RESOLVED – 1. That the actual gross and net expenditure for the year and the sources of finance, as shown at Appendices B to D to the report, be noted; 2. That the proposed variations to the 2018/19 Capital programme set out in paragraphs 4.3 to 4.4 of the report be approved; and 3. That the inclusion of a new scheme into the capital programme as set out in paragraph 4.5 of the report be noted. REASON FOR DECISION: Managing and forecasting capital expenditure effectively was vital in order to support all of the services provided by the Council.
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
Cabinet 6 December 2018 Is the final decision on the recommendations in this report to be made at this meeting? Yes
Capital Management Report: Quarter 2 (to 30 September 2018) Final Decision-Maker Cabinet Portfolio Holder(s) Councillor David Reilly – Portfolio Holder for Finance and Governance Lead Director Lee Colyer – Director of Finance, Policy and Development Head of Service Jane Fineman – Head of Finance and Procurement Lead Officer/Author Deborah Hazell – Service Accountant Classification Non-exempt Wards affected All
This report makes the following recommendations to the final decision-maker: 1. That the actual gross and net expenditure for the year and the sources of finance as shown in Appendices B to D to the report be noted;
2. That the proposed variations to the 2018/19 Capital programme set out in paragraphs 4.3 to 4.4 of the report be approved; and
3. That the inclusion of a new scheme into the capital programme as set out in paragraph 4.5 of the report be noted.
This report relates to the following Five Year Plan Key Objectives: This report supports all of the Key Objectives. Managing and forecasting capital expenditure effectively is vital in order to support all of the services provided by the Council.
Timetable Meeting Date Management Board 24 October 2018 (Verbal Update) Discussion with Portfolio Holder 13 November 2018 Cabinet Advisory Board 13 November 2018 (Verbal Update) Cabinet 6 December 2018 Tunbridge Wells Committee Report, version: April 2017 Capital Management Report: Quarter 2 (to 30 September 2018)
1. PURPOSE OF REPORT AND EXECUTIVE SUMMARY
1.1This report summarises the actual and forecast outturn expenditure on capital schemes as at the 30 September 2018. The total capital expenditure is forecast to be £19,279,000, a net increase of £404,000 from the previously approved budgets.
2. INTRODUCTION AND BACKGROUND
2.1At their meeting on 1 March 2018, Cabinet approved schemes to be met from the Capital Programme for the years 2018/19 to 2020/21.
2.2The figures approved by Cabinet were on the basis of the net cost after specific funding to be met by the Council, either from reserves or from the sale of existing assets. The total approved spending was £71,905,000 during that period, of which £7,363,000 was to be spent during 2018/19.
2.3As the Capital Programme is a 4 year rolling plan an additional £914,000 has now been approved. This consists of Disabled Facilities Grants, Housing Renewal advances, and IT Strategy. A further £35,000,000 was agreed at Full Council 6 December 2017 for the Calverley Square project TIJ (FC50/17)
2.4As shown in Appendix A, the approved programme for 2018/19 moved to £12,096,000 by the end of the 2017/18 financial year, accounting for new schemes, deletions and deferrals into future years and was approved by CAB71/18 on 21 June 2018.
2.5New movements for 2018/19 are now forecasting an outturn of £19,279,000.
2.6Appendices B and C set out in gross and net terms the actual spend and amounts approved against the forecast outturn to 31 March 2019, whilst Appendix D summarises the movement in approvals and in sources of finance for the year.
2.7Approval is sought for a net increase in the capital programme of £404,000 (see notes 4.3 to 4.5).
3. AVAILABLE OPTIONS
3.1Retain the approved rolling capital programme as at the end of Quarter 1. This would not reflect delays, advancements, underspends or new schemes and therefore provide an inaccurate forecast to the end of the financial year. 3.2 Amend the rolling capital programme to reflect changes since the end of Quarter 1. These projections help to manage the public finances effectively which support the objectives and priorities of the Council.
4. PREFERRED OPTION AND REASONS FOR RECOMMENDATIONS
New Budget Approvals
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.