RESOLVED – 1. That the motions passed by Full Council be noted; 2. That the proposed response to the Full Council resolutions as set out in the report, in particular paragraphs 3 and 4 of the report, be agreed; and 3. That a report concerning the completion of RIBA Stage 4 be added to the Forward Plan for Cabinet on 12 September 2019 to include briefings and a meeting of the Development Advisory Panel from week commencing 19 August 2019 and consideration by a special meeting of the Cabinet Advisory Boards during week commencing 02 September 2019. REASON FOR DECISION: To comply with the Council’s request for an orderly consideration of alternatives and to enable Full Council to take a role in the final decision.
Word for word from the decision Tunbridge Wells published for this meeting.Source: democracy.tunbridgewells.gov.uk
Cabinet 01 August 2019 Is the final decision on the recommendations in this report to be made at this meeting? Yes
Calverley Square – Council Motions Final Decision-Maker Cabinet Portfolio Holder(s) Councillor Alan McDermott – Leader of the Council Lead Director Lee Colyer – Director of Finance, Policy and Development Head of Service David Candlin – Head of Economic Development and Property Lead Officer/Author David Candlin – Head of Economic Development and Property Classification Non-Exempt Wards affected All
This report makes the following recommendations to the final decision-maker:
1. That the motions passed by Full Council be noted; and
2. That the proposed response to the Full Council resolutions set out in the report, in particular paragraphs 3 and 4 of the report, be agreed.
A Prosperous Borough A Green Borough A Confident Borough
The proposals within the Calverley Square Development support delivery of the Council’s Five Year Plan through development of a new enhanced theatre, the provision of new office space and a new car park, and improvements to the entrance setting to Calverley Grounds, whilst protecting the historic integrity of the listed civic suite of buildings.
Timetable Meeting Date Discussion with Portfolio Holder 18 July 2019 Cabinet 01 August 2019 Calverley Square – Council Motions
1. PURPOSE OF REPORT AND EXECUTIVE SUMMARY
1.1On 17 June, at an Extraordinary Council Meeting, Full Council agreed two motions relating to the Calverley Square project as set out in the report. In addition a third motion was agreed by Full Council on 17 July 2019. This report sets out Cabinet’s response to these three requests.
2. INTRODUCTION AND BACKGROUND
2.1Calverley Square was given approval by Full Council on the 6 December 2017. The decisions delegated all aspects to Cabinet or to officers in consultation with Portfolio Holders. Since approval in December 2017 work has progressed with a planning application being submitted and approved, and site assembly has also continued with a Compulsory Purchase Order (CPO) having been made by the Council. The Inspector appointed by the Secretary of State at a public inquiry in February/March 2019 approved confirmation of the CPO having considered objections and representations in support of the project. The CPO was confirmed on 10 May 2019. Progress has also continued in developing the technical design of the development and the appointment of the construction contractor.
2.2On 17 June, at an Extraordinary Council Meeting, Full Council agreed two motions relating to the Calverley Square project as follows:
Cabinet be requested to stop all new expenditure on the Calverley Square project with immediate effect and to not enter into further commitments other than, with the involvement of all political parties and other relevant stakeholder groups, to manage an orderly consideration of all alternative proposals.
Cabinet is requested to require Full Council to decide whether it wishes to proceed to RIBA Stage 5 (the construction stage of Calverley Square).
2.3On the 17 July Full Council agreed the following motion:
Cabinet be requested to stop all new expenditure on the Calverley Square project with immediate effect and to not enter into further commitments other than, with the involvement of all political parties acting in good faith and other relevant stakeholder groups, to manage an orderly consideration of all alternative proposals. Cabinet is also requested to confirm that all new spending from all budgets and reserves on Calverley Square is stopped. Cabinet will instruct staff for a comprehensive update on Calverley Square commitments and penalties.
2.4This report sets out Cabinet’s response to these three requests. 3 EXPENDITURE
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Management Report Quarter 1RESOLVED – 1. That the actual gross expenditure and that net of revenue for the year and the sources of finance, as s...
Revenue Management Report Quarter 1RESOLVED – 1. That the Quarter 1 net expenditure on services to the end of June 2026 was £5,414,000, £102,000 less th...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.