RESOLVED – 1. That progress in delivering the Cultural Hub be noted; 2. That a grant offer of £886,250 from Arts Council England towards the project costs be accepted; 3. That a grant offer of £4,294,900 from the Heritage Lottery Fund towards the project costs be accepted; 4. That delegated authority be granted to the Director of Change and Communities, in consultation with the Portfolio Holder for Culture, Leisure and Tourism, to sign any necessary agreements with Arts Council England, Heritage Lottery Fund and any other external funders; and 5. That delegated authority be granted to the Director Of Change and Communities, in consultation with the Portfolio Holder for Culture Leisure and Tourism, to authorise the completion of the Collaboration and Development Agreements, together with ancillary documents, with Kent County Council. REASON FOR DECISION: To enable the delivery of the project through external funding.
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
Cabinet 21 June 2018 Is the final decision on the recommendations in this report to be made at this meeting? Yes
Cultural Hub – Update and External Funding Final Decision-Maker Cabinet Portfolio Holder(s) Councillor Jane March, Portfolio Holder for Culture, Leisure and Tourism Lead Director Paul Taylor, Director of Change and Communities Head of Service Nicky Carter, Head of People, Culture and Customer Service Lead Officer/Author Nicky Carter, Head of People, Culture and Customer Service Classification Non-exempt Wards affected All
This report makes the following recommendations to the final decision-maker:
1. That progress in delivering the Cultural Hub be noted;
2. That a grant offer of £886,250 from Arts Council England towards the project costs be accepted;
3. That a grant offer of £4,294,900 from the Heritage Lottery Fund towards the project costs be accepted;
4. That delegated authority be granted to the Director of Change and Communities, in consultation with the Portfolio Holder, to sign any necessary agreements with Arts Council England, Heritage Lottery Fund and any other external funders; and
5. That delegated authority be granted to the Director Of Change and Communities, in consultation with the Portfolio Holder, to authorise the completion of the Collaboration and Development Agreements, together with ancillary documents, with Kent County Council.
This report relates to the following Five Year Plan Key Objectives: A Confident Borough – this project delivers a new cultural building, incorporating a range of enhanced services. Timetable Meeting Date Management Board 9 May 2018 Discussion with Portfolio Holder 19 April 2018 Communities Cabinet Advisory Board 30 May 2018 Cabinet 21 June 2018 Tunbridge Wells Committee Report, version: January 2018 Cultural Hub – Update and External Funding
1. PURPOSE OF REPORT AND EXECUTIVE SUMMARY
1.1Good progress has been made in delivering the proposed Cultural Hub - to be located where the present museum, library and adult education buildings are. This report updates Cabinet on that progress.
1.2It also confirms external funding secured for the project, and seeks formal acceptance of those funding offers.
2. INTRODUCTION AND BACKGROUND
2.1On 25 June 2015 Cabinet agreed to support and progress this project. Working with Kent County Council, the hub will bring together - in one organisation and one service - the museum, art gallery, library, adult education, tourist information and Gateway.
2.2The Cultural Hub will be rich with objects, with an inspirational programme to engage and inspire visitors. It is expected to become a vibrant centre of heritage, arts and culture - recognised nationally as a beacon for best practice and new ways of working - and will be an active place where people van develop skills and exchange ideas.
2.3A Project Board has been established, with both officer and Member representation of Tunbridge Wells and Kent County Councils. The Board is chaired by the Chief Executive of Tunbridge Wells Council.
2.4A team of architects and other professionals has been assembled, and plans developed with extensive public consultation.
2.5Planning permission was secured in January this year, and work on detailed design is currently underway.
2.6Funding has also been secured from Arts Council England, with a grant offer of £886,250 confirmed at the end of last year.
2.7The Heritage Lottery Fund have just confirmed an offer of £4,294,900 in funding, and are seeking formal acceptance of the offer from Cabinet. This report seeks that acceptance.
2.8Tendering for a build contractor will take place this year. It is anticipated that a contractor will be on site early in 2019, with completion two years later.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.