RESOLVED – 1. That the library and adult education buildings, together with all associated land, be purchased from Kent County Council for £400,000 plus Stamp Duty Land Tax (currently £137,000 in 2018); 2. That a capital and revenue contribution of £7,280,000 be agreed towards the costs of building the new hub (as agreed in June 2015), and that approval of the final sum subject to contract be delegated to the Chief Executive in consultation with the Leader of Council and the Portfolio Holder for Finance and Governance; 3. That all necessary legal agreements in order to deliver the hub be agreed; 4. That a fundraising target of £1.2m (inclusive of the cost of establishing the trust) be agreed; 5. That £200,000 of up front-funding be agreed to set up a fundraising trust; and 6. That the Director of Change and Communities be delegated authority, in consultation with the Portfolio Holder for Culture, Leisure and Tourism, to establish the trust. REASON FOR DECISION: To note an update on the capital build costs at the end of RIBA Stage 4 and set out a realistic fundraising target for the new building.
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
Cabinet 6 December 2018 Is the final decision on the recommendations in this report to be made at this meeting? Yes
Update on the Culture and Learning Hub: Costs and Funding Final Decision-Maker Cabinet Portfolio Holder(s) Councillor Jane March – Portfolio Holder for Culture, Leisure and Tourism Lead Director Paul Taylor – Director of Change and Communities Head of Service Nicky Carter – Head of HR, Customer Service and Culture Lead Officer/Author Paul Taylor – Director of Change and Communities Classification Non-Exempt Wards affected All
This report makes the following recommendations to the final decision-maker:
1. To agree that the library and adult education buildings, together with all associated land, be purchased from Kent County Council for £400,000 plus Stamp Duty Land Tax (currently £137,000 in 2018);
2. That a capital and revenue contribution of £7,280,000 be agreed towards the costs of building the new hub (as agreed in June 2015), and that approval of the final sum subject to contract be delegated to the Chief Executive in consultation with the Leader of Council and the Portfolio-holder for Finance and Governance;
3. To agree to enter into all necessary legal agreements in order to deliver the hub;
4. To agree a fundraising target of £1.2m (inclusive of the cost of establishing the trust);
5. To agree £200,000 of up front-funding to set up a fundraising trust; and
6. To give delegated authority to the Director of Change and Communities, in consultation with the Portfolio Holder for Culture, Leisure and Tourism, to establish the trust. Explain how this report relates to the Corporate Priorities in the Five Year Plan: A Confident Borough – this project delivers a new cultural building, incorporating a range enhanced services. The Cultural and Learning Hub is also a key project set out in the Five Year Plan and the Cultural Strategy.
Timetable Meeting Date Management Board 24 October 2018 Discussion with Portfolio Holder Communities Cabinet Advisory Board 14 November 2018 Cabinet 6 December 2018 Tunbridge Wells Committee Report, version: May 2018 Update on the Culture and Learning Hub: Costs and Funding
1. PURPOSE OF REPORT AND EXECUTIVE SUMMARY
1.1The report provides an update for members on the capital build costs at the end of RIBA stage 4. It also sets out a realistic fundraising target for the new building and seeks approval to front-fund the establishment of a fundraising trust in order to secure £1.2m external funding.
2. INTRODUCTION AND BACKGROUND
2.1In 2015 Cabinet agreed to support a joint project with Kent County Council to establish the Cultural and Learning Hub (likely to be named the Amelia Scott) bringing together in one integrated space, the museum, art gallery, library, adult education, tourist information and Gateway. The vision for the new hub was to become a vibrant centre for heritage, arts, culture and learning, delivering a diverse programme to engage and inspire visitors.
2.2At its meeting of 21 June 2018, Cabinet received an update on progress noting that detailed designs (RIBA stage 4) were underway and a further report setting out the current costings would be brought back to Cabinet. The project is overseen and managed by a Culture and Learning Hub Board comprising cabinet members and senior officers from KCC and TWBC who receive regular reports on the programme and its constituent projects, costs and timelines for delivery.
2.3Planning permission along with listed planning consent for the scheme was granted in January 2018.
2.4Confirmation from ACE confirming their stage two investment was received in December 2017 and HLF confirmed their round two investment in March 2018 with permission to start being given in October 2018.
2.5Kent County Council and TWBC signed the Collaboration Agreement in September 2018 setting out how the delivery phase will be undertaken.
3. PROJECT FUNDING
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies