RESOLVED – 1. That the revised Mid Kent Services (MKS) objectives and strategic priorities be agreed; 2. That the revised MKS Governance Arrangements be agreed and authority be delegated to the Chief Executive to sign the Agreement; 3. That the model MKS Shared Service Collaboration Agreement template be agreed; and 4. That authority be delegated to the Head of Legal Partnership in consultation with the Portfolio Holder for Finance and Governance and the Chief Executive to make any further minor amendments as necessary to the documents described in 2 and 3 above. REASON FOR DECISION: Mid Kent Services continues to support the provision of shared services across the three Councils. The commitment to shared service working is set out in the Council’s Five Year Plan as a means of providing services efficiently and with appropriate expertise. It is therefore appropriate to revise and amend the governance documents to bring them up to date and to ensure that they reflect the current operating practices of Mid Kent Services.
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
Cabinet 4 July 2016 Is the final decision on the recommendations in this report to be made at this meeting? Yes
Mid Kent Services Revised Governance Arrangements Final Decision-Maker Cabinet Portfolio Holder(s) Councillor Paul Barrington-King – Portfolio Holder for Finance and Governance Management Board Lead William Benson – Chief Executive Head of Service John Scarborough – Head of Legal Partnership Lead Officer/Report Author Estelle Culligan – Deputy Head of Legal Partnership Classification Non-exempt Wards affected All
This report makes the following recommendations to the final decision-maker: 1. That the revised Mid Kent Services (MKS) objectives and strategic priorities be agreed;
2. That the revised MKS Governance Arrangements be agreed and authority be delegated to the Chief Executive to sign the Agreement;
3. That the model MKS Shared Service Collaboration Agreement template be agreed; and
4. That authority be delegated to the Head of Legal Partnership in consultation with the Portfolio Holder for Finance and Governance and the Chief Executive to make any further minor amendments as necessary to the documents described in 2 and 3 above.
This report relates to the following Five Year Plan Key Objectives: A Prosperous Borough A Confident Borough Mid Kent Services continues to support the provision of shared services across the three Councils. The commitment to shared service working is set out in the Council’s Five Year Plan as a means of providing services efficiently and with appropriate expertise. It is therefore appropriate to revise and amend the governance documents to bring them up to date and to ensure that they reflect the current operating practices of Mid Kent Services. Timetable Meeting Date Finance and Governance Cabinet Advisory 27 June 2016 Board Cabinet (co-located meeting with Swale 4 July 2016 Borough Council Cabinet and Maidstone Borough Council Policy and Resources Committee) Mid Kent Services Revised Governance Arrangements
1. PURPOSE OF REPORT AND EXECUTIVE SUMMARY
1.1This report presents the amendments to the Governance Arrangements for Mid Kent Services and the model Shared Services Collaboration Agreement.
1.2These amendments have been discussed and agreed by the MKS Chief Executives and the MKS Board, with input and advice from the Director of Shared Services, s151 Officers and Monitoring Officers.
1.3Formal approval of the documents is now required from Tunbridge Wells, Swale and Maidstone Borough Councils’ appropriate decision making bodies.
1.4Cabinet has authority to make the decisions on behalf of Tunbridge Wells BC.
1.5In order to ensure consideration of the issues by the three Councils simultaneously, a co-located meeting will take place on 4 July, comprising Tunbridge Wells BC Cabinet, Maidstone BC Policy & Resources Committee, and Swale BC Cabinet.
2. INTRODUCTION AND BACKGROUND
Governance Arrangements
2.1The Agreement covering the Governance Arrangements of the Mid Kent Improvement Partnership (MKIP), now called Mid Kent Services (MKS), was originally prepared in 2008. It was updated in May 2012, and stated to be for a period of another four years. That period expired on 30 April this year.
2.2With the passage of time, the experience of managing shared services and the increased number of shared services, it became apparent that the document needed to be revised. The main changes which members are requested to note are set out below:
2.3The arrangements are now permanent, where previously they were for a fixed period of four years.
2.4With the move to permanent arrangements, the arrangements are now subject to termination provisions, which are linked to the termination provisions in the model Shared Service Collaboration Agreement.
2.5The MKS Objectives and Strategic Priorities have been updated to more accurately reflect the current intentions of the Councils in operating shared services. The revised Objectives are to:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies