RESOLVED – 1. That the business case as prepared and presented by the Mid Kent Services Director be agreed subject to any amendments following necessary consultation with affected staff; 2. That Tunbridge Wells Borough Council exits the Planning Support Collaboration Agreement with the consent of Maidstone and Swale Borough Councils; and 3. That the continuation of the shared Land Charges Service between Maidstone, Swale and Tunbridge Wells Borough Councils be noted. REASON FOR DECISION: The Council needs to provide a Planning Support service which meets the expectations of the Council and stakeholders, and for the reasons set out in the report the best prospect for achieving this would be to re-establish a standalone in-house service.
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
This report seeks to approve the implementation of the ‘in principle’ decision of Cabinet on 6 August 2015 that the Planning Support service be brought back in-house.
Tunbridge Wells Borough Council along with Maidstone and Swale Borough Councils established a shared Planning Support service which came into being on 1 June 2014.
The efficiency and quality elements of the critical success criteria agreed in the business case are not being fully met. Performance has improved since the shared service came under the responsibility of the Mid-Kent Services Director from May 2015. Planning is an important front-line service and the suggested way to bring about sustainable improvement in performance and cost effectiveness is to withdraw from the shared service and re- establish a Tunbridge Wells based Planning Support service.
It is important to recognise the impact on both Maidstone and Swale Borough Councils and the associated risks that a change in delivery will bring about.
Just as the shared service was established through a three-way agreement, it can only come to an end through a joint three-way decision.
Following this decision the process of consulting on the required staffing changes can commence and instructions issued to the software providers. Maidstone Borough Council will lead on these aspects as the employer of the staff and owner of the contract with the software supplier.
The timeframe of this work currently indicates a go-live date for a stand-alone Tunbridge Wells Planning Support service in July 2016.
LINK TO STRATEGIC COMPASS
This report supports the ‘customers’ and ‘value’ quadrants on the Strategic Compass. Report status
For decision
Route to Implementation/Timetable:
The recommended action will be implemented following approval by Cabinet.
BACKGROUND/INTRODUCTION
1. In June 2013 the Cabinets of Tunbridge Wells, Maidstone and Swale Borough Councils considered a report on entering into a Planning Support shared service. The business case was jointly agreed and the service went live on 1 June 2014. The new service combined the administrative functions of the three councils’ Planning Departments, leaving the Development Management and Planning Policy functions with each council.
2. The following critical success factors were set for the new shared Planning Support service:
Efficiencies - Delivery of significant savings through economies of scale, sharing systems and processes and carrying out common work once;
Quality - Provision of reliable, accurate and flexible support to the Planning teams in order to enable them to meet their targets;
Resilience - Robust cover and sharing of specialisms to reduce the impact of absences and spikes in workload on service quality and provide opportunities to learn and develop; and
Culture - Creation of a service where the culture is pro-active in serving the Mid- Kent public as a whole and for the benefit of all Mid-Kent Planning authorities in the Mid-Kent Improvement Partnership.
3. The joint report approved by the Cabinets of Tunbridge Wells, Maidstone and Swale Councils concluded that:
“The ambitious vision is of a high performing Planning Support service that delivers high quality, accurate and timely support to customers including planning departments and external customers with a culture of ownership of overall planning targets, as well as the service’s own target, whilst reducing overall costs to partners.”
4. The shared service resulted in the following major operational changes:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.