Resolved
RESOLVED – The Audit and Governance Committee notes the risk management report and arrangements for managing strategic risk and recommends the same to Finance and Governance Cabinet Advisory Board and Cabinet.
Audit and Governance Committee decided this item on Tuesday 2 July 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – The Audit and Governance Committee notes the risk management report and arrangements for managing strategic risk and recommends the same to Finance and Governance Cabinet Advisory Board and Cabinet.
Audit and Governance 2 July 2019 Committee Is the final decision on the recommendations in this report to be made at this meeting? No
Strategic Risk Review * Final Decision-Maker Audit and Governance Committee Portfolio Holder(s) All Lead Director Lee Colyer – Director of Finance, Policy and Development Head of Service Rich Clarke – Head of Audit Partnership Lead Officer/Report Author Lee Colyer – Director of Finance, Policy and Development Classification Non-Exempt Wards affected All
This report makes the following recommendations to the final decision-maker:
1. That the Committee notes the risk management report and arrangements for managing strategic risk and recommends the same to Finance and Governance Cabinet Advisory Board and Cabinet for noting.
This report relates to the following Five Year Plan Key Objectives: A Prosperous Borough A Green Borough A Confident Borough
This report is concerned with the internal control and governance of the Council. Successful controls and effective governance are a crucial underpinning for all corporate priorities.
Timetable Meeting Date Management Board 8 May 2019 Audit and Governance Committee 2 July 2019 Finance and Governance Cabinet Advisory Board 11 July 2019 Cabinet 1 August 2019 Strategic Risk Review
1. PURPOSE OF REPORT AND EXECUTIVE SUMMARY
1.1The report sets out the proposed strategic risks identified by the Council. The report provides a current update on the evaluated threat level and controls in place for each risk issue.
2. INTRODUCTION AND BACKGROUND
2.1The risks included in the report have been developed following a risk management workshop and health check facilitated by Zurich Insurance Limited on 25 March 2019. The report from Zurich is included as Appendix A and summaries the process, outcomes and next steps. The Audit & Governance Committee has the opportunity to comment on the new strategic risks prior to Cabinet formally adopting the strategic risk register on 1 August 2019.
2.2The review identified the following strategic risks which can be removed:
Previous CSR 01 - Cinema Site remains undeveloped. This site in now in the ownership of a housing developer who has the funding and commitment to deliver the scheme. Previous CSR 03 – Resident engagement. The Council received a follow-up report from the Local Government Association which found that there had been clear improvements in the Council’s approach to communication and that there was a good flow of information to the public. Previous CSR 09 – Development Programme. A well rehearsed process has enabled the successful development and disposal of sites.
2.3The review identified the following new strategic risks:
New CSR01 - Cyber attack/ incident. This was previously covered under service interruption but now warrants a separate risk due to the sophistication and impact of cyber risks compared to traditional physical causes of service interruption. New CSR03 – Contract management and delivery. The Council has recently awarded a new waste contract and will shortly be starting the procurement process for grounds maintenance. New CSR09 – The Culture & Learning Hub. This is a £13 million construction project involving multiple service providers.
2.4The Council’s Management Board periodically reviews the risks identified along with the risk owners.
2.5Once the strategic risk register has been adopted risk owners (managers) for certain risks will be invited to attend future Audit and Governance Committee meetings to outline the Council’s approach to managing their particular risk(s). 3. AVAILABLE OPTIONS
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
12 Appendix A Strategic Risk Refresh Report April 2019 /19Appendix | 181 KB | Download |
PDF |
12 Appendix B Strategic Risks June 2019 /19Appendix | 288 KB | Download |
PDF |
Strategic Risk ReviewReport | 112 KB | DownloadRead as text |
Follow Audit and Governance Committee at Tunbridge Wells and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Jul 2026 | Minutes of the meeting of the Audit and Governance Committee dated 10 March 2026RESOLVED – That the minutes of the meeting dated 10 March 2026 be approved as a correct record. | Approved | Open |
| 2 Jul 2026 | Future Work Programme as at 2 July 2026RESOLVED – That the Future Work Programme as at 2 July 2026, be noted. | Noted | Open |
| 2 Jul 2026 | External Audit Progress and Sector Update ReportRESOLVED - That the committee consider and agree the Audit Progress and Sector Update Report. | Agreed | Open |
| 2 Jul 2026 | Internal Audit Report & Annual Audit Opinion 2025/26RESOLVED – 1. That the Audit & Governance Committee notes the Head of Audit Partnership opinion. 2. That the Audit & ... | Decided | Open |
| 10 Mar 2026 | Minutes of the meeting of the Audit and Governance Committee dated 25 November 2025RESOLVED – That the minutes of the meeting dated 25 November 2026 be approved as a correct record. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.