE TAKE? (where appropriate)

11. The Audit and Governance Committee could choose not to accept the proposed audit fee.

CONCLUSIONS

12. The audit fee set covers the fee required by auditors to carry out the work necessary to meet their statutory responsibilities in accordance with the Code of Practice.

RECOMMENDATION(S):

1. That the Audit and Governance Committee consider and agree the planned audit fee in Appendix B.

REASON(S) FOR RECOMMENDATION(S):

The Audit and Governance Committee’s functions and delegations, as outlined in its constitution and terms of reference states that it should:

 agree the external Audit Plan for the year;  approve the cost of the audit;  consider specific reports as agreed with the external audit work and to ensure it gives value for money; and  comment on the scope and depth of external audit work and to ensure it gives value for money.

Contact Officer: Lee Colyer, Finance Director 01892 554132

William Benson Chief Executive

Background Papers  None

APPENDICES TO REPORT  Appendix A: Cross Cutting Issues  Appendix B: Planned audit fee notification 2015/16

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
/15Appendix A 66 KB Download
PDF
Planned Audit Fee Letter 2015-16 /15Appendix B 79 KB Download
PDF
Planned Audit Fee 2015/16Report 82 KB DownloadRead as text

More from Tunbridge Wells Audit and Governance Committee

All decisions
MeetingDecisionOutcome
2 Jul 2026 Minutes of the meeting of the Audit and Governance Committee dated 10 March 2026RESOLVED – That the minutes of the meeting dated 10 March 2026 be approved as a correct record. Approved Open
2 Jul 2026 Future Work Programme as at 2 July 2026RESOLVED – That the Future Work Programme as at 2 July 2026, be noted. Noted Open
2 Jul 2026 External Audit Progress and Sector Update ReportRESOLVED - That the committee consider and agree the Audit Progress and Sector Update Report. Agreed Open
2 Jul 2026 Internal Audit Report & Annual Audit Opinion 2025/26RESOLVED – 1. That the Audit & Governance Committee notes the Head of Audit Partnership opinion. 2. That the Audit & ... Decided Open
10 Mar 2026 Minutes of the meeting of the Audit and Governance Committee dated 25 November 2025RESOLVED – That the minutes of the meeting dated 25 November 2026 be approved as a correct record. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies