Resolved
RESOLVED - That the Audit and Governance Committee considered and agreed the planned audit fee.
Audit and Governance Committee agreed this item on Tuesday 2 July 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED - That the Audit and Governance Committee considered and agreed the planned audit fee.
Audit and Governance 2 July 2019 Committee Is the final decision on the recommendations in this report to be made at this meeting? Yes
Planned Audit Fee 2019/20 Final Decision-Maker Audit and Governance Committee Portfolio Holder(s) Councillor Dawlings – Portfolio Holder for Finance & Governance Lead Director Lee Colyer, Director of Finance, Policy & Development Head of Service Jane Fineman, Head of Finance and Procurement Lead Officer/Report Author Elizabeth Jackson, Engagement Lead for Grant Thornton LLP Classification Non-exempt Wards affected All Wards
This report makes the following recommendations to the final decision-maker: (1) That the Audit and Governance Committee consider and agree the planned audit fee set out in Appendix A.
This report relates to the following Five Year Plan Key Objectives: A Confident Borough A Green Borough A Confident Borough
Timetable Meeting Date Discussion with Portfolio Holder 10 June 2019 Audit and Governance Committee 2 July 2019 Planned Audit Fee 2019/20
1. PURPOSE OF REPORT AND EXECUTIVE SUMMARY
This report outlines the planned audit fee for 2019/20 as notified by the External Auditor, Grant Thornton. The scale of fees has been set by Public Sector Audit Appointments Limited (PSAA) following the closure of the Audit Commission in March 2015.
2. INTRODUCTION AND BACKGROUND
2.1Each year the External Auditor undertakes the following pieces of work:
Audit of financial statements; Value for money conclusion; and Whole of government accounts return.
2.2The Council is charged for this work in accordance with the scale of fees set by Public Sector Audit Appointments Limited (PSAA).
2.3The scale of fees for 2019/20 has been set at £39,447, unchanged from the fee for 2018/19.
2.4The Council is also charged an audit fee in relation to the certification of grant claims which is a separate arrangement as this work falls outside of the PSAA contract.
2.5The comprehensive and independent auditing of public bodies is part of the assurance process to ensure that the public have confidence in the financial reporting and management of the Council.
2.6The estimated fee for 2019/20 is unchanged from the 2018/19 level. This assumes that the Council has no significant audit risks and has in a place a sound control environment that ensures the auditor is provided with complete and materially accurate financial statements with supporting working papers within agreed timeframes.
2.7In addition to this Council’s strong financial track record the procurement process undertaken also contributed to the reduction in audit fees. Grant Thornton UK LLP were appointed to audit the accounts of the Council from 2018/19 for five years with an optional two year extension.
2.8The audit work will be undertaken in accordance with International Standards on Auditing.
2.9A schedule of the outline audit timetable is set out in Appendix A
3. AVAILABLE OPTIONS
3.1The Audit and Governance Committee could choose not to accept the proposed audit fee. This is not recommended as there are no grounds at this stage for rejecting the proposed fee. 4. PREFERRED OPTION AND REASONS FOR RECOMMENDATIONS
4.1The External Auditor has consulted with the Chief Executive and the Director of Finance, Policy and Development. The Audit and Governance Committee is now being asked for their approval.
4.2This report will be published on the Council’s website.
5. CONSULTATION RESULTS AND PREVIOUS COMMITTEE FEEDBACK
5.1The audit fee set covers the fee required by auditors to carry out the work necessary to meet their statutory responsibilities in accordance with the Code of Practice.
5.2The Audit and Governance Committee’s functions and delegations, as outlined in its constitution and terms of reference state that it should:
• agree the external Audit Plan for the year; • approve the cost of the audit; • consider specific reports as agreed with the external audit work and to ensure it gives value for money; and comment on the scope and depth of external audit work and to ensure it gives value for money.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
10 Planned Audit Fee Appendix A /19Appendix | 116 KB | Download |
PDF |
Planned Audit Fee 2019/20Report | 112 KB | DownloadRead as text |
Follow Audit and Governance Committee at Tunbridge Wells and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Jul 2026 | Minutes of the meeting of the Audit and Governance Committee dated 10 March 2026RESOLVED – That the minutes of the meeting dated 10 March 2026 be approved as a correct record. | Approved | Open |
| 2 Jul 2026 | Future Work Programme as at 2 July 2026RESOLVED – That the Future Work Programme as at 2 July 2026, be noted. | Noted | Open |
| 2 Jul 2026 | External Audit Progress and Sector Update ReportRESOLVED - That the committee consider and agree the Audit Progress and Sector Update Report. | Agreed | Open |
| 2 Jul 2026 | Internal Audit Report & Annual Audit Opinion 2025/26RESOLVED – 1. That the Audit & Governance Committee notes the Head of Audit Partnership opinion. 2. That the Audit & ... | Decided | Open |
| 10 Mar 2026 | Minutes of the meeting of the Audit and Governance Committee dated 25 November 2025RESOLVED – That the minutes of the meeting dated 25 November 2026 be approved as a correct record. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.